Council planning record

Reserved matters application for access, appearance, landscaping, layout and scale following consent granted under reference P14/V2873/O relating solely to Phase 1a of the overall allocation regarding infrastructure elements to enable works for Phase 1 and 2. An EIA was submitted as part of the approved outline permission (as amplified and amended by information received 16 May 2022, 28 April 2023, 17 August 2023, 4 December 2023, 30 January 2024 and 15 February 2024).

Phase 1a, Valley Park, Land to the West of Great Western Park

Decision MadeReference: P22/V0604/RMVale of White Horse District Council

Last published check: 12 Oct 2026, 04:47. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Issue Date

    Published milestoneCouncil source

Application summary

Status
Decision Made
Application type
Not published
Received
15 Mar 2022
Validated
Not published
Determination deadline
Not published
Local authority
Vale of White Horse District Council

Application overview

Reserved matters application for access, appearance, landscaping, layout and scale following consent granted under reference P14/V2873/O relating solely to Phase 1a of the overall allocation regarding infrastructure elements to enable works for Phase 1 and 2. An EIA was submitted as part of the approved outline permission (as amplified and amended by information received 16 May 2022, 28 April 2023, 17 August 2023, 4 December 2023, 30 January 2024 and 15 February 2024).

Proposal details

Reference
P22/V0604/RM
Agent
RPS

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Phase 1a, Valley Park, Land to the West of Great Western Park

This record has no verified map location.

Documents 314 of 314

DocumentPublishedAction
SUPERSEDED Application FormApplication FormNot publishedView
Application FormApplication FormNot publishedView
SUPERSEDED Tree Pit Details Sheet 2 of 2 drwgno JSL3180 401Other Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 512 DOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 5 drwgno 10219-HL-RM1-500-080Other Plans/InformationNot publishedView
Foul Water Pumping Station Elevation drwgno 10219-HL-RM1-500-034DOther Plans/InformationNot publishedView
SUPERSEDED Tree and Shrub Palette Northern Hamlet JSL3180 RM1A 553Other Plans/InformationNot publishedView
SUPERSEDED Tree and Shrub Palette Moore Ditch JSL3180 550 COther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 501 JOther Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage drwgno 10219-HL-RM1-500- 002ROther Plans/InformationNot publishedView
Pump Station CGI - View 2Other Plans/InformationNot publishedView
SUPERSEDED Location Plan drwgno 10219-HL-RM1-100-001EOther Plans/InformationNot publishedView
SUPERSEDED Ecological Construction Management Plan-Phase 1A Infrastructure V2Other Plans/InformationNot publishedView
Landscape and Ecology Management Plan-Phase 1a Infrastructure V2Other Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage drwgno10219-HL-RM1-500-001XOther Plans/InformationNot publishedView
Foul Water Pumping Station Plan drwgno 10219-HL-RM1-500-030MOther Plans/InformationNot publishedView
SUPERSEDED Strategic Arboricultural Method Statement Rev BOther Plans/InformationNot publishedView
Surface Water Drainage Design Flows drwgno 10219-HL-RM1-500-220AOther Plans/InformationNot publishedView
SUPERSEDED Site Clearance Plan drwgno 10219-HL-RM1-100-011KOther Plans/InformationNot publishedView
SUPERSEDED Highway Works - Longitudinal drwgno 10219-HL-RM1-400-002FOther Plans/InformationNot publishedView
SUPERSEDED Drainage Excedance Plan drwgno 10219-HL-RM1-500-205FOther Plans/InformationNot publishedView
SUPERSEDED Tree Pit Details Sheet 1 of 2 drwgno JSL3180 400Other Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 502 IOther Plans/InformationNot publishedView
SUPERSEDED Northern Hamlet LEAP drwgno JSL 3180 520 BOther Plans/InformationNot publishedView
SUPERSEDED Retained Watercourse Buffer Zone Scheme V2Other Plans/InformationNot publishedView
Surface Water Catchment Plan drwgno 10219-HL-RM1-500-200FOther Plans/InformationNot publishedView
SUPERSEDED Visibility Plan drwgno 10219-HL-RM1-100-007OOther Plans/InformationNot publishedView
SUPERSEDED Temporary Bus Turning Head drwgno 10219-HL-RM1-100-021AOther Plans/InformationNot publishedView
SUPERSEDED Junction Tracking drwgno 10219-HL-RM1-100-020BOther Plans/InformationNot publishedView
SUPERSEDED Composite Plan drwgno 10219-HL-RM1-100-015FOther Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 1 of 3 drwgno JSL3180 721BOther Plans/InformationNot publishedView
SUPERSEDED Arboricultural Assessment and Method Statement Addendum rev DOther Plans/InformationNot publishedView
SUPERSEDED Tree and Shrub Palette Northern Wetlands JSL3180 RM1A 551AOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 511 DOther Plans/InformationNot publishedView
SUPERSEDED Biodiversity Enhancement Plan V2Other Plans/InformationNot publishedView
Typical Sections drwgno 10219-HL-RM1-100-006EOther Plans/InformationNot publishedView
SUPERSEDED Planning Layout drwgno 10219-HL-RM1-100-004TOther Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 2 of 3 drwgno JSL3180 722BOther Plans/InformationNot publishedView
2023-04-21 Covering letter Phase 1aOther Plans/InformationNot publishedView
Substation Elevations & Floor Plan drwgno HT-SUBST-01Other Plans/InformationNot publishedView
SUPERSEDED Tracking Plan drwgno 10219-HL-RM1-100-008POther Plans/InformationNot publishedView
SUPERSEDED Lighting Layout drwgno 10219-HL-RM1-100-1300EOther Plans/InformationNot publishedView
SUPERSEDED Highway Works GA drwgno 10219-HL-RM1-100-003TOther Plans/InformationNot publishedView
SUPERSEDED Cross Sections drwgno 10219-HL-RM1-400-003FOther Plans/InformationNot publishedView
SUPERSEDED Construction detail sheet 2 drwgno 10219-HL-RM1-100-110AOther Plans/InformationNot publishedView
Cut and Fill Isopachyte Plan drwgno 10219-HL-RM1-602-001Other Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 3 of 3 drwgno JSL3180 723BOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 503 FOther Plans/InformationNot publishedView
Landscape Management Plan rev BOther Plans/InformationNot publishedView
Pump Station CGI - View 1Other Plans/InformationNot publishedView
Application P22 V0604 RM planning comments responseOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections-Sheet 2 of 2 drwgno 10219-HL-RM1-500-021DOther Plans/InformationNot publishedView
SUPERSEDED Foul Water Catchment Plan drwgno 10219-HL-RM1-500-210FOther Plans/InformationNot publishedView
Drainage Standard Details drwgno 10219-HL-RM1-500-040COther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 2 of 4 drwgno 10219-HL-RM1-500-024HOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 1 of 4 drwgno 10219-HL-RM1-500-023FOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections-Sheet 1 of 2 drwgno 10219-HL-RM1-500-020FOther Plans/InformationNot publishedView
SUPERSEDED Highways Works Proposed Levels drwgno 10219-HL-RM1-400-001NOther Plans/InformationNot publishedView
SUPERSEDED Planning Compliance Statement Phase 1a April 2023Other Plans/InformationNot publishedView
JSL3180 401 Tree Pit Details Sheet 2 of 2Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-020K - Phase 1 Basins Layout and Sections - Sheet 1 of 4Other Plans/InformationNot publishedView
JSL3180 512 F Phase 1A Infrastructure LandscapeOther Plans/InformationNot publishedView
Security Screen Assessment 300mm Headwalls from CarriagewayOther Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-323C - Phase 1 Basins Layout and Sections - Sheet 4 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-105G Drainage Scale 1 to 500 Sheet 5Other Plans/InformationNot publishedView
10219-HL-RM1-500-060C- Headwall DetailsOther Plans/InformationNot publishedView
10219-HL-RM1-500-011J - Drainage Longitudinal Sections Sheet 2 of 7Other Plans/InformationNot publishedView
JSL3180 771 F Arboricultural Assessment and Method Statement AddendumOther Plans/InformationNot publishedView
JSL3180 602 Landscape Management AreasOther Plans/InformationNot publishedView
JSL3180 601 Hedgerow Overview PlanOther Plans/InformationNot publishedView
JSL3180 520D Northern Hamlet LEAPOther Plans/InformationNot publishedView
Debris Screen Assessment 1200mm dia outfall to Basin 1BOther Plans/InformationNot publishedView
10219-HL-RM1-500-104J Drainage Scale 1 to 500 Sheet 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-014E - Drainage Longitudinal Sections-Sheet 5 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-400-003H Cross SectionsOther Plans/InformationNot publishedView
10219-HL-RM1-100-110B Construction details - Sheet 2Other Plans/InformationNot publishedView
10219-HL-RM1-100-025B Highway GeometryOther Plans/InformationNot publishedView
10219-HL-RM1-100-021D Temporary Bus Turning HeadOther Plans/InformationNot publishedView
Debris Screen Assessment 375mm dia outfall to Cow LaneOther Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-322A - Phase 1 Basins Layout and Sections - Sheet 3 of 4Other Plans/InformationNot publishedView
SUPERSEDED Ecology Construction Management Plan - Phase 1aOther Plans/InformationNot publishedView
JSL3180 RM1A 553B Tree and Shrub Palette Northen Hamlet LEAPOther Plans/InformationNot publishedView
JSL3180 RM1A 550E Tree and Shrub Palette Moore DitchOther Plans/InformationNot publishedView
10219-HL-RM1-500-101L Drainage Scale 1 to 500 Sheet 1Other Plans/InformationNot publishedView
10219-HL-RM1-500-016E - Drainage Longitudinal Sections-Sheet 7 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-100-003X Highway Works GAOther Plans/InformationNot publishedView
10219-HL-RM1-500-210J- Foul Water Catchment PlanOther Plans/InformationNot publishedView
10219-HL-RM1-500-102J Drainage Scale 1 to 500 Sheet 2Other Plans/InformationNot publishedView
10219-HL-RM1-400-001S Proposed LevelsOther Plans/InformationNot publishedView
10219-HL-RM1-100-015J Composite PlanOther Plans/InformationNot publishedView
10219-HL-RM1-100-008T Tracking Sheet 1Other Plans/InformationNot publishedView
JSL3180 RM1A 551D Tree and Shrub Palette Northern WetlandsOther Plans/InformationNot publishedView
JSL3180 604 HIF Safeguarding Land Impact to Landscape Proposals Sheet 2 of 2Other Plans/InformationNot publishedView
JSL3180 603 HIF Safeguarding Land Impact to Landscape Proposals Sheet 1 of 2Other Plans/InformationNot publishedView
JSL3180 560 B Soft Landscape SpecificationOther Plans/InformationNot publishedView
JSL3180 501M Phase 1A Infrastructure LandscapeOther Plans/InformationNot publishedView
10219-HL-RM1-DR-150K - Basins and Swales Layout, Phase 1AOther Plans/InformationNot publishedView
10219-HL-RM1-602-001C Cut and Fill Isopachyte PlanOther Plans/InformationNot publishedView
10219-HL-RM1-500-107G Drainage Scale 1 to 500 Sheet 7Other Plans/InformationNot publishedView
10219-HL-RM1-500-106H Drainage Scale 1 to 500 Sheet 6Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-001AC Highway Works Drainage Sheet 1Other Plans/InformationNot publishedView
10219-HL-RM1-500-205J- Excedance PlanOther Plans/InformationNot publishedView
10219-HL-RM1-500-065B - Headwall Details Screen & Gating DetailsOther Plans/InformationNot publishedView
JSL3180 723C Tree Removal and Protection Plan 3 of 3Other Plans/InformationNot publishedView
JSL3180 511 E Phase 1A Infrastructure LandscapeOther Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-024K - Phase 1 Swale Cross Sections-Sheet 2 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-220B Surface Water Drainage Design FlowsOther Plans/InformationNot publishedView
10219-HL-RM1-500-103K Drainage Scale 1 to 500 Sheet 3Other Plans/InformationNot publishedView
10219-HL-RM1-500-015E - Drainage Longitudinal Sections-Sheet 6 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-500-012F - Drainage Longitudinal Sections-Sheet 3 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-400-002G Longitudinal SectionsOther Plans/InformationNot publishedView
10219-HL-RM1-100-011Q Site ClearanceOther Plans/InformationNot publishedView
JSL3180 770 B Strategic Arboricultural Method StatementOther Plans/InformationNot publishedView
JSL3180 721D Tree Removal and Protection Plan 1 of 3Other Plans/InformationNot publishedView
JSL3180 401 Tree Pit Details Sheet 2 of 2Other Plans/InformationNot publishedView
JSL3180 400 Tree Pit Details Sheet 1 of 2Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-002U Highway Works Drainage Sheet 2Other Plans/InformationNot publishedView
10219-HL-RM1-500-080A- Phase 1 Swale Cross Sections- Sheet 5 of 5Other Plans/InformationNot publishedView
10219-HL-RM1-100-020E Tracking Sheet 2Other Plans/InformationNot publishedView
10219-HL-RM1-100-004X Highway Planning LayoutOther Plans/InformationNot publishedView
10219-HL-RM1-100-002T Highway Works S38Other Plans/InformationNot publishedView
JSL3180 503 I Phase 1A Infrastructure LandscapeOther Plans/InformationNot publishedView
Security Screen Assessment 375 dia outfall to Cow LaneOther Plans/InformationNot publishedView
Security Screen Assessment 1200mm Dia pipe basin B1Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-026H - Phase 1 Swale Cross Sections-Sheet 4 of 4Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-021F - Phase 1 Basins Layout and Sections - Sheet 2 of 4Other Plans/InformationNot publishedView
JSL3180 502L Phase 1A Infrastructure LandscapeOther Plans/InformationNot publishedView
JSL3180 400 Tree Pit Details Sheet 1 of 2Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-500-023K - Phase 1 Swale Cross Sections-Sheet 1 of 4Other Plans/InformationNot publishedView
SUPERSEDED 10219-HL-RM1-100-007R VisibilityOther Plans/InformationNot publishedView
10219-HL-RM1-500-013F - Drainage Longitudinal Sections-Sheet 4 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-500-010K - Drainage Longitudinal Sections-Sheet 1 of 7Other Plans/InformationNot publishedView
10219-HL-RM1-100-1300G Lighting LayoutOther Plans/InformationNot publishedView
10219-HL-RM1-100-026A-Infrastructure Flood Zone OverlaidOther Plans/InformationNot publishedView
JSL3180 722D Tree Removal and Protection Plan 2 of 3Other Plans/InformationNot publishedView
10219-HL-RM1-100-007S VisibilityOther Plans/InformationNot publishedView
Ecology Constraint Plans fig.1a & 1bOther Plans/InformationNot publishedView
SUPERSEDED Retained Watercourse Buffer Zone SchemeOther Plans/InformationNot publishedView
Phase 1 Habitat Survey fig.1aOther Plans/InformationNot publishedView
Phase 1 Infrastructure Tree Protection & Watercourse Buffer Zones fig.3aOther Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage drwgno10219-HL-RM1-500-001POther Plans/InformationNot publishedView
SUPERSEDED Highway Works - Longitudinal drwgno 10219-HL-RM1-400-002 COther Plans/InformationNot publishedView
SUPERSEDED Drainage Standard Details drwgno 10219-HL-RM1-500-040BOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 4 of 7 drwgno 10219-HL-RM1-500-013BOther Plans/InformationNot publishedView
SUPERSEDED Construction details drwgno 10219-HL-RM1-100-009BOther Plans/InformationNot publishedView
SUPERSEDED Site Clearance Plan drwgno 10219-HL-RM1-100-011COther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 502 E Rev FOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Foul Water Rising Main Longitudinal Section- Sheet 2 of 2 drwgno10219-HL-RM1-500-033COther Plans/InformationNot publishedView
SUPERSEDED Highway Works GA drwgno 10219-HL-RM1-100-003NOther Plans/InformationNot publishedView
SUPERSEDED Foul Water Pumping Station Elevation drwgno 10219-HL-RM1-500-034AOther Plans/InformationNot publishedView
SUPERSEDED Typical Sections drwgno 10219-HL-RM1-100-006BOther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 712 BOther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 702 COther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 503 C Rev DOther Plans/InformationNot publishedView
SUPERSEDED Lighting Layout drwgno 10219-HL-RM1-100-1300Other Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 2 of 7 drwgno 10219-HL-RM1-500-011DOther Plans/InformationNot publishedView
SUPERSEDED Foul Water Catchment Plan drwgno 10219-HL-RM1-500-210COther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 7 of 7 drwgno 10219-HL-RM1-500-016AOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 6 of 7 drwgno 10219-HL-RM1-500-015AOther Plans/InformationNot publishedView
SUPERSEDED Drainage Excedance Plan drwgno 10219-HL-RM1-500-205COther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 715AOther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 701 COther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 3 of 4 drwgno 10219-HL-RM1-500-025BOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections-Sheet 2 of 2 drwgno 10219-HL-RM1-500-021COther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections-Sheet 1 of 2 drwgno 10219-HL-RM1-500-020COther Plans/InformationNot publishedView
SUPERSEDED Land Ownership drwgno 10219-HL-RM1-100-005EOther Plans/InformationNot publishedView
SUPERSEDED Visibility Plan drwgno 10219-HL-RM1-100-007JOther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 705 BOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 511 Rev AOther Plans/InformationNot publishedView
SUPERSEDED Foul Water Pumping Station Plan drwgno 10219-HL-RM1-500-030FOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 1 of 7 drwgno 10219-HL-RM1-500-010DOther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 711 BOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 501 E Rev FOther Plans/InformationNot publishedView
SUPERSEDED Planning Layout drwgno 10219-HL-RM1-100-004NOther Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage drwgno 10219-HL-RM1-500- 002JOther Plans/InformationNot publishedView
SUPERSEDED Control Manhole Details drwgno 10219-HL-RM1-500-027COther Plans/InformationNot publishedView
SUPERSEDED Tree Protection & Removal Plan drwgno JSL3180 703 COther Plans/InformationNot publishedView
SUPERSEDED Tracking Plan drwgno 10219-HL-RM1-100-008JOther Plans/InformationNot publishedView
SUPERSEDED Redline Plan drwgno 10219-HL-RM1-100-010SOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscape drwgno JSL3180 512 Rev AOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 4 of 4 drwgno 10219-HL-RM1-500-026FOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 2 of 4 drwgno 10219-HL-RM1-500-024GOther Plans/InformationNot publishedView
SUPERSEDED Location Plan drwgno 10219-HL-RM1-100-001BOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 5 of 7 drwgno 10219-HL-RM1-500-014AOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 3 of 7 drwgno 10219-HL-RM1-500-012BOther Plans/InformationNot publishedView
SUPERSEDED Cross Sections drwgno 10219-HL-RM1-400-003COther Plans/InformationNot publishedView
SUPERSEDED Check Dam Detail drwgno 10219-HL-RM1-500-022COther Plans/InformationNot publishedView
SUPERSEDED Surface Water Catchment Plan drwgno 10219-HL-RM1-500-200COther Plans/InformationNot publishedView
SUPERSEDED Basins and Swales Layout Phase 1A drwgno10219-HL-RM1-DR-150COther Plans/InformationNot publishedView
Planning Compliance Statement Phase 1a fv with appendicesOther Plans/InformationNot publishedView
Retained Watercourse Buffer Zone SchemeOther Plans/InformationNot publishedView
SUPERSEDED Retained Watercourse Buffer Zone SchemeOther Plans/InformationNot publishedView
Ecology Construction Management Plan - Phase 1aOther Plans/InformationNot publishedView
Play Area Proposal Plan drwgno OP1001Other Plans/InformationNot publishedView
10219 TN55 Rv0 - Valley Park RM1A FEH Rainfall Data Sensitivity Check ISSUEDOther Plans/InformationNot publishedView
SUPERSEDED Temporary Bus Turning Head drwgno 10219-HL-RM1-100-021BOther Plans/InformationNot publishedView
SUPERSEDED Longitudinal Sections drwgno 10219-HL-RM1-400-002GOther Plans/InformationNot publishedView
SUPERSEDED Highway Works S38 drwgno 10219-HL-RM1-100-002ROther Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 3 of 3 drwgno JSL3180 723 BOther Plans/InformationNot publishedView
Hedgerow Overview Plan drwgno JSL3180 601Other Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscaping drwgno JSL3180 512 EOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscaping drwgno JSL3180 511 EOther Plans/InformationNot publishedView
SUPERSEDED Tracking Plan Sheet 1 drwgno 10219-HL-RM1-100-008ROther Plans/InformationNot publishedView
SUPERSEDED Surface Water Drainage Design Flows drwgno 10219-HL-RM1-500-220BOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections - Sheet 4 of 4 drwgno 10219-HL-RM1-500-323Other Plans/InformationNot publishedView
SUPERSEDED Highway Planning Layout drwgno 10219-HL-RM1-100-004VOther Plans/InformationNot publishedView
SUPERSEDED Highway Geometry drwgno 10219-HL-RM1-100-025 Other Plans/InformationNot publishedView
Tree Removal and Protection Plan drwgno PHW24093-03B 1POther Plans/InformationNot publishedView
SUPERSEDED Soft Landscape Specification JSL3180 560 BOther Plans/InformationNot publishedView
SUPERSEDED Landscape Management Areas Plan drwgno JSL3180 602Other Plans/InformationNot publishedView
092 - RM1A Comments Response ScheduleOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 1 of 7 drwgno 10219-HL-RM1-500-010JOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscaping drwgno JSL3180 502 JOther Plans/InformationNot publishedView
SUPERSEDED Northern Hamlet LEAP drwgno JSL3180 520 COther Plans/InformationNot publishedView
SUPERSEDED Site Clearance Plan drwgno 10219-HL-RM1-100-011NOther Plans/InformationNot publishedView
SUPERSEDED Infrastructure Flood Zone Overlaid drwgno 10219-HL-RM1-100-026Other Plans/InformationNot publishedView
SUPERSEDED Highway Works Proposed Levels drwgno 10219-HL-RM1-400-001POther Plans/InformationNot publishedView
SUPERSEDED Highway Works GA drwgno 10219-HL-RM1-100-003VOther Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage Sheet 1 drwgno 10219-HL-RM1-500-001ZOther Plans/InformationNot publishedView
SUPERSEDED Excedance Plan drwgno 10219-HL-RM1-500-205HOther Plans/InformationNot publishedView
SUPERSEDED Drainage Scale 1 to 500 Sheet 4 drwgno 10219-HL-RM1-500-104GOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 2 of 7 drwgno 10219-HL-RM1-500-011H -Other Plans/InformationNot publishedView
SUPERSEDED Cut and Fill Isopachyte Plan drwgno 10219-HL-RM1-602-001AOther Plans/InformationNot publishedView
SUPERSEDED Cross Sections drwgno 10219-HL-RM1-400-003GOther Plans/InformationNot publishedView
SUPERSEDED Composite Plan drwgno 10219-HL-RM1-100-015GOther Plans/InformationNot publishedView
1T Tree Removal and Protection Plan drwgno TW 720 Rev AOther Plans/InformationNot publishedView
SUPERSEDED Ecological Construction Management Plan - Phase 1A Infrastructure V2 August 2023Other Plans/InformationNot publishedView
Valley Park Didcot Spine Road 1 checked DROther Plans/InformationNot publishedView
SUPERSEDED Surface Water Catchment Plan drwgno 10219-HL-RM1-500-200HOther Plans/InformationNot publishedView
SUPERSEDED Foul Water Catchment Plan drwgno 10219-HL-RM1-500-210HOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 3 of 7 drwgno 10219-HL-RM1-500-012FOther Plans/InformationNot publishedView
SUPERSEDED Basins and Swales Layout, Phase 1A drwgno 10219-HL-RM1-DR-150JOther Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 1 of 3 drwgno JSL3180 721 COther Plans/InformationNot publishedView
SUPERSEDED Tree and Shrub Palette Northern Hamlet drwgno JSL3180 RM1A 553 AOther Plans/InformationNot publishedView
SUPERSEDED Visibility Plan drwgno 10219-HL-RM1-100-007QOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections - Sheet 2 of 4 drwgno 10219-HL-RM1-500-021EOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections - Sheet 1 of 4 drwgno 10219-HL-RM1-500-020HOther Plans/InformationNot publishedView
SUPERSEDED Drainage Scale 1 to 500 Sheet 3 drwgno 10219-HL-RM1-500-103GOther Plans/InformationNot publishedView
05.06.23 SW Network 1Other Plans/InformationNot publishedView
SUPERSEDED Tree Removal and Protection Plan 2 of 3 drwgno JSL3180 722 COther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscaping drwgno JSL3180 503 GOther Plans/InformationNot publishedView
SUPERSEDED Retained Watercourse Buffer Zone Scheme V2 August 2023Other Plans/InformationNot publishedView
Biodiversity Enhancement Plan V2 August 2023Other Plans/InformationNot publishedView
SUPERSEDED Redline Plan drwgno 10219-HL-RM1-100-010YOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Basins Layout and Sections - Sheet 3 of 4 drwgno 10219-HL-RM1-500-322Other Plans/InformationNot publishedView
SUPERSEDED Headwall Details drwgno 10219-HL-RM1-500-060COther Plans/InformationNot publishedView
SUPERSEDED Screen and Grating Detail drwgno 10219-HL-RM1-500-065Other Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 2 of 4 drwgno 10219-HL-RM1-500-024JOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 1 of 4 drwgno 10219-HL-RM1-500-023HOther Plans/InformationNot publishedView
SUPERSEDED Lighting Layout drwgno 10219-HL-RM1-100-1300FOther Plans/InformationNot publishedView
SUPERSEDED Drainage Scale 1 to 500 Sheet 2 drwgno 10219-HL-RM1-500-102GOther Plans/InformationNot publishedView
SUPERSEDED Drainage Scale 1 to 500 Sheet 1 drwgno 10219-HL-RM1-500-101GOther Plans/InformationNot publishedView
SUPERSEDED Phase 1A Infrastructure Landscaping drwgno JSL3180 501 KOther Plans/InformationNot publishedView
SUPERSEDED Tracking Sheet 2 drwgno 10219-HL-RM1-100-020DOther Plans/InformationNot publishedView
SUPERSEDED Highway Works Drainage Sheet 2 drwgno 10219-HL-RM1-500-002TOther Plans/InformationNot publishedView
SUPERSEDED Drainage Longitudinal Sections-Sheet 4 of 7 drwgno 10219-HL-RM1-500-013FOther Plans/InformationNot publishedView
10219 - Drawing Register RM1A 2023.08.15Other Plans/InformationNot publishedView
Strategic Arboricultural Method Statement JSL3180 770 BOther Plans/InformationNot publishedView
SUPERSEDED Tree and Shrub Palette Northern Wetlands drwgno JSL3180 RM1A 551 BOther Plans/InformationNot publishedView
SUPERSEDED Headwall Details drwgno 10219-HL-RM1-500-060COther Plans/InformationNot publishedView
SUPERSEDED Earthworks drwgno 10219-HL-RM1-600-001LOther Plans/InformationNot publishedView
SUPERSEDED Highway Works S38 drwgno 10219-HL-RM1-100-002LOther Plans/InformationNot publishedView
SUPERSEDED Highways Works Proposed Levels drwgno 10219-HL-RM1-400-001FOther Plans/InformationNot publishedView
SUPERSEDED Traffic Signs and Road Markings drwgno10219-HL-RM1-1200-001KOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Swale Cross Sections-Sheet 1 of 4 drwgno 10219-HL-RM1-500-023DOther Plans/InformationNot publishedView
SUPERSEDED Phase 1 Foul Water Rising Main-Sheet 1 of 2 drwgno 10219-HL-RM1-500-032BOther Plans/InformationNot publishedView
SUPERSEDED Kerbs Footways and Paved Areas drwgno 10219-HL-RM1-1100-001JOther Plans/InformationNot publishedView
10219-SK-RM1-052 - Cow Lane Amended Ditch Plan Sheet 1 2Other Plans/InformationNot publishedView
10219-SK-415A Watercourse Clearance 1Other Plans/InformationNot publishedView
10219-SK-RM1-053 - Cow Lane Amended Ditch Plan Sheet 2 2Other Plans/InformationNot publishedView
Application P22 V0604 RM planning comments responseOther Plans/InformationNot publishedView
Appendix 1 Schedule of Compliance 2Other Plans/InformationNot publishedView
Security Screen Assessment HWS79Other Plans/InformationNot publishedView
Security Screen Assessment 375 dia outfall to Cow LaneOther Plans/InformationNot publishedView
Security Screen Assessment HWS53Other Plans/InformationNot publishedView
10219-HL-RM1-500-024L - Phase 1 Swale Cross Sections-Sheet 2 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-020L - Phase 1 Basins Layout and Sections - Sheet 1 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-323D - Phase 1 Basins Layout and Sections - Sheet 4 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-004C S104 Drainage Sheet 2Other Plans/InformationNot publishedView
Security Screen Assessment 1200mm Dia pipe basin B1Other Plans/InformationNot publishedView
10219-HL-RM1-500-325A - Basin Contour PlanOther Plans/InformationNot publishedView
10219-HL-RM1-500-200L- Surface Water Catchment PlanOther Plans/InformationNot publishedView
10219-HL-RM1-500-021G - Phase 1 Basins Layout and Sections - Sheet 2 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-324 - Phase 1 Basins Layout and Sections - Sheet 5 of 5Other Plans/InformationNot publishedView
10219-HL-RM1-500-026J - Phase 1 Swale Cross Sections-Sheet 4 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-322B - Phase 1 Basins Layout and Sections - Sheet 3 of 4Other Plans/InformationNot publishedView
Security Screen Assessment HWS74Other Plans/InformationNot publishedView
10219-HL-RM1-500-023L - Phase 1 Swale Cross Sections-Sheet 1 of 4Other Plans/InformationNot publishedView
10219-HL-RM1-500-003D S104 Drainage Sheet 1Other Plans/InformationNot publishedView
SUPERSEDED Substation Elevations & Floor Plan drwgno 32582 HT -01Other Plans/InformationNot publishedView
092 - RM1A Comments Response Schedule 30.11.23General PlanNot publishedView
10219-HL-RM1-100-010AA Redline PlanGeneral PlanNot publishedView
SUPERSEDED Ecological Construction Management Plan – Phase 1 InfrastructureSupporting documentationNot publishedView
SUPERSEDED Soft landscape SpecificationSupporting documentationNot publishedView
SUPERSEDED Planning Compliance Statement Phase 1aSupporting documentationNot publishedView
SUPERSEDED Site Waste Management PlanSupporting documentationNot publishedView
SUPERSEDED Landscape Management PlanSupporting documentationNot publishedView
SUPERSEDED ValleyPark LEAPSupporting documentationNot publishedView
SUPERSEDED Landscape and Ecology Management Plan – Phase 1a InfrastructureSupporting documentationNot publishedView
Tree Survey ReportSupporting documentationNot publishedView
SUPERSEDED Strategic Arboricultural Method Statement Rev ASupporting documentationNot publishedView
Covering LetterSupporting documentationNot publishedView
Transport AssessmentSupporting documentationNot publishedView
SUPERSEDED Biodiversity Enhancement PlanSupporting documentationNot publishedView
SUPERSEDED Arboricultural Assessment and Method Statement AddendumSupporting documentationNot publishedView
SUPERSEDED Tree and Shrub Palette - JSL3180 550 BSupporting documentationNot publishedView
Block Plan drwgno PL-03 A with AB obsPre-application advice givenNot publishedView
2021-12-13 Officer ResponsePre-application advice givenNot publishedView
Pre Application EnquiryPre-application advice givenNot publishedView
Block Plan drwgno PL-03 APre-application advice givenNot publishedView
Location Plan drwgno PL-01Pre-application advice givenNot publishedView
Application FormPre-application advice givenNot publishedView
Decision NoticeDecisionNot publishedView
Officer reportDecisionNot publishedView

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Planning Permission is Granted
Decision Notice Officer report
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.