Council planning record

Variation of Condition 2 (approved plans) and Conditions 4, 5, 6, 7, 8, 9, 12, 13, 14, 15, 16, 17 and 18 of Planning Permission 21/01749/FULLN (Construction and operation of a solar photovoltaic farm, battery storage and associated infrastructure, including inverters, batteries, substation compound, mast, security cameras, fencing, access tracks and landscaping) to allow for a partial reconfiguration of infrastructure

Land South East Of Perham Down Down Road Kimpton Down Hampshire

DecidedReference: 24/01585/VARNTest Valley Borough Council

Last published check: 9 Oct 2026, 06:21. Check the council record for more recent changes.

Application location

Land South East Of Perham Down Down Road Kimpton Down Hampshire

This record has no verified map location.

View council map

Application summary

Status
Decided
Application type
VARIATION OF CONDITIONS - NORTH
Received
10 Jul 2024
Validated
10 Jul 2024
Determination deadline
9 Oct 2024
Local authority
Test Valley Borough Council

Application overview

Variation of Condition 2 (approved plans) and Conditions 4, 5, 6, 7, 8, 9, 12, 13, 14, 15, 16, 17 and 18 of Planning Permission 21/01749/FULLN (Construction and operation of a solar photovoltaic farm, battery storage and associated infrastructure, including inverters, batteries, substation compound, mast, security cameras, fencing, access tracks and landscaping) to allow for a partial reconfiguration of infrastructure

Proposal details

Reference
24/01585/VARN
Alternative references
PP-13197213
Ward
BELLINGER
Parish
KIMPTON
Agent
DWD

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 70 of 70

DocumentPublishedAction
DELEGATEDOfficer Report · PDF20 Dec 2024View
PERMISSION SUBJECT TO CONDITIONS AND NOTESDecision Notice · PDF20 Dec 2024View
ENVIRONMENTAL PROTECTIONConsultation Responses4 Dec 2024View
SECTION 106 AGREEMENTLegal Agreement · PDF26 Nov 2024View
ADDITIONAL - NOISE ASSESSMENT (LF ACOUSTICS, NOVEMBER 2024)Supporting Information · PDF14 Nov 2024View
DEFENCE INFRASTRUCTURE ORGANISATIONConsultation Responses · PDF11 Oct 2024View
NATURAL ENGLANDConsultation Responses · PDF10 Sept 2024View
LANDSCAPE AND ECOLOGY MANAGEMENT PLANSupporting Information · PDF29 Aug 2024View
DETAILED SOFT LANDSCAPE DESIGNSupporting Information · PDF29 Aug 2024View
DETAILED SOFT LANDSCAPE DESIGNSupporting Information · PDF29 Aug 2024View
HIGHWAYS (HCC)Consultation Responses · PDF6 Aug 2024View
AMENDED - COVERING LETTERSupporting Information · PDF2 Aug 2024View
ADDITIONAL - SUBSTATION FLOOR PLANDrawing · PDF2 Aug 2024View
ADDITIONAL - SOLAR PANEL ELEVATIONDrawing · PDF2 Aug 2024View
ECOLOGY (TVBC)Consultation Responses · PDF2 Aug 2024View
CONSERVATION (TVBC)Consultation Responses · PDF2 Aug 2024View
RIGHTS OF WAY (HCC)Consultation Responses · PDF1 Aug 2024View
ENVIRONMENTAL PROTECTIONConsultation Responses1 Aug 2024View
LEAD FLOOD AUTHORITY (HCC)Consultation Responses · PDF31 Jul 2024View
SCREENING OPINIONSupporting Information31 Jul 2024View
LANDSCAPE (TVBC)Consultation Responses · PDF30 Jul 2024View
ARCHAEOLOGY (HCC)Consultation Responses · PDF24 Jul 2024View
HAMPSHIRE FIRE AND RESCUEConsultation Responses · PDF24 Jul 2024View
APPLICATION FORMSupporting Information · PDF10 Jul 2024View
ARCHAEOLOGICAL EVALUATION ADDENDUM TO WRITTEN SCHEME OF INVESTIGATIONSupporting Information · PDF10 Jul 2024View
ECOLOGICAL ASSESSMENT - ADDENDUMSupporting Information · PDF10 Jul 2024View
ECOLOGICAL INSPECTION PROFORMASupporting Information · PDF10 Jul 2024View
SURFACE WATER DRAINAGE SCHEMESupporting Information · PDF10 Jul 2024View
SURFACE WATER DRAINAGE SCHEMESupporting Information · PDF10 Jul 2024View
SURFACE WATER DRAINAGE SCHEMESupporting Information · PDF10 Jul 2024View
FLOOD RISK ASSESSMENTSupporting Information · PDF10 Jul 2024View
SWALE MAINTENANCE PROCEDURESSupporting Information · PDF10 Jul 2024View
FLOOD RISK ASSESSMENTSupporting Information · PDF10 Jul 2024View
CULTURAL HERITAGE ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND BIODIVERSITY STRATEGYSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
LANDSCAPE AND VISUAL APPRAISAL ADDENDUMSupporting Information · PDF10 Jul 2024View
GENERAL LIGHTINGSupporting Information · PDF10 Jul 2024View
PROPOSED LIGHTING LAYOUTDrawing · PDF10 Jul 2024View
NOISE ASSESSMENTSupporting Information · PDF10 Jul 2024View
CONSTRUCTION TRAFFIC MANAGEMENT PLANSupporting Information · PDF10 Jul 2024View
INVERTER STATION (SIDE VIEWS)Drawing · PDF10 Jul 2024View
DEVELOPMENT ZONE PLANDrawing · PDF10 Jul 2024View
CROSS SECTION ELEVATION PLANDrawing · PDF10 Jul 2024View
SUBSTATION COMPOUND PLANDrawing · PDF10 Jul 2024View
SITE LOCATION PLANDrawing · PDF10 Jul 2024View
FINAL SITE LAYOUT PLANDrawing · PDF10 Jul 2024View
INVERTER STATION (FRONT, REAR AND TOP VIEW)Drawing · PDF10 Jul 2024View
ACCESS TRACK CROSS SECTIONDrawing · PDF10 Jul 2024View
INDICATIVE DEER FENCE STANDARD DETAILDrawing · PDF10 Jul 2024View
CCTV POST STANDARD DRAWINGSDrawing · PDF10 Jul 2024View
PANEL ARRANGEMENT 4 LANDSCAPE 29.5 DEGREE TILTDrawing · PDF10 Jul 2024View
20FT SPARE PARTS CONTAINERDrawing · PDF10 Jul 2024View
O&M BUILDINGDrawing · PDF10 Jul 2024View
DNO TRACK CROSS SECTION STANDARD DETAILDrawing · PDF10 Jul 2024View
SOLAR PANEL ELEVATION MAX HEIGHT 2.7MDrawing · PDF10 Jul 2024View
INVERTER (PCSK)Drawing · PDF10 Jul 2024View
CUSTOMER SUBSTATION ELEVATIONS AND DIMENSION PLANSDrawing · PDF10 Jul 2024View
BESS CUSTOMER SUBSTATIONDrawing · PDF10 Jul 2024View
BATTERY INTERFACE CABINETDrawing · PDF10 Jul 2024View
TRANSFORMER AND HV SWITCH GEAR (TX+RMU)Drawing · PDF10 Jul 2024View
240,000L WATER TANKDrawing · PDF10 Jul 2024View
BATTERY UNITDrawing · PDF10 Jul 2024View
FLOOD RISK ASSESSMENTSupporting Information · PDF10 Jul 2024View
SURFACE WATER DRAINAGE SCHEMESupporting Information · PDF10 Jul 2024View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  4. Last Advertised In Press Date

    Published milestoneCouncil source
  5. Last Site Notice Posted Date

    Published milestoneCouncil source
  6. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  10. Standard Consultation Date

    Published milestoneCouncil source
  11. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  12. Decision Issued Date

    Published milestoneCouncil source

Decision & conditions

PERMISSION subject to conditions & notes
PERMISSION SUBJECT TO CONDITIONS AND NOTES
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.