ApprovedCouncil status: Permitted

Development of an Ecological Wildlife Site including a pond, on land associated with Tilbury Power Station. The land is owned on TWE nPower and was formerly part of an arable field. Non material amendment sought - Alteration to details submitted pursuant to the discharge of condition 7 (Pond Levels) figure A43998-18-L04-E is replaced by figure A43998-18-L04-H. The water level is now 0.1m AOD, approximately 1-1.3m below existing ground level. The overall excavation depth is 2.5-2.8m. The maximum water depth is 1.5m The previous design included a greater excavation to give an assumed water level of 2.5m-3m below ground level. The revised design takes account of geotechnical soil and clay stability and strength testing. The bund gradients are now appropriate for the nature of excavated material. Reduced excavation results in reduced material volume to be placed in bund's. Northern bund is at max height of 1.8m above ground level, domed to allow for surface run-off. Southern bund proposed to be 2.5m lower than approved due to reduction in volume of excavated material.

Power Station Fort Road Tilbury Essex RM18 8UL

Thurrock CouncilReference 10/50214/TTGNMAFull Planning Permission Application

Last published check: 21 Nov 2026, 02:01. Check the council record for more recent changes.

Status and dates

Last published check: 21 Nov 2026, 02:01 (UK)

  1. DoneReceived15 Sept 2010
  2. DoneValidated15 Sept 2010
  3. Not publishedConsultationNo date on council record
  4. Date set by councilTarget decision date10 Nov 2010
  5. DecidedApproved20 Sept 2010

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (4)
  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Decision Issued Date

    Published milestoneCouncil source
  4. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
Application type
Full Planning Permission Application
Ward
OLD Tilbury Riverside And Thurrock Park
Documents
6 published

Proposal

Development of an Ecological Wildlife Site including a pond, on land associated with Tilbury Power Station. The land is owned on TWE nPower and was formerly part of an arable field. Non material amendment sought - Alteration to details submitted pursuant to the discharge of condition 7 (Pond Levels) figure A43998-18-L04-E is replaced by figure A43998-18-L04-H. The water level is now 0.1m AOD, approximately 1-1.3m below existing ground level. The overall excavation depth is 2.5-2.8m. The maximum water depth is 1.5m The previous design included a greater excavation to give an assumed water level of 2.5m-3m below ground level. The revised design takes account of geotechnical soil and clay stability and strength testing. The bund gradients are now appropriate for the nature of excavated material. Reduced excavation results in reduced material volume to be placed in bund's. Northern bund is at max height of 1.8m above ground level, domed to allow for surface run-off. Southern bund proposed to be 2.5m lower than approved due to reduction in volume of excavated material.

Reference
10/50214/TTGNMA
Ward
OLD Tilbury Riverside And Thurrock Park

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • Completed Planning Application FormApplication Form24 Oct 2012View
  • TTGDC Officer's ReportDelegated Report24 Oct 2012View
  • CP - A43998-18-L04-RevEDrawing24 Oct 2012View
  • Decision NoticeDecision Notice24 Oct 2012View
  • CP - A43998-18-L04-RevHDrawing24 Oct 2012View
  • Planning Application Covering LetterApplication Form24 Oct 2012View

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Approved
Decision Notice
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.