Council planning record

Application to discharge condition 13 (Construction Management Plan) of permission SCC/3745/2020: The development hereby permitted shall not commence until a Construction Management Plan has been submitted to and approved in writing by the Local Planning Authority. The plan shall include construction vehicle movements, construction operation hours, construction vehicular routes to and from site, construction delivery hours, expected number of construction vehicles per day, car parking for contractors, specific measures to be adopted to mitigate construction impacts in pursuance of the Environmental Code of Construction Practice and a scheme to encourage the use of public transport amongst contractors. The development shall be carried out strictly in accordance with the approved Construction Management Plan. Reason: In the interests of highway safety and not to cause inconvenience to other highway users and in accordance with Policy D14 of the Sedgemoor District Local Plan.

Saltlands Transport Depot Saltlands Avenue Bridgwater TA6 3JG

Application ApprovedReference: SCC/3745/2020/Cond13Somerset Council

Last published check: 14 Sept 2026, 21:45. Check the council record for more recent changes.

Application location

Saltlands Transport Depot Saltlands Avenue Bridgwater TA6 3JG

This record has no verified map location.

Application summary

Status
Application Approved
Application type
Not published
Received
Not published
Validated
9 Nov 2021
Determination deadline
Not published
Local authority
Somerset Council

Application overview

Application to discharge condition 13 (Construction Management Plan) of permission SCC/3745/2020: The development hereby permitted shall not commence until a Construction Management Plan has been submitted to and approved in writing by the Local Planning Authority. The plan shall include construction vehicle movements, construction operation hours, construction vehicular routes to and from site, construction delivery hours, expected number of construction vehicles per day, car parking for contractors, specific measures to be adopted to mitigate construction impacts in pursuance of the Environmental Code of Construction Practice and a scheme to encourage the use of public transport amongst contractors. The development shall be carried out strictly in accordance with the approved Construction Management Plan. Reason: In the interests of highway safety and not to cause inconvenience to other highway users and in accordance with Policy D14 of the Sedgemoor District Local Plan.

Proposal details

Reference
SCC/3745/2020/Cond13
Agent
Chris Winn

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 7 of 7

DocumentPublishedAction
3745cond13 Highways - redacted.pdfCONSULTATION & CORRESPONDENCE (STATUTORY CONSULTEES)23 Nov 2021View
DECISION NOTICE_SCC-3745-2020-COND13 - Redacted.pdfDECISION NOTICES22 Dec 2021View
ApplicationFormRedacted.pdfPLANNING APPLICATION FORMS9 Nov 2021View
Location Plan.pdfPLANS & DRAWINGS12 Nov 2021View
Saltlands Construction Traffic Management Plan.pdfReport9 Nov 2021View
Saltlands Health & Safety File - Redacted.pdfReport12 Nov 2021View
OFFICER REPORT_SCC-3745-2020-CONDS5151413 - Redacted.pdfReport22 Dec 2021View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Valid

    Published milestoneCouncil source
  2. Consultation Expiry

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  3. Decision Date

    Published milestoneCouncil source

Decision & conditions

Application Approved
DECISION NOTICE_SCC-3745-2020-COND13 - Redacted.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.