Council planning record

DNS/3216558 - Wentlooge - Renewable Energy Hub

Land on the Wentlooge Levels to the West of Hawse Lane ; Tir ar Wastadeddau Gwynllwg i’r Gorllewin o Hawse Lane

Problem SolvedReference: CAS-01265-G8M4F9Welsh Ministers

Application location

Land on the Wentlooge Levels to the West of Hawse Lane ; Tir ar Wastadeddau Gwynllwg i’r Gorllewin o Hawse Lane

Location point supplied by the council.

Application summary

Status
Problem Solved
Application type
Developments of National Significance
Received
6 May 2020
Validated
16 Jul 2020
Determination deadline
Not published
Local authority
Welsh Ministers

Application overview

Erection of a Renewable Energy Hub comprising ground mounted solar panels, battery storage units (160 units) with a combined installed generating capacity of up to 125MW, underground cabling, grid connection hub, associated infrastructure, landscaping and environmental enhancements for a temporary period of 40 years ; Codi Hwb Ynni Adnewyddadwy sy’n cynnwys paneli solar wedi’u gosod ar y ddaear, unedau storio batris (160 o unedau) â chapasiti cynhyrchu gosodedig cyfunol o hyd at 125MW, ceblau tanddaear, hwb cysylltu â’r grid, seilwaith cysylltiedig, tirweddu a gwelliannau amgylcheddol am gyfnod dros dro o 40 mlynedd

Proposal details

Reference
CAS-01265-G8M4F9

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 2 of 2

DocumentPublishedAction
2021-03-26 - Inspector's Report.pdfFinal Decision/Report11 Oct 2021View
2021-09-21 - Decision Letter.pdfFinal Decision/Report22 Oct 2021View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Written acceptance of notice

    Published milestoneCouncil source
  2. Application submitted

    Published milestoneCouncil source
  3. Application accepted as valid

    Published milestoneCouncil source
  4. Representation period ends

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Deadline for application submission

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Report due

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Inspector report submitted to Welsh Government

    Published milestoneCouncil source
  8. Suspension starts

    Published milestoneCouncil source
  9. Decision made

    Published milestoneCouncil source
  10. Suspension ends

    Published milestoneCouncil source

Decision & conditions

Dismissed
2021-03-26 - Inspector's Report.pdf 2021-09-21 - Decision Letter.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.