Awaiting decisionCouncil status: Awaiting decision

Submission of details pursuant to Requirement 9 - Surface and Foul Water Drainage for Phase 2 Main Construction Works in relation to The Mallard Pass Solar Farm Order 2024 No. 796.

Mallard Pass Solar Farm

South Kesteven District CouncilReference S26/0951NSIP Requirement

Last published check: 21 Sept 2026, 21:26. Check the council record for more recent changes.

Open council website

Status and dates

Last published check: 21 Sept 2026, 21:26 (UK)

108days past target decision date12 Aug 2026 · decision not yet published

  1. DoneReceived15 May 2026
  2. DoneValidated3 Jun 2026
  3. Not publishedConsultationNo date on council record
  4. Overdue · 108 daysTarget decision date12 Aug 2026
  5. Not yet publishedDecisionNo decision on council record

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (5)
  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
Application type
NSIP Requirement
Ward
Casewick Ward
Parish
Uffington Parish Council
Documents
7 published

Proposal

Submission of details pursuant to Requirement 9 - Surface and Foul Water Drainage for Phase 2 Main Construction Works in relation to The Mallard Pass Solar Farm Order 2024 No. 796.

Reference
S26/0951
Ward
Casewick Ward
Parish
Uffington Parish Council
Agent
Envams

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • COVER LETTER - REDACTEDCorrespondence14 Aug 2026View
  • PHASE 2 MAIN CONSTRUCTION WORKS - SURFACE WATER DRAINAGE STRATEGY - REDACTEDReport14 Aug 2026View
  • PHASE 2 MAIN CONSTRUCTION WORKS - SURFACE WATER DRAINAGE STRATEGY - TRACKEDReport14 Aug 2026View
  • HIGHWAYS / SUDSConsultee Comment - PUBLIC23 Jun 2026View
  • MALLARD PASS ACTION GROUPConsultee Comment - PUBLIC8 Jun 2026View
  • COVER LETTER - REDACTEDCorrespondence15 May 2026View
  • WATER MANAGEMENT PLANReport15 May 2026View

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Decision not yet published
Planning conditions

We haven’t collected any decision conditions for this application.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.