Discharge of Requirement 16(1) Access Management Plan - Onshore Cable Duct Installation Stage

East Anglia ONE North Offshore Wind Farm

Application ApprovedReference: SCC/0144/25/DoR/EA1NSuffolk County Council

Application location

East Anglia ONE North Offshore Wind Farm

This record has no verified map location.

Application summary

Status
Application Approved
Application type
Discharge of Requirements
Received
16 Oct 2025
Validated
17 Oct 2025
Determination deadline
Not published
Local authority
Suffolk County Council

Application overview

Discharge of Requirement 16(1) Access Management Plan - Onshore Cable Duct Installation Stage

Proposal details

Reference
SCC/0144/25/DoR/EA1N
Agent
SLR Consulting Limited

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 10 of 10

DocumentPublishedAction
EA1N-ONC-CNS-PLN-IBR-000008_Cable_For Discharge_ AccessMP_Rev1EA1N-ONC-CNS-PLN-IBR-000008_Cable_For Discharge_ AccessMP_Rev1.pdf ( kb)17 Oct 2025View
Appendix 3 Road Safety AuditAppendix 3_Road Safety Audit.pdf ( kb)17 Oct 2025View
Response From PRoW RedactedResponse from PRoW_redacted.pdf ( kb)22 Oct 2025View
Comments From Friston Parish CouncilComments from Friston Parish Council.pdf ( kb)4 Nov 2025View
Response From East Suffolk Council Energy Projects RedactedResponse from East Suffolk Council Energy Projects_redacted.pdf ( kb)6 Nov 2025View
Response From SCC Transport StrategyResponse from SCC Transport Strategy.pdf ( kb)10 Nov 2025View
Response From Flood & Water RedactedResponse from Flood & Water_redacted.pdf ( kb)12 Nov 2025View
Further Response From SCC Transport StrategyFurther Response from SCC Transport Strategy.pdf ( kb)9 Dec 2025View
Officer Delegated Summary - AMP onshore cables_Officer Delegated Summary - AMP onshore cables_.pdf ( kb)10 Dec 2025View
EA1N Decision Letter AMP Cable Duct Installation 10.12.25_redactedEA1N Dec Letter AMP Cable Duct Installation 10.12.25_redacted.pdf ( kb)10 Dec 2025View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Decision Date

    Published milestoneCouncil source

Decision & conditions

DOR - Fully Discharged
EA1N Decision Letter AMP Cable Duct Installation 10.12.25_redacted
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.