Planning Application made under Section 73 of the Town and Country Planning Act 1990 (as amended) to vary condition 3 of planning permission reference 10/000032/CM (as amended) to increase the throughput of the EnviRecover Energy from Waste Facility from 200,000 to 230,000 tonnes per annum

Mercia EnviRecover, Plot H600, Oak Drive, Hartlebury Trading Estate, DY10 4JB

PermittedReference: 18/000057/CMWorcestershire County Council

Last published check: 14 Sept 2026, 23:51. Check the council record for more recent changes.

Application location

Mercia EnviRecover, Plot H600, Oak Drive, Hartlebury Trading Estate, DY10 4JB

This record has no verified map location.

Application summary

Status
Permitted
Application type
County Matter
Received
23 Nov 2018
Validated
29 Nov 2018
Determination deadline
Not published
Local authority
Worcestershire County Council

Application overview

Planning Application made under Section 73 of the Town and Country Planning Act 1990 (as amended) to vary condition 3 of planning permission reference 10/000032/CM (as amended) to increase the throughput of the EnviRecover Energy from Waste Facility from 200,000 to 230,000 tonnes per annum

Proposal details

Reference
18/000057/CM
Parish
Chaddesley Corbett, Elmbridge, Elmley Lovett, Westwood
Agent
Nick Roberts, AXIS PED

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 96 of 96

DocumentPublishedAction
42 Old Application - Vol 1 - Figure 11.1 - Surface Water Drainage42_Old_Application_-_Vol_1_-_Figure_11.1_-_Surface_Water_Drainage.pdfNot publishedView
41 Old Application - Vol 1 - Figure 9.1 - Habitat Map41_Old_Application_-_Vol_1_-_Figure_9.1_-_Habitat_Map.pdfNot publishedView
40 Old Application - Vol 1 - Figure 8.3n Representative Viewpoints Sheet 1440_Old_Application_-_Vol_1_-_Figure_8.3n_Representative_Viewpoints_Sheet_14.pdfNot publishedView
39 Old Application - Vol 1 - Figure 8.3m Representative Viewpoints Sheet 1339_Old_Application_-_Vol_1_-_Figure_8.3m_Representative_Viewpoints_Sheet_13.pdfNot publishedView
38 Old Application - Vol 1 - Figure 8.3l Representative Viewpoints Sheet 1238_Old_Application_-_Vol_1_-_Figure_8.3l_Representative_Viewpoints_Sheet_12.pdfNot publishedView
37 Old Application - Vol 1 - Figure 8.3k Representative Viewpoints Sheet 1137_Old_Application_-_Vol_1_-_Figure_8.3k_Representative_Viewpoints_Sheet_11.pdfNot publishedView
36 Old Application - Vol 1 - Figure 8.3j Representative Viewpoints Sheet 1036_Old_Application_-_Vol_1_-_Figure_8.3j_Representative_Viewpoints_Sheet_10.pdfNot publishedView
35 Old Application - Vol 1 - Figure 8.3i Representative Viewpoints Sheet 935_Old_Application_-_Vol_1_-_Figure_8.3i_Representative_Viewpoints_Sheet_9.pdfNot publishedView
34 Old Application - Vol 1 - Figure 8.3h Representative Viewpoints Sheet 834_Old_Application_-_Vol_1_-_Figure_8.3h_Representative_Viewpoints_Sheet_8.pdfNot publishedView
33 Old Application - Vol 1 - Figure 8.3g Representative Viewpoints Sheet 733_Old_Application_-_Vol_1_-_Figure_8.3g_Representative_Viewpoints_Sheet_7.pdfNot publishedView
32 Old Application - Vol 1 - Figure 8.3f Representative Viewpoints Sheet 632_Old_Application_-_Vol_1_-_Figure_8.3f_Representative_Viewpoints_Sheet_6.pdfNot publishedView
31 Old Application - Vol 1 - Figure 8.3e Representative Viewpoints Sheet 531_Old_Application_-_Vol_1_-_Figure_8.3e_Representative_Viewpoints_Sheet_5.pdfNot publishedView
30 Old Application - Vol 1 - Figure 8.3d Representative Viewpoints Sheet 430_Old_Application_-_Vol_1_-_Figure_8.3d_Representative_Viewpoints_Sheet_4.pdfNot publishedView
29 Old Application - Vol 1 - Figure 8.3c Representative Viewpoints Sheet 329_Old_Application_-_Vol_1_-_Figure_8.3c_Representative_Viewpoints_Sheet_3.pdfNot publishedView
28 Old Application - Vol 1 - Figure 8.3b Representative Viewpoints Sheet 228_Old_Application_-_Vol_1_-_Figure_8.3b_Representative_Viewpoints_Sheet_2.pdfNot publishedView
27 Old Application - Vol 1 - Figure 8.3a Representative Viewpoints Sheet 127_Old_Application_-_Vol_1_-_Figure_8.3a_Representative_Viewpoints_Sheet_1.pdfNot publishedView
26 Old Application - Vol 1 - Figure 8.2 - Viewpoint Locations26_Old_Application_-_Vol_1_-_Figure_8.2_-_Viewpoint_Locations.pdfNot publishedView
25 Old Application - Vol 1 - Figure 8.1 - Landscape Assessment Study Area25_Old_Application_-_Vol_1_-_Figure_8.1_-_Landscape_Assessment_Study_Area.pdfNot publishedView
24 Old Application - Vol 1 - Figure 5.12 - Indicative Construction Phase Arrangements24_Old_Application_-_Vol_1_-_Figure_5.12_-_Indicative_Construction_Phase_Arrangements.pdfNot publishedView
23 Old Application - Vol 1 - Figure 5.11 - Energy from Waste Process Diagram23_Old_Application_-_Vol_1_-_Figure_5.11_-_Energy_from_Waste_Process_Diagram.pdfNot publishedView
22 Old Application - Vol 1 - Figure 5.10 - Landscape Proposals22_Old_Application_-_Vol_1_-_Figure_5.10_-_Landscape_Proposals.pdfNot publishedView
21 Old Application - Vol 1 - Figure 5.9 - 3D Representations21_Old_Application_-_Vol_1_-_Figure_5.9_-_3D_Representations.pdfNot publishedView
20 Old Application - Vol 1 - Figure 5.8 - Proposed Plan & Elevations - Weighbridge20_Old_Application_-_Vol_1_-_Figure_5.8_-_Proposed_Plan_&_Elevations_-_Weighbridge.pdfNot publishedView
19 Old Application - Vol 1 - Figure 5.7 - Proposed Elevations - Turbine Complex19_Old_Application_-_Vol_1_-_Figure_5.7_-_Proposed_Elevations_-_Turbine_Complex.pdfNot publishedView
18 Old Application - Vol 1 - Figure 5.6 - Proposed West Elevation - Main Building18_Old_Application_-_Vol_1_-_Figure_5.6_-_Proposed_West_Elevation_-_Main_Building.pdfNot publishedView
17 Old Application - Vol 1 - Figure 5.5 - Proposed South Elevation - Main Building17_Old_Application_-_Vol_1_-_Figure_5.5_-_Proposed_South_Elevation_-_Main_Building.pdfNot publishedView
16 Old Application - Vol 1 - Figure 5.4 - Proposed East Elevation - Main Building16_Old_Application_-_Vol_1_-_Figure_5.4_-_Proposed_East_Elevation_-_Main_Building.pdfNot publishedView
15 Old application - Vol 1 - Figure 5.3 Proposed North Elevation - Main Building15_Old_application_-_Vol_1_-_Figure_5.3_Proposed_North_Elevation_-_Main_Building.pdfNot publishedView
14 Old application - Vol 1 - Figure 5.2 Proposed Site Cross Sections14_Old_application_-_Vol_1_-_Figure_5.2_Proposed_Site_Cross_Sections.pdfNot publishedView
13 Old application - Vol 1 - Figure 5.1 Proposed Site Layout13_Old_application_-_Vol_1_-_Figure_5.1_Proposed_Site_Layout.pdfNot publishedView
12 Old application - Vol 1 - Figure 1.1 Site Location Plan12_Old_application_-_Vol_1_-_Figure_1.1_Site_Location_Plan.pdfNot publishedView
11 Old application - Vol 1 - ES Main Report11_Old_application_-_Vol_1_-_ES_Main_Report.pdfNot publishedView
10 New application - 2295-01-01 Statutory Plan10_New_application_-_2295-01-01_Statutory_Plan.pdfNot publishedView
09 New application - Appendix 4.2 Human Health Risk Assessment09_New_application_-_Appendix_4.2_Human_Health_Risk_Assessment.pdfNot publishedView
08 New application - Appendix 4.1 Dispersion Modelling Assessment08_New_application_-_Appendix_4.1_Dispersion_Modelling_Assessment.pdfNot publishedView
07 New application - Appendix 3.1 Transport Statement07_New_application_-_Appendix_3.1_Transport_Statement.pdfNot publishedView
06 New application - Figure 1.1 Site Location Plan06_New_application_-_Figure_1.1_Site_Location_Plan.pdfNot publishedView
05 New application - ES Addendum Vol 2 Non-Technical Summary05_New_application_-_ES_Addendum_Vol_2_Non-Technical_Summary.pdfNot publishedView
04 New application - ES Addendum Vol 1 Main Report04_New_application_-_ES_Addendum_Vol_1_Main_Report.pdfNot publishedView
03 New application - Planning Statement03_New_application_-_Planning_Statement.pdfNot publishedView
02 New application - ApplicationFormNoPersonalData02_New_application_-_ApplicationFormNoPersonalData.pdfNot publishedView
01 New application - Covering Letter01_New_application_-_Covering_Letter.pdfNot publishedView
92 Committee Minutes - Item 5 - Dated 26th March 201992_Committee_Minutes_-_Item_5_-_Dated_26th_March_2019.pdfNot publishedView
91 Public Notice to go into Press - Kidderminster Shuttle - Dated 4th April 201991_Public_Notice_to_go_into_Press_-_Kidderminster_Shuttle_-_Dated_4th_April_2019.pdfNot publishedView
90 Public Notice to go into Press - Droitwich Advertiser - Dated 3rd April 201990_Public_Notice_to_go_into_Press_-_Droitwich_Advertiser_-_Dated_3rd_April_2019.pdfNot publishedView
89 Committee Report - Item 5 - Dated 26th March 201989_Committee_Report_-_Item_5_-_Dated_26th_March_2019.pdfNot publishedView
88 Decision Notice - Dated 26th March 201988_Decision_Notice_-_Dated_26th_March_2019.pdfNot publishedView
87 Public Notice - Dated 19th December 201887_Public_Notice_-_Dated_19th_December_2018.pdfNot publishedView
86 Old Application - Regulation 19 Submission No.3b - Great Crested Newt Impact Assessment86_Old_Application_-_Regulation_19_Submission_No.3b_-_Great_Crested_Newt_Impact_Assessment.pdfNot publishedView
85 Old Application - Regulation 19 Submission No.3a - Heat Off-take Connection85_Old_Application_-_Regulation_19_Submission_No.3a_-_Heat_Off-take_Connection.pdfNot publishedView
84 Old Application - Regulation 19 Submission No.2b - Grid Connection84_Old_Application_-_Regulation_19_Submission_No.2b_-_Grid_Connection.pdfNot publishedView
83 Old Application - Regulation 19 Submission No.2a - Revised Non-Technical Summary83_Old_Application_-_Regulation_19_Submission_No.2a_-_Revised_Non-Technical_Summary.pdfNot publishedView
82 Old Application - Regulation 19 Submission No.1 - Protected Species Clarification82_Old_Application_-_Regulation_19_Submission_No.1_-_Protected_Species_Clarification.pdfNot publishedView
81e Old Application - Vol 3 - NTS Figure 4 - Energy from Waste Process Diagram81e_Old_Application_-_Vol_3_-_NTS_Figure_4_-_Energy_from_Waste_Process_Diagram.pdfNot publishedView
81d Old Application - Vol 3 - NTS Figure 3 - 3D Representations81d_Old_Application_-_Vol_3_-_NTS_Figure_3_-_3D_Representations.pdfNot publishedView
81c Old Application - Vol 3 - NTS Figure 2 - Proposed Site Layout81c_Old_Application_-_Vol_3_-_NTS_Figure_2_-_Proposed_Site_Layout.pdfNot publishedView
81b Old Application - Vol 3 - NTS Figure 1 - Site Location Plan81b_Old_Application_-_Vol_3_-_NTS_Figure_1_-_Site_Location_Plan.pdfNot publishedView
81a Old Application - Vol 3 - Non-Technical Summary81a_Old_Application_-_Vol_3_-_Non-Technical_Summary.pdfNot publishedView
80 Old Application - Vol 2 - Chapter 15.0 - Appendix 15.1 HER_Summary80_Old_Application_-_Vol_2_-_Chapter_15.0_-_Appendix_15.1_HER_Summary.pdfNot publishedView
79 Old Application - Vol 2 - Chapter 14.0 - Appendix 14.1 AgricRpt-Rev01A79_Old_Application_-_Vol_2_-_Chapter_14.0_-_Appendix_14.1_AgricRpt-Rev01A.pdfNot publishedView
78 Old Application - Vol 2 - Chapter 13.0 - Appendix 13.1 Air Quality Report78_Old_Application_-_Vol_2_-_Chapter_13.0_-_Appendix_13.1_Air_Quality_Report.pdfNot publishedView
77 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.11 noise mapping77_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.11_noise_mapping.pdfNot publishedView
76 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.10 Construction plant76_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.10_Construction_plant.pdfNot publishedView
75 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.9 vibration monitoring75_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.9_vibration_monitoring.pdfNot publishedView
74 Old Applicaton - Vol 2 - Chapter 12.0 - Appendix 12.8 vibration terminology74_Old_Applicaton_-_Vol_2_-_Chapter_12.0_-_Appendix_12.8_vibration_terminology.pdfNot publishedView
73 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.7 Background noise results73_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.7_Background_noise_results.pdfNot publishedView
72 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.6 Noise survey details72_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.6_Noise_survey_details.pdfNot publishedView
71 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.5 Experience71_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.5_Experience.pdfNot publishedView
70 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.4 Low freq noise criteria70_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.4_Low_freq_noise_criteria.pdfNot publishedView
69 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.3 Existing EFW survey results69_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.3_Existing_EFW_survey_results.pdfNot publishedView
68 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.2 Source noise levels68_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.2_Source_noise_levels.pdfNot publishedView
67 Old Application - Vol 2 - Chapter 12.0 - Appendix 12.1 Basic Acoustic Terminology67_Old_Application_-_Vol_2_-_Chapter_12.0_-_Appendix_12.1_Basic_Acoustic_Terminology.pdfNot publishedView
66 Old Application - Vol 2 - Chapter 11.0 - Appendix 11.1 Micro Drainage Calculations66_Old_Application_-_Vol_2_-_Chapter_11.0_-_Appendix_11.1_Micro_Drainage_Calculations.pdfNot publishedView
65 Old Application - Vol 2 - Chapter 10.0 - Appendix 10.2 Contaminated Land Report65_Old_Application_-_Vol_2_-_Chapter_10.0_-_Appendix_10.2_Contaminated_Land_Report.pdfNot publishedView
64 Old Application - Vol 2 - Chapter 10.0 - Appendix 10.1-Appendix D Nat Soil Report64_Old_Application_-_Vol_2_-_Chapter_10.0_-_Appendix_10.1-Appendix_D_Nat_Soil_Report.pdfNot publishedView
63 Old Application - Vol 2 - Chapter 10.0 - Appendix 10.1-Appendix C Envirocheck Maps63_Old_Application_-_Vol_2_-_Chapter_10.0_-_Appendix_10.1-Appendix_C_Envirocheck_Maps.pdfNot publishedView
62 Old Application - Vol 2 - Chapter 10.0 - Appendix 10.1-Appendix B Envirocheck Datasheets62_Old_Application_-_Vol_2_-_Chapter_10.0_-_Appendix_10.1-Appendix_B_Envirocheck_Datasheets.pdfNot publishedView
61 Old Application - Vol 2 - Chapter 10.0 - Appendix 10.1 Desk Study Report61_Old_Application_-_Vol_2_-_Chapter_10.0_-_Appendix_10.1_Desk_Study_Report.pdfNot publishedView
60 Old Application - Vol 2 - Chapter 9.0 - Appendix 9.3 Bird Survey Results60_Old_Application_-_Vol_2_-_Chapter_9.0_-_Appendix_9.3_Bird_Survey_Results.PDFNot publishedView
59 Old Application - Vol 2 - Chapter 9.0 - Appendix 9.2 Hartlebury Bat Activity Survey59_Old_Application_-_Vol_2_-_Chapter_9.0_-_Appendix_9.2_Hartlebury_Bat_Activity_Survey.pdfNot publishedView
58 Old Application - Vol 2 - Chapter 9.0 - Appendix 9.1 - habitat target notes58_Old_Application_-_Vol_2_-_Chapter_9.0_-_Appendix_9.1_-_habitat_target_notes.pdfNot publishedView
57 Old Application - Vol 2 - Chapter 8.0 - Appendix 8.2 Schedule of Visual Effects.rev157_Old_Application_-_Vol_2_-_Chapter_8.0_-_Appendix_8.2_Schedule_of_Visual_Effects.rev1.pdfNot publishedView
56 Old Application - Vol 2 - Chapter 8.0 - Appendix 8.1 LVIA Methodology.rev156_Old_Application_-_Vol_2_-_Chapter_8.0_-_Appendix_8.1__LVIA_Methodology.rev1.pdfNot publishedView
55 Old Application - Vol 2 - Chapter 5.0 - Appendix 5.5 Letter from Wienerberger55_Old_Application_-_Vol_2_-_Chapter_5.0_-_Appendix_5.5_Letter_from_Wienerberger.pdfNot publishedView
54 Old Application - Vol 2 - Chapter 5.0 - Appendix 5.4 Outline Construction Programme54_Old_Application_-_Vol_2_-_Chapter_5.0_-_Appendix_5.4_Outline_Construction_Programme.pdfNot publishedView
53 Old Application - Vol 2 - Chapter 5.0 - Appendix 5.3 Grid Connection Study53_Old_Application_-_Vol_2_-_Chapter_5.0_-_Appendix_5.3_Grid_Connection_Study.PDFNot publishedView
52 Old Application - Vol 2 - Chapter 5.0 - Appendix 5.2 IBA Letters of Support52_Old_Application_-_Vol_2_-_Chapter_5.0_-_Appendix_5.2_IBA_Letters_of_Support.pdfNot publishedView
51 Old Application - Vol 2 - Chapter 5.0 - Appendix 5.1 Utilities report220210151_Old_Application_-_Vol_2_-_Chapter_5.0_-_Appendix_5.1_Utilities_report2202101.pdfNot publishedView
50 Old Application - Vol 2 - Chapter 3.0 - Appendix 3.1 waste treatment options appraisal50_Old_Application_-_Vol_2_-_Chapter_3.0_-_Appendix_3.1_waste_treatment_options_appraisal.pdfNot publishedView
49 Old Application - Vol 2 - Chapter 2.0 - Appendix 2.2 Scoping Response49_Old_Application_-_Vol_2_-_Chapter_2.0_-_Appendix_2.2_Scoping_Response.pdfNot publishedView
48 Old Application - Vol 2 - Chapter 2.0 - Appendix 2.1 Scoping Report - Rev A - FINAL48_Old_Application_-_Vol_2_-_Chapter_2.0_-_Appendix_2.1_Scoping_Report_-_Rev_A_-_FINAL.pdfNot publishedView
47 Old Application - Vol 1 - Figure 16.1 - Cumulative Effects Assessment Plan47_Old_Application_-_Vol_1_-_Figure_16.1_-_Cumulative_Effects_Assessment_Plan.pdfNot publishedView
46 Old Application - Vol 1 - Figure 15.1 - Location of Cultural Heritage46_Old_Application_-_Vol_1_-_Figure_15.1_-_Location_of_Cultural_Heritage.pdfNot publishedView
45 Old Application - Vol 1 - Figure 13.2 Stack Emissions45_Old_Application_-_Vol_1_-_Figure_13.2_Stack_Emissions.PDFNot publishedView
44 Old Application - Vol 1 - Figure 13.1 - Sensitive Receptors44_Old_Application_-_Vol_1_-_Figure_13.1_-_Sensitive_Receptors.pdfNot publishedView
43 Old Application - Vol 1 - Figure 12.1 - Noise Monitoring Positions43_Old_Application_-_Vol_1_-_Figure_12.1_-_Noise_Monitoring_Positions.pdfNot publishedView

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Valid Date

    Published milestoneCouncil source
  3. Consultation Start Date

    Published milestoneCouncil source
  4. Site Visited / Site Notice Date

    Published milestoneCouncil source
  5. Consultation End

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Decision Date

    Published milestoneCouncil source

Decision & conditions

Permitted
88 Decision Notice - Dated 26th March 2019
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.