Council planning record

Construction, operation and eventual decommissioning of up to a 12MW solar farm and will comprise the construction of solar panels mounted on metal frames, new access tracks, substation buildings, spares container, underground cabling, perimeter fencing with CCTV cameras and access gates, landscaping, temporary construction compounds and all ancillary grid infrastructure and associated site works.

Land East Of Dunmow Braintree Road Dunmow

ApprovedReference: UTT/25/1374/FULUttlesford District Council

Last published check: 27 Sept 2026, 13:13. Check the council record for more recent changes.

Application location

Land East Of Dunmow Braintree Road Dunmow

This record has no verified map location.

View council map

Application summary

Status
Approved
Application type
Fully Detailed
Received
20 May 2025
Validated
28 May 2025
Determination deadline
27 Aug 2025
Local authority
Uttlesford District Council

Application overview

Construction, operation and eventual decommissioning of up to a 12MW solar farm and will comprise the construction of solar panels mounted on metal frames, new access tracks, substation buildings, spares container, underground cabling, perimeter fencing with CCTV cameras and access gates, landscaping, temporary construction compounds and all ancillary grid infrastructure and associated site works.

Proposal details

Reference
UTT/25/1374/FUL
Alternative references
PP-14024829
Ward
Great Dunmow North
Parish
Great Dunmow
Agent
Neo Environmental

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 140 of 140

DocumentPublishedAction
ACFULZ - CONDITIONAL APPROVAL FULDecision Notice · PDF24 Sept 2026View
ACFULZ - CONDITIONAL APPROVAL FULDecision Notice · PDF24 Sept 2026View
OTHERB110-Officers Reports · PDF24 Sept 2026View
2.9.26 COMMITTEE PRESENTATIONB110-Officers Reports · PDF2 Sept 2026View
ADDENDUM LIST 02.09.26B110-Officers Reports · PDF28 Aug 2026View
FORMAL REPRESENTATION ON COMMITTEE REPORTB610-Supporting information · PDF27 Aug 2026View
COMMITTE REPORT 2.9.26B110-Officers Reports · PDF26 Aug 2026View
WWA LANDSCAPE - RESPONSEB900-AP Consultation Replies · PDF26 Aug 2026View
AGENT RESPONSE RE FORMAL REPRESENTATION ON UPDATED NPPFB900-AP Consultation Replies · PDF25 Aug 2026View
ECOLOGY PLACE SERVICES - RESPONSEB900-AP Consultation Replies · PDF14 Aug 2026View
LANDSCAPE AND VISUAL ADDENDUMB610-Supporting information · PDF7 Aug 2026View
ENVIRONMENTAL HEALTH - RESPONSEB900-AP Consultation Replies · PDF27 Jul 2026View
UDC CONSERVATION - REVISED RESPONSEB900-AP Consultation Replies · PDF23 Jul 2026View
UDC URBAN DESIGN - RESPONSEB900-AP Consultation Replies · PDF14 Jul 2026View
ESSEX COUNTY FIRE AND RESCUE - RESPONSEB900-AP Consultation Replies · PDF14 Jul 2026View
AFFINITY WATER - RESPONSEB900-AP Consultation Replies · PDF14 Jul 2026View
NATURAL ENGLAND - REVISED RESPONSEB900-AP Consultation Replies · PDF10 Jul 2026View
WWA LANDSCAPE - RESPONSEB900-AP Consultation Replies · PDF10 Jul 2026View
ECC SUDS - RESPONSE (DATED 14.8.25)B900-AP Consultation Replies · PDF9 Jul 2026View
ECC SUDS - RESPONSE (EMAIL)B900-AP Consultation Replies · PDF9 Jul 2026View
DNS SUBSTATION DETAILB020-Plan · PDF8 Jul 2026View
HISTORIC ENGLAND - RESPONSEB900-AP Consultation Replies · PDF29 Jun 2026View
AERODROME SAFGUARDING - RESPONSEB900-AP Consultation Replies · PDF29 Jun 2026View
ECC HIGHWAYS - COMMENTSB900-AP Consultation Replies · PDF25 Jun 2026View
ESSEX POLICE - RESPONSEB900-AP Consultation Replies · PDF25 Jun 2026View
ACTIVE TRAVEL ENGLAND - COMMENTSB900-AP Consultation Replies · PDF24 Jun 2026View
ANGLIAN WATER - RESPONSEB900-AP Consultation Replies · PDF24 Jun 2026View
UKPN - LETTERB900-AP Consultation Replies · PDF24 Jun 2026View
ESP UTILITIES GROUD - RESPONSEB900-AP Consultation Replies · PDF24 Jun 2026View
CADENT GAS - RESPONSEB900-AP Consultation Replies · PDF24 Jun 2026View
GIGACLEAR - RESPONSEB900-AP Consultation Replies · PDF24 Jun 2026View
PS ARCHAEOLOGICAL ADVICE - RESPONSEB900-AP Consultation Replies · PDF22 Jun 2026View
ARCHAEOLOGY MANAGEMENT STRATEGYB610-Supporting information · PDF17 Jun 2026View
PS ARCHAEOLOGICAL ADVICE - RESPONSEB900-AP Consultation Replies · PDF30 Apr 2026View
PRE-DETERMINATION ARCHAEOLOGICAL EVALUATIONB610-Supporting information · PDF21 Apr 2026View
PS ECOLOGY - REVISED RESPONSEB900-AP Consultation Replies · PDF27 Feb 2026View
REVISED BIODIVERSITY NET GAIN CONDITION ASSESSMENT SHEETSB610-Supporting information12 Feb 2026View
REVISED BIODIVERSITY NET GAIN METRICB610-Supporting information11 Feb 2026View
RESPONSE LETTER TO ECOLOGY COMMENTSB610-Supporting information · PDF11 Feb 2026View
PS ECOLOGY -REVISED RESPONSEB900-AP Consultation Replies · PDF9 Jan 2026View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT SHEET 3B020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT SHEET 4B020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT SHEET 5B020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT SHEET 6B020-Plan · PDF21 Nov 2025View
INDICATIVE INFRASTRUCTURE LAYOUT SHEET 7B020-Plan · PDF21 Nov 2025View
REVISED BIODIVERSITY NET GAIN ASSESSMENT - APPENDIX 2CB610-Supporting information · PDF21 Nov 2025View
TECHNICAL NOTE ECOLOGYB610-Supporting information · PDF21 Nov 2025View
SITE LOCATION MAPB020-Plan · PDF21 Nov 2025View
LEMPB020-Plan · PDF21 Nov 2025View
REVISED SITE LOCATION AND SITE NOTICE LOCATIONSB020-Plan · PDF21 Nov 2025View
SITE LOCATION AND SITE NOTICE LOCATIONS SHEET 2B020-Plan · PDF21 Nov 2025View
SITE LOCATION AND SITE NOTICE LOCATIONS SHEET 3B020-Plan · PDF21 Nov 2025View
REVISED AERIAL VIEWB020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE STRUCTURE LAYOUTB020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT (OVERALL)B020-Plan · PDF21 Nov 2025View
REVISED INDICATIVE INFRASTRUCTURE LAYOUT SHEET 2B020-Plan · PDF21 Nov 2025View
REVISED TECHNICAL APPENDIX 2:ECOLOGICAL ASSESSMENTB610-Supporting information · PDF21 Nov 2025View
SUPERSEDED BIODIVERSITY NET GAIN METRIC CALCULATIONB610-Supporting information21 Nov 2025View
REVISED TECHNICAL APPENDIX 1:LANDSCAPE AND VISUAL IMPACT ASSESSMENTB610-Supporting information · PDF21 Nov 2025View
SUPERSEDED BIODIVERSITY NET GAIN CONDITION ASSESSMENT SHEETSB610-Supporting information21 Nov 2025View
ECOLOGY PLACE SERVICES - RESPONSEB900-AP Consultation Replies · PDF7 Oct 2025View
ECC ARCHAEOLOGY - RESPONSEB900-AP Consultation Replies · PDF2 Sept 2025View
PLACE SERVICE ARCHEOLOGY - RESPONSEB900-AP Consultation Replies · PDF22 Aug 2025View
WRITTEN SCHEME OF INVESTIGATION V2B610-Supporting information · PDF18 Aug 2025View
SUDS - COMMENTSB900-AP Consultation Replies · PDF14 Aug 2025View
PLACE SERVICES HISTORIC ENVIRONMENT - RESPONSEB900-AP Consultation Replies · PDF13 Aug 2025View
ECOLOGICAL TECHNICAL NOTEB610-Supporting information · PDF8 Aug 2025View
REBUTTAL LETTERB610-Supporting information · PDF8 Aug 2025View
SUPERSEDED BIODIVERSITY CONDITION ASSESSMENT SHEETSB610-Supporting information · PDF8 Aug 2025View
UDC LANDSCAPE - RESPONSEB900-AP Consultation Replies · PDF7 Aug 2025View
MERKS HALL - COMMENTSB999 - Representation Letter · PDF3 Aug 2025View
9 BURY FIELDS - COMMENTSB999 - Representation Letter · PDF11 Jul 2025View
ECC HIGHWAYS - RESPONSEB900-AP Consultation Replies · PDF1 Jul 2025View
PLACE SERVICE ECOLOGY - RESPONSEB900-AP Consultation Replies · PDF30 Jun 2025View
ESSEX FIRE & RESCUE - RESPONSEB900-AP Consultation Replies · PDF26 Jun 2025View
4 ST CIBI PLACE - COMMENTSB999 - Representation Letter · PDF25 Jun 2025View
4 ST CIBI PLACE - COMMENTSB999 - Representation Letter · PDF25 Jun 2025View
GUSSETTS COTTAGES - COMMENTSB999 - Representation Letter · PDF24 Jun 2025View
HOME BARN - COMMENTSB999 - Representation Letter · PDF24 Jun 2025View
WINNIES LODGE - COMMENTSB999 - Representation Letter · PDF24 Jun 2025View
UDC CONSERVATION - RESPONSEB900-AP Consultation Replies · PDF23 Jun 2025View
GREAT DUNMOW TOWN COUNCIL - COMMENTSB900-AP Consultation Replies · PDF20 Jun 2025View
WOODLAND TRUST - RESPONSEB900-AP Consultation Replies · PDF20 Jun 2025View
ECC FIRE AND RESCUE SERVICE - RESPONSEB900-AP Consultation Replies · PDF18 Jun 2025View
ECC MINERALS & WASTE - RESPONSEB900-AP Consultation Replies · PDF17 Jun 2025View
NATURAL ENGLAND - RESPONSEB900-AP Consultation Replies · PDF16 Jun 2025View
ENVIRONMENTAL HEALTH - RESPONSEB900-AP Consultation Replies · PDF16 Jun 2025View
ECC ARCHAEOLOGY - COMMENTSB900-AP Consultation Replies · PDF13 Jun 2025View
MAG AERODROME SAFEGUARDING - RESPONSEB900-AP Consultation Replies · PDF11 Jun 2025View
HISTORIC ENGLAND - RESPONSEB900-AP Consultation Replies · PDF10 Jun 2025View
ESP UTILITIES GROUP - RESPONSEB900-AP Consultation Replies · PDF9 Jun 2025View
GIGACLEAR LTD - RESPONSEB900-AP Consultation Replies · PDF9 Jun 2025View
UKPN - LETTERB900-AP Consultation Replies · PDF9 Jun 2025View
CADENT GAS - RESPONSEB900-AP Consultation Replies · PDF9 Jun 2025View
REVISED APPLICATION FORMB610-Supporting information · PDF9 Jun 2025View
REVISED DESIGN AND ACCESS STATEMENTB610-Supporting information · PDF9 Jun 2025View
REVISED STATEMENT OF COMMUNITY INVOLVEMENTB610-Supporting information · PDF9 Jun 2025View
REVISED PLANNING STATEMENTB610-Supporting information · PDF9 Jun 2025View
ESSEX POLICE - RESPONSEB900-AP Consultation Replies · PDF6 Jun 2025View
UDC URBAN DESIGN - COMMENTSB900-AP Consultation Replies · PDF4 Jun 2025View
ACTIVE TRAVEL ENGLAND - COMMENTSB900-AP Consultation Replies · PDF2 Jun 2025View
ANGLIAN WATER SERVICE - RESPONSEB900-AP Consultation Replies · PDF30 May 2025View
ACKAPP STANDARD ACKNOWLEDGEMENTCorrespondence · PDF29 May 2025View
ESSEX POLICE - COMMENTSB900-AP Consultation Replies · PDF29 May 2025View
SUPERSEDED BIODIVERSITY METRICB610-Supporting information28 May 2025View
BIODIVERSITY CHECKLISTB610-Supporting information · PDF28 May 2025View
SUPERSEDED PLANNING STATEMENTB610-Supporting information · PDF28 May 2025View
SUPERSEDED TECHNICAL APPENDIX 2 - ECOLOGICAL ASSESSMENTB610-Supporting information · PDF28 May 2025View
CONSTR - CONSTRAINTS LISTReport · PDF21 May 2025View
SUPERSEDED APPLICATION FORMB610-Supporting information · PDF20 May 2025View
MERKS HILL FARM SOLAR PARK SITE LOCATION MAPB020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUTB020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUT (SHEET 2)B020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUT (SHEET 3)B020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUT (SHEET 4)B020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUT (SHEET 5)B020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUT (SHEET 6)B020-Plan · PDF20 May 2025View
ACCESS TRACKB020-Plan · PDF20 May 2025View
TEMPORARY CONSTRUCTION COMPOUNDB020-Plan · PDF20 May 2025View
PV MODULE AND RACK DETAILB020-Plan · PDF20 May 2025View
PV MODULE AND RACK DETAIL WITH STILTSB020-Plan · PDF20 May 2025View
SECURITY FENCE DETAILB020-Plan · PDF20 May 2025View
CCTV DETAILB020-Plan · PDF20 May 2025View
INVERTER DETAILB020-Plan · PDF20 May 2025View
SUBSTATION BUILDING - PLANB020-Plan · PDF20 May 2025View
SUBSTATION BUILDING - ELEVATIONB020-Plan · PDF20 May 2025View
STORAGE CONTAINERB020-Plan · PDF20 May 2025View
AUX TRANSFORMER UNITB020-Plan · PDF20 May 2025View
SUPERSEDED LOCATION PLANB020-Plan · PDF20 May 2025View
SUPERSEDED ARIEL VIEW OF DEVELOPEMENT BOUNDARYB020-Plan · PDF20 May 2025View
SUPERSEDED INDICATIVE INFRASTRUCTURE LAYOUTB020-Plan · PDF20 May 2025View
SUPERSEDED TECHNICAL APPENDIX 1: LANDSCAPE AND VISUAL IMPACT ASSESSMENTB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 3 - CULTURAL HERITAGE IMPACT ASSESSMENTB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 4: FLOOD RISK AND DRAINAGE SCHEMEB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 5: CONSTRUCTION TRAFFIC MANAGEMENT PLANB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 6: NOISE IMPACT ASSESSMENTB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 8: OUTLINE CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLANB610-Supporting information · PDF20 May 2025View
TECHNICAL APPENDIX 7: GLINT AND GLARE ASSESSMENTB610-Supporting information · PDF20 May 2025View
AGRICULTURE QUAILITY OF LAND AT TOOLEYS FARM GREAT DUNMOW REPORT 2429/1B610-Supporting information · PDF20 May 2025View
SUPERSEDED DESIGN AND ACCESS STATEMENTB610-Supporting information · PDF20 May 2025View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Last Advertised In Press Date

    Published milestoneCouncil source
  4. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Last Site Notice Posted Date

    Published milestoneCouncil source
  6. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Standard Consultation Date

    Published milestoneCouncil source
  10. Latest Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  11. Actual Committee Date

    Published milestoneCouncil source
  12. Decision Issued Date

    Published milestoneCouncil source
  13. Decision Made Date

    Published milestoneCouncil source
  14. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  15. Agreed Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  16. Permission Expiry Date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Approve with Conditions

Appeal status: Blank Field · Blank Field

ACFULZ - CONDITIONAL APPROVAL FUL ACFULZ - CONDITIONAL APPROVAL FUL
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.