Council planning record

Provision of a 2.09 km access track and associated works, new junction and temporary construction compound.

Unclassified road to Upper Kergord runs approximately 1.5km, from a junction with the B9075, approximately 70m east of B9075 of Weisdale crossing.

DecidedReference: 2018/096/PPFShetland Islands

Last published check: 30 Sept 2026, 12:17. Check the council record for more recent changes.

Application location

Unclassified road to Upper Kergord runs approximately 1.5km, from a junction with the B9075, approximately 70m east of B9075 of Weisdale crossing.

This record has no verified map location.

View council map

Application summary

Status
Decided
Application type
Planning Permission Full
Received
17 Apr 2018
Validated
18 Jun 2018
Determination deadline
18 Aug 2018
Local authority
Shetland Islands

Application overview

Provision of a 2.09 km access track and associated works, new junction and temporary construction compound.

Proposal details

Reference
2018/096/PPF
Alternative references
100089210-001
Agent
Arcus Consultancy Service Ltd

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 481 of 481

DocumentPublishedAction
EMAIL TO DEVELOPER - 11.9.2020 18.42Correspondence · PDF11 Sept 2020View
LETTER TO DEVELOPER GIVING INFORMAL AGREEMENT TO AMEND WORKING HOURS (ATTACHED TCorrespondence · PDF11 Sept 2020View
CONSULTEE COMMENT - ROADSConsultee Comment · PDF4 Aug 2020View
EMAIL TO DEVELOPER - 10.7.2020 11.27Correspondence · PDF10 Jul 2020View
LETTER TO DEVELOPER GIVING INFORMAL AGREEMENT TO AMEND WORKING HOURS (ATTACHED TCorrespondence · PDF10 Jul 2020View
EMAIL FROM DEVELOPER - 6.7.2020 12.57Correspondence · PDF6 Jul 2020View
REQUEST FROM DEVELOPER TO AMEND THE APPROVED WORKING HOURS (ATTACHED TO EMAIL 6.Correspondence · PDF6 Jul 2020View
CHIEF PLANNER LETTER SUBMITTED BY DEVELOPER IN SUPPORT OF REQUEST TO AMEND WORKISupporting Documents · PDF6 Jul 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF24 Jun 2020View
COVER E MAIL WITH INFORMATION FOR DCON13Correspondence · PDF24 Jun 2020View
COPY OF LETTER TO K ADAMCorrespondence · PDF24 Jun 2020View
COPY OF RESPONSE FROM K ADAMCorrespondence · PDF24 Jun 2020View
EMAIL FROM FRANK HAYCorrespondence · PDF18 Jun 2020View
CONSTRUCTION AND AIL TRAFFIC ROUTESCorrespondence17 Jun 2020View
HGV MOVEMENTS - JUNE 20 TO NOV 20 STAGE 2Correspondence17 Jun 2020View
TDL KAT TMP SIGNS STAGE 2Correspondence · PDF17 Jun 2020View
DELIVER DRIVER INSTRUCTIONSCorrespondence17 Jun 2020View
TDL KAT 018 UN NAMDED ROAD MAINT REV BCorrespondence17 Jun 2020View
16:00 EMAIL CORRESPONDENCECorrespondence · PDF17 Jun 2020View
SITE LAYOUTDrawing · PDF17 Jun 2020View
SITE LOCATIONDrawing · PDF17 Jun 2020View
SANDWATER ROAD ALIGNMENTDrawing · PDF17 Jun 2020View
KERGORD ROAD ALIGNMENTDrawing · PDF17 Jun 2020View
ROAD AGREEMENTDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
ROAD JUNCTIONDrawing · PDF17 Jun 2020View
CONSULTATION TO ROADS ON FURTHER INFORMATION SUBMISSION - 9.6.2020 09.51Correspondence · PDF9 Jun 2020View
FURTHER INFORMATION SUBMISSION FROM APPLICANT - EMAIL 8.6.2020 16.24Correspondence · PDF8 Jun 2020View
DISCHARGE OF NID COND 2Discharge of Condition(s)4 Jun 2020View
DISCHARGE OF CONDITION 2Discharge of Condition(s) · PDF4 Jun 2020View
EMAIL TO APPLICANT REQUESTING FURTHER INFORMATION - 3.6.2020 16.54Correspondence · PDF3 Jun 2020View
EMAIL RE NID FORMDischarge of Condition(s) · PDF2 Jun 2020View
NID FORMSuperseded Supporting Documents · PDF2 Jun 2020View
EMAIL RE NID FORMDischarge of Condition(s) · PDF2 Jun 2020View
REVISED NID FORMDischarge of Condition(s) · PDF2 Jun 2020View
CONSULTATION RESPONSE - ROADSConsultee Comment · PDF25 May 2020View
EMAIL FROM APPLICANT PROVIDING INFORMATION REQUESTED - 19.5.2020 10.20Correspondence · PDF19 May 2020View
SUPPORTING DOCUMENTS SUBMITTED BY APPLICANT WITH EMAIL 19.5.2020 10.20Supporting Documents · PDF19 May 2020View
EMAIL FROM APPLICANT 14.5.2020 TO DISCHARGE CONDITION 19Application Form · PDF18 May 2020View
REQUEST TO APPLICANT FOR COPIES OF EVIDENCE TO SUPPORT THE APPLICATION - 18.5.20Correspondence · PDF18 May 2020View
CONSULTEE COMMENT - ARCHAEOLOGYConsultee Comment · PDF15 May 2020View
--ARCHAEOLOGICAL WRITTEN SCHEME OF INVESTIGATIONApproved Plans · PDF15 May 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF15 May 2020View
APPENDIX BI_PLAN DRAWING AND PEAT REINSTATEMENTApproved Plans · PDF20 Mar 2020View
CULVERT DESIGN METHODOLOGY STATEMENTApproved Plans · PDF20 Mar 2020View
POST WORKS WATERCOURSE AND DRAIN CATCHMENT AREASApproved Plans · PDF20 Mar 2020View
PRE WORKS WATERCOURSE AND DRAIN CATCHMENT AREASApproved Plans · PDF20 Mar 2020View
DESIGN NOTE: BURN OF WEISDALE CROSSING FLOOD ASSESSMENTApproved Plans · PDF20 Mar 2020View
PRE/POST WORKS BURN OF WEISDALE CATCHMENT AREAApproved Plans · PDF20 Mar 2020View
TYPICAL CULVERT DETAILS (SHEET 1 OF 2)Approved Plans · PDF20 Mar 2020View
TYPICAL CULVERT DETAILS (SHEET 2 OF 2)Approved Plans · PDF20 Mar 2020View
TYPICAL DRAINAGE DETAILSApproved Plans · PDF20 Mar 2020View
BURN OF DROSWALL CULVERT DETAILSApproved Plans · PDF20 Mar 2020View
KERGORD ACCESS ADVANCED WORKS DRAINAGE DETAILS (SHEET 1 OF 2)Approved Plans · PDF20 Mar 2020View
KERGORD ACCESS ADVANCED WORKS DRAINAGE DETAILS (SHEET 2 OF 2)Approved Plans · PDF20 Mar 2020View
VEWF_CEMP_APPENDICES_FINAL_V1.5IApproved Plans · PDF20 Mar 2020View
VEWF_CEMP_FINALApproved Plans · PDF20 Mar 2020View
PEAT MANAGEMENT PLANApproved Plans · PDF20 Mar 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF20 Mar 2020View
COVERING E MAIL WITH REIVSED DRAWINGSCorrespondence · PDF18 Mar 2020View
PEAT MANAGE PLAN APPENDIX ADrawing · PDF18 Mar 2020View
PEAT MANAGE PLAN APPENDIX BIDrawing · PDF18 Mar 2020View
PEAT MANAGE PLAN APPENDIX BIIDrawing · PDF18 Mar 2020View
EXCAVATED WASTE STATEMENTSupporting Documents · PDF18 Mar 2020View
SITE WASTE MANAGEMENT PLAN REV 2Supporting Documents · PDF18 Mar 2020View
CONSULTEE COMMENT - DRAINAGE/FLOODConsultee Comment · PDF17 Mar 2020View
CONSULTEE COMMENT - DRAINAGE/FLOODConsultee Comment · PDF17 Mar 2020View
NID FORMDischarge of Condition(s) · PDF13 Mar 2020View
EMAIL RE DISCHARGING CONDITIONSDischarge of Condition(s) · PDF13 Mar 2020View
15:45 EMAIL RE DISCHARGING CONDITIONSDischarge of Condition(s) · PDF13 Mar 2020View
15:45 EMAIL RE DISCHARGING CONDITIONSDischarge of Condition(s) · PDF13 Mar 2020View
APPENDIX BI_PLAN DRAWING AND PEAT REINSTATEMENT EXTENDischarge of Condition(s) · PDF13 Mar 2020View
CEMP - UPDATE TO APPENDIX 8.1Discharge of Condition(s) · PDF13 Mar 2020View
APPENDIX 8.1_POLLUTION PREVENTION PLANDischarge of Condition(s) · PDF13 Mar 2020View
PEAT MANAGEMENT PLAN_FINAL_V5Superseded Report · PDF11 Mar 2020View
PEAT MANAGEMENT PLAN_APPENDIX AApproved Plans · PDF11 Mar 2020View
APPENDIX BI_PLAN DRAWINGApproved Plans · PDF11 Mar 2020View
APPENDIX BII_SECTION DRAWING_PEAT REINSTATEMENTApproved Plans · PDF11 Mar 2020View
APPENDIX C_EXCAVATED WASTE STATEMENTApproved Plans · PDF11 Mar 2020View
SITE WASTE MANAGEMENT PLANApproved Plans · PDF11 Mar 2020View
PEAT MANAGEMENT PLAN_APPENDIX C_SWMPApproved Plans · PDF11 Mar 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF11 Mar 2020View
EMAIL FROM AGENT WITH FURTHER INFORMATION ON CONDITION 7 (E) (H) CEMP - RCD 11.3Supporting Documents · PDF11 Mar 2020View
KERGORD ROAD - PROPOSED CONSTRUCTION COMPOUND DRG ATTACHED TO EMAIL 11.3.2020 1Drawing · PDF11 Mar 2020View
EMAIL CORRESPONDENCE FROM APPLICANTCorrespondence · PDF9 Mar 2020View
CONTRACTOR DISCHARGE INFOCorrespondence · PDF9 Mar 2020View
SITE WASTE MANAGEMENT PLANCorrespondence · PDF9 Mar 2020View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF9 Mar 2020View
11:47 EMAIL CORRESPONDENCE FROM F HAYCorrespondence · PDF9 Mar 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF9 Mar 2020View
EMAIL CORRESPONDENCEDischarge of Condition(s) · PDF6 Mar 2020View
CEMP_APPENDICES_FINALSuperseded Drawing · PDF6 Mar 2020View
VEWF_CEMP_FINALDischarge of Condition(s) · PDF6 Mar 2020View
EMAIL CORRESPONDENCEDischarge of Condition(s) · PDF6 Mar 2020View
S118021-TG-HML-KA-DR-CH-0002 PLANSuperseded Drawing · PDF6 Mar 2020View
S118021-TG-HML-KA-DR-CH-0003 PLANSuperseded Drawing · PDF6 Mar 2020View
S118021-TG-HML-KA-DR-CH-0004 PLANSuperseded Drawing · PDF6 Mar 2020View
EMAIL REGARDING CONDITION 7 (E) AND (H)Correspondence · PDF6 Mar 2020View
EMAIL RE PEAT MANAGEMENT PLANCorrespondence · PDF6 Mar 2020View
APPENDIX A - PEAT MANAGEMENT PLANDischarge of Condition(s) · PDF6 Mar 2020View
APPENDIX BI_PLAN DRAWINGDischarge of Condition(s) · PDF6 Mar 2020View
APPENDIX BII_SECTION DRAWING_PEAT REINSTATEMENTDischarge of Condition(s) · PDF6 Mar 2020View
APPENDIX C_EXCAVATED WASTE STATEMENTDischarge of Condition(s) · PDF6 Mar 2020View
APPENDIX C - SITE WASTE MANAGEMENT PLANDischarge of Condition(s) · PDF6 Mar 2020View
PEAT MANAGEMENT PLAN_FINAL_V5Discharge of Condition(s) · PDF6 Mar 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF5 Mar 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF4 Mar 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF4 Mar 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF4 Mar 2020View
EMAIL CORRESPONDENCEDischarge of Condition(s) · PDF2 Mar 2020View
APPENDIX 11.1_TYPICAL PERMANENT DRAINAGE DETAILDrawing2 Mar 2020View
SITE WASTE MANAGEMENT PLANApproved Plans · PDF28 Feb 2020View
SUMMARY CONTRACTOR APPROACH TO EXCAVATED WASTEApproved Plans · PDF28 Feb 2020View
EMAIL RE REVISED INFORMATIONDischarge of Condition(s) · PDF28 Feb 2020View
APPENDIX A KERGORD REFINED ALIGNMENTDrawing · PDF28 Feb 2020View
APPENDIX BI - PLANDrawing · PDF28 Feb 2020View
APPENDIX BII - CROSS SECTIONSDrawing · PDF28 Feb 2020View
APPENDIX C - KERGORD ACCESS TRACK_EXCAVATED WASTE STATEMENTDrawing · PDF28 Feb 2020View
APPENDIX C_KERGORD ACCESS TRACK_SITE WASTE MANAGEMENT PLANDrawing · PDF28 Feb 2020View
PEAT MANAGEMENT PLAN_V4Drawing · PDF28 Feb 2020View
PEAT MANAGEMENT PLAN_V4Drawing · PDF28 Feb 2020View
PEAT MANAGEMENT PLAN_V4_HIGHLIGHTED CHANGESDrawing · PDF28 Feb 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF27 Feb 2020View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF27 Feb 2020View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF27 Feb 2020View
APPROVED DETAILSApproved Plans · PDF26 Feb 2020View
EMAIL REQUESTING DISCHARGE OF CONDITIONSDischarge of Condition(s) · PDF26 Feb 2020View
EMAIL CORRESPONDENCEDischarge of Condition(s) · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF26 Feb 2020View
EMAIL REQUESTING TO DISCHARGE CONDITION 12Discharge of Condition(s) · PDF24 Feb 2020View
EMAIL REQUESTING DISCHARGE OF CON 18Discharge of Condition(s) · PDF21 Feb 2020View
FIGURE 2.1-CEMP_SITE LOCATIONDrawing · PDF21 Feb 2020View
FIGURE 10.1 - CEMP_TYPICAL DETAILSDrawing · PDF21 Feb 2020View
FIGURE 10.2 - CEMP_INDICATIVE TRACK AND WATERCOURSE CROSSINGDrawing · PDF21 Feb 2020View
FIGURE 10.3 - CEMP_INDICATIVE SCHEMATIC SECTION OF TRACK DRAINAGEDrawing · PDF21 Feb 2020View
FIGURE 10.4 - CEMP_INDICATIVE BORROW PIT DRAINAGEDrawing · PDF21 Feb 2020View
FIGURE 10.5 - CEMP_ INDICATIVE TURBINE DRAINAGEDrawing · PDF21 Feb 2020View
FIGURE 10.6 - CEMP_INDICATIVE SUBSTATION CONTROL ROOMDrawing · PDF21 Feb 2020View
FIGURE 13.1A_D_CEMP_HABITATSDrawing · PDF21 Feb 2020View
FIGURE 14.1 - CEMP_ARCHAEOLOGYDrawing · PDF21 Feb 2020View
CONSTRUCTION ENVIROMENTAL MANAGEMENT PLANDischarge of Condition(s) · PDF21 Feb 2020View
CEMP_APPENDIX 2.1_SCHEDULE OF MITIGATIONDrawing21 Feb 2020View
CEMP_APPENDIX 8.1_CAR_CONSTRUCTION SITE LICENCE_POLLUTION PRVENTION PLANSuperseded Drawing · PDF21 Feb 2020View
CEMP_APPENDIX 11.1_TYPICAL PERMANENT DRAINAGE DETAILDrawing21 Feb 2020View
CEMP_APPENDIX 17.1_INDICATIVE CONSTRUCTION PROGRAMMEDrawing21 Feb 2020View
DISCHARGE OF CONDITION - APPROVEDDecision · PDF20 Feb 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF19 Feb 2020View
HABITAT MANAGEMENT PLANApproved Plans · PDF19 Feb 2020View
DISCHARGE OF CONDITION - APPROVEDDischarge of Condition(s) · PDF14 Feb 2020View
APPENDIX B - CONSTRUCTION AND AIL TRAFFIC ROUTESApproved Plans · PDF13 Feb 2020View
HGV MOVEMENTS - MAR 20 TO AUG 20Approved Plans · PDF13 Feb 2020View
SIGNAGE ENTRANCE LN000046-VIK-SID-SK-0014-02Approved Plans · PDF13 Feb 2020View
SIGNAGE LN000046-VIK-SID-SK-0014-01Approved Plans · PDF13 Feb 2020View
GEOPHYSICS REPORT VWFS 16Discharge of Condition(s) · PDF12 Feb 2020View
GEOPHYSICS REPORT DOCUMENTDischarge of Condition(s) · PDF12 Feb 2020View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF10 Feb 2020View
CONSULTATION RESPONSE - ROADSConsultee Comment10 Feb 2020View
EMAIL FROM DR TURNER RE WSIDischarge of Condition(s) · PDF7 Feb 2020View
COVERING E MAIL TO DISHARGE CONDITION 3Correspondence · PDF5 Feb 2020View
EMAIL CORRESPONDENCECorrespondence · PDF4 Feb 2020View
EMAIL FROM DR TURNER REGARDING CONDITION DISCHARGEAdvert · PDF29 Jan 2020View
EMAIL TO JAMIE WATT REGARD TO INFORMATION REQUIREDDischarge of Condition(s) · PDF29 Jan 2020View
CONSULTATION RESPONSE - SHETLAND REGIONAL ARCHAEOLOGISTConsultee Comment · PDF28 Jan 2020View
CONSULTATION RESPONSE - SHETLAND REGIONAL ARCHAEOLOGISTConsultee Comment · PDF28 Jan 2020View
EMAIL RE REVISED TMPDischarge of Condition(s) · PDF28 Jan 2020View
REVISED TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF28 Jan 2020View
EMAIL RE REVISED TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF28 Jan 2020View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF22 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 02, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 02, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 07, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 08, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 09, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 10, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 11, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 12, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 13, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 14, MBS COVERAGEApproved Plans · PDF20 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 14, ARCTIC TERNApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 13, GREYLAGApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 12, SKUASApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 11, RINGED PLOVERApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 10, LAPWINGApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 09, OYSTERCATCHERApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 08, DUNLINApproved Plans · PDF16 Jan 2020View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 07, GOLDEN PLOVERApproved Plans · PDF16 Jan 2020View
BIRD PROTECTION PLANApproved Plans · PDF16 Jan 2020View
DISCHARGE OF CONDITION - APPROVEDDischarge of Condition(s) · PDF16 Jan 2020View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF7 Jan 2020View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF7 Jan 2020View
EMAIL CORRESPONDENCE FROM APPLICANTDischarge of Condition(s) · PDF20 Dec 2019View
EMAIL CORRESPONDENCE FROM APPLICANTDischarge of Condition(s) · PDF20 Dec 2019View
CULVERT DESIGN METHODOLOGY STATEMENTDischarge of Condition(s) · PDF20 Dec 2019View
CULVERT DESIGN METHODOLOGY STATEMENTDischarge of Condition(s) · PDF20 Dec 2019View
DRAINAGE STRATEGY REPORTDischarge of Condition(s) · PDF20 Dec 2019View
DRAINAGE STRATEGY REPORTDischarge of Condition(s) · PDF20 Dec 2019View
BURN OF WEISDALE CROSSING FLOOD ASSESSMENTDischarge of Condition(s) · PDF20 Dec 2019View
BURN OF WEISDALE CROSSING FLOOD ASSESSMENTDischarge of Condition(s) · PDF20 Dec 2019View
EMAIL CORRESPONDENCE FROM APPLICANTDischarge of Condition(s) · PDF20 Dec 2019View
EMAIL CORRESPONDENCE FROM APPLICANTDischarge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 0-300) (1 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 300-600) (2 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 600-900) (3 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 900-1200) (4 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 1200-1500) (5 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 1500-1800) (6 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLAN & PROFILE (CHAINAGE 1800-2027) (7 OF 7)Discharge of Condition(s) · PDF20 Dec 2019View
PROPOSED MAINLINE PLANSuperseded Drawing · PDF20 Dec 2019View
PREWORKS WATERCOURSE & DRAIN CATCHMENT AREASDischarge of Condition(s) · PDF20 Dec 2019View
PREWORKS WATERCOURSE & DRAIN CATCHMENT AREASDischarge of Condition(s) · PDF20 Dec 2019View
PRE/POST WORKS BURN OF WEISDALE CATCHMENT AREADischarge of Condition(s) · PDF20 Dec 2019View
POST WORKS WATERCOURSE & DRAIN CATCHMENT AREASDischarge of Condition(s) · PDF20 Dec 2019View
POST WORKS WATERCOURSE & DRAIN CATCHMENT AREASDischarge of Condition(s) · PDF20 Dec 2019View
TYPICAL CULVERT DETAILS (SHEET 1 OF 2)Discharge of Condition(s) · PDF20 Dec 2019View
TYPICAL CULVERT DETAILS (SHEET 2 OF 2)Discharge of Condition(s) · PDF20 Dec 2019View
BURN OF DROSWALL CULVERT DETAILSDischarge of Condition(s) · PDF20 Dec 2019View
KERGORD ACCESS ADVANCED WORKS DRAINAGE DETAILS (SHEET 1 OF 2)Discharge of Condition(s) · PDF20 Dec 2019View
KERGORD ACCESS ADVANCED WORKS DRAINAGE DETAILS (SHEET 2 OF 2)Discharge of Condition(s) · PDF20 Dec 2019View
TYPICAL DRAINAGE DETAILSDischarge of Condition(s) · PDF20 Dec 2019View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF18 Dec 2019View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF18 Dec 2019View
EMAIL FROM AGENT RE BIRD PROTECTION PLANDischarge of Condition(s) · PDF12 Dec 2019View
EMAIL FROM AGENT RE BIRD PROTECTION PLANDischarge of Condition(s) · PDF12 Dec 2019View
BIRD PROTECTION PLANDischarge of Condition(s)12 Dec 2019View
EMAIL TO APPLICANT CONFIRMING RECONSULTATION WITH ROADS AUTHORITY - 2.12.2019 1Correspondence · PDF2 Dec 2019View
EMAIL TO APPLICANT CONFIRMING RECONSULTATION WITH ROADS AUTHORITY - 2.12.2019 1Correspondence · PDF2 Dec 2019View
EMAIL RE TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF28 Nov 2019View
KERGORD ROAD- TMP- CONDITION 17Discharge of Condition(s)28 Nov 2019View
SITE LOCATION LN000046-VIK-SID-SD-0002-01Discharge of Condition(s) · PDF28 Nov 2019View
ROAD ALIGNMENT LN000046-VIK-SID-SD-0003-02Discharge of Condition(s) · PDF28 Nov 2019View
ROAD AGREEMENT LN000046-VIK-SID-SK-0030-04Discharge of Condition(s) · PDF28 Nov 2019View
PUBLIC HIGHWAY SPEED LIMITSDischarge of Condition(s) · PDF28 Nov 2019View
APPENDIX B - CONSTRUCTION AND AIL TRAFFIC ROUTESDischarge of Condition(s)28 Nov 2019View
EMAIL RE TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF28 Nov 2019View
HGV MOVEMENTS - MAR 20 TO AUG 20Discharge of Condition(s)28 Nov 2019View
KERGORD ROAD- TMP- CONDITION 17Discharge of Condition(s)28 Nov 2019View
PUBLIC HIGHWAY SPEED LIMITSDischarge of Condition(s) · PDF28 Nov 2019View
ROAD AGREEMENT LN000046-VIK-SID-SK-0030-04Discharge of Condition(s) · PDF28 Nov 2019View
ROAD ALIGNMENT LN000046-VIK-SID-SD-0003-02Discharge of Condition(s) · PDF28 Nov 2019View
SIGNAGE ENTRANCE LN000046-VIK-SID-SK-0014-02Discharge of Condition(s) · PDF28 Nov 2019View
SIGNAGE LN000046-VIK-SID-SK-0014-01Discharge of Condition(s) · PDF28 Nov 2019View
SITE LOCATION LN000046-VIK-SID-SD-0002-01Discharge of Condition(s) · PDF28 Nov 2019View
CONSULTATION RESPONSE - ENV HEALTHConsultee Comment · PDF26 Nov 2019View
CONSULTATION RESPONSE - ENV HEALTHConsultee Comment · PDF26 Nov 2019View
EMAIL TO APPLICANT REQUESTING FURTHER INFORMATION - 20.11.2019 14.55Correspondence · PDF20 Nov 2019View
EMAIL TO APPLICANT REQUESTING FURTHER INFORMATION - 20.11.2019 14.55Correspondence · PDF20 Nov 2019View
CONSULTEE COMMENT - ROADSConsultee Comment19 Nov 2019View
CONSULTEE COMMENT - ROADSDischarge of Condition(s)19 Nov 2019View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF18 Nov 2019View
CONSULTATION RESPONSE - SNHDischarge of Condition(s) · PDF18 Nov 2019View
EMAIL SEEKING TO DISCHARGE PLANNING PERMISSION CONDITION 14- BIRD SURVEY AND BIRCorrespondence · PDF25 Oct 2019View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF16 Oct 2019View
CONSULTATION RESPONSE - SNHDischarge of Condition(s) · PDF16 Oct 2019View
CONSULTEE COMMENT - ROADSConsultee Comment11 Oct 2019View
CONSULTEE COMMENT - ROADSDischarge of Condition(s)11 Oct 2019View
CONSULTEE COMMENT - SEPADischarge of Condition(s) · PDF10 Oct 2019View
CONSULTEE COMMENT - SEPADischarge of Condition(s) · PDF10 Oct 2019View
PRE-CONSTRUCTION BIRD SURVEYCorrespondence · PDF10 Oct 2019View
BIRD PROTECTION PLANCorrespondence · PDF10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 02, MBS COVERAGEDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 07, GOLDEN PLOVERDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 08, DUNLINDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 09, OYSTERCATCHERDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 10, LAPWINGDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 11, RINGED PLOVER & SANDPIPERDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 12, SKUASDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 13, GREYLAG & GROUSEDrawing10 Oct 2019View
PRE-CON BIRD SURVEY APPENDIX 1 FIG 14, ARCTIC TERN & TEALDrawing10 Oct 2019View
BIRD PROTECTION PLANCorrespondence · PDF10 Oct 2019View
PRE-CONSTRUCTION BIRD SURVEYCorrespondence · PDF10 Oct 2019View
DISCHARGE CONDITION 9Discharge of Condition(s) · PDF9 Oct 2019View
CONDITION 13 DISCHARGEDischarge of Condition(s) · PDF9 Oct 2019View
CONSULTEE COMMENT - SEPAConsultee Comment · PDF2 Oct 2019View
CONSULTEE COMMENT - SEPAConsultee Comment · PDF2 Oct 2019View
EMAIL RE UPDATED INFORMATION SUBMITTEDDischarge of Condition(s) · PDF1 Oct 2019View
TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF1 Oct 2019View
EMAIL RE UPDATED INFORMATION SUBMITTEDDischarge of Condition(s) · PDF1 Oct 2019View
TRAFFIC MANAGEMENT PLANDischarge of Condition(s) · PDF1 Oct 2019View
CONSULTEE COMMENT - SNHConsultee Comment · PDF1 Oct 2019View
CONSULTEE COMMENT - SNHConsultee Comment · PDF1 Oct 2019View
ACKNOWLEDGEMENT LETTERCorrespondence · PDF26 Sept 2019View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF25 Sept 2019View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF25 Sept 2019View
CONSULTATION RESPONSE - SHETLAND REGIONAL ARCHAEOLOGISTConsultee Comment · PDF25 Sept 2019View
CONSULTATION RESPONSE - SHETLAND REGIONAL ARCHAEOLOGISTConsultee Comment · PDF25 Sept 2019View
PUBLIC HIGHWAY SPEED LIMITSSupporting Documents · PDF24 Sept 2019View
TRAFFIC MANAGEMENT PLANSuperseded Report · PDF24 Sept 2019View
APPENDIX B - CONSTRUCTION AND AIL TRAFFIC ROUTESDrawing24 Sept 2019View
HGV MOVEMENTSSupporting Documents24 Sept 2019View
ROAD AGREEMENTSuperseded Drawing · PDF24 Sept 2019View
SIGNAGE ENTRANCESuperseded Drawing · PDF24 Sept 2019View
SIGNAGESuperseded Drawing · PDF24 Sept 2019View
KERGORD ROAD ALIGNMENTSuperseded Drawing · PDF24 Sept 2019View
SANDWATER ROAD ALIGNMENTDrawing · PDF24 Sept 2019View
CONSENTED SITE LAYOUT ADVANCED WORKSDrawing · PDF24 Sept 2019View
CONSENTED SITE LAYOUT ADVANCED WORKSDrawing24 Sept 2019View
SANDWATER ROAD ALIGNMENTDrawing · PDF24 Sept 2019View
KERGORD ROAD ALIGNMENTDrawing · PDF24 Sept 2019View
SIGNAGEDrawing · PDF24 Sept 2019View
SIGNAGE ENTRANCESuperseded Drawing · PDF24 Sept 2019View
ROAD AGREEMENTDrawing · PDF24 Sept 2019View
PUBLIC HIGHWAY SPEED LIMITSSupporting Documents · PDF24 Sept 2019View
TRAFFIC MANAGEMENT PLANSupporting Documents · PDF24 Sept 2019View
HGV MOVEMENTSSupporting Documents24 Sept 2019View
CONSTRUCTION AND AIL TRAFFIC ROUTESSupporting Documents24 Sept 2019View
COVERING E MAIL TO DISCHARGE CONDITION 17Correspondence · PDF24 Sept 2019View
EMAIL TO DISCHARGE CONDITION 13Discharge of Condition(s) · PDF17 Sept 2019View
EMAIL TO DISCHARGE CONDITION 13Discharge of Condition(s) · PDF17 Sept 2019View
EMAIL FROM SNH REQUESTING EXTENSION OF TIME - 16.9.2019 11.25Correspondence · PDF16 Sept 2019View
EMAIL FROM SNH REQUESTING EXTENSION OF TIME - 16.9.2019 11.25Correspondence · PDF16 Sept 2019View
EMAIL TO SNH AGREEING TO EXTENSION OF TIME TO 16.10.2019 - 16.9.2019 14.49Correspondence · PDF16 Sept 2019View
EMAIL TO SNH AGREEING TO EXTENSION OF TIME TO 16.10.2019 - 16.9.2019 14.49Correspondence · PDF16 Sept 2019View
CONSULTATION RESPONSE - MARINE SCOTLAND SCIENCEConsultee Comment · PDF16 Sept 2019View
CONSULTATION RESPONSE - MARINE SCOTLAND SCIENCEConsultee Comment · PDF16 Sept 2019View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF13 Sept 2019View
CONSULTATION RESPONSE - DRAINAGEConsultee Comment · PDF13 Sept 2019View
[EXTERNAL] RE: VIKING WQMPDischarge of Condition(s) · PDF12 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY PARTNERSHIP - CONSULTATION - WATER QUALITYDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY PARTNERSHIP - CONSULTATION - WATER QUALITYDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - MEETING AGENDA (17TH JUNE) &Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - MEETING AGENDA (17TH JUNE) &Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - MEETING AGENDA (17TH JUNE) &Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - MEETING AGENDA (17TH JUNE) &Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING WQMPDischarge of Condition(s) · PDF11 Sept 2019View
FIGURE 1_SAMPLING LOCATIONSDischarge of Condition(s) · PDF11 Sept 2019View
FIGURE 1_SAMPLING LOCATIONSDischarge of Condition(s) · PDF11 Sept 2019View
VIKING WIND FARM-WQMPDischarge of Condition(s) · PDF11 Sept 2019View
VIKING WIND FARM-WQMPDischarge of Condition(s) · PDF11 Sept 2019View
EMAIL RE KERGORD ROAD (2018/096/PPF)- CONDITION 9 - WQMPDischarge of Condition(s) · PDF11 Sept 2019View
EMAIL RE KERGORD ROAD (2018/096/PPF)- CONDITION 9 - WQMPDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - PLANNING CONSENT COND. NO. 4 (CEMP)Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING ENERGY WIND FARM - PLANNING CONSENT COND. NO. 4 (CEMP)Discharge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING WIND FARM - PLANNING CONSENT COND. NO. 4 (CONSTRUCTIONDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] RE: VIKING WIND FARM - PLANNING CONSENT COND. NO. 4 (CONSTRUCTIONDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] VIKING WIND FARM - PLANNING CONSENT CONDITION NO. 4 (CONSTRUCTIONDischarge of Condition(s) · PDF11 Sept 2019View
[EXTERNAL] VIKING WIND FARM - PLANNING CONSENT CONDITION NO. 4 (CONSTRUCTIONDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.2.1SITELOCDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.2.1SITELOCDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.9.1A_CHABITATSDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.9.1A_CHABITATSDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.10.1ARCHAEOLOGYDischarge of Condition(s) · PDF11 Sept 2019View
CEMP_FIG.10.1ARCHAEOLOGYDischarge of Condition(s) · PDF11 Sept 2019View
CONDITION 6 & 7 CEMP COVER LETTERDischarge of Condition(s) · PDF11 Sept 2019View
CONDITION 6 & 7 CEMP COVER LETTERDischarge of Condition(s) · PDF11 Sept 2019View
VIKING_CEMP_V1.1Discharge of Condition(s) · PDF11 Sept 2019View
VIKING_CEMP_V1.1Discharge of Condition(s) · PDF11 Sept 2019View
CEMP_APPENDIX 2.1_SCHEDULE OF MITIGATIONDischarge of Condition(s)11 Sept 2019View
CEMP_APPENDIX 2.1_SCHEDULE OF MITIGATIONDischarge of Condition(s)11 Sept 2019View
CEMP_APPENDIX 13.1_INDICATIVE CONSTRUCTION PROGRAMMEDischarge of Condition(s)11 Sept 2019View
CEMP_APPENDIX 13.1_INDICATIVE CONSTRUCTION PROGRAMMEDischarge of Condition(s)11 Sept 2019View
EMAIL RE KERGORD ROAD (2018096PPF)- CONDITION 6&7Discharge of Condition(s) · PDF11 Sept 2019View
EMAIL RE KERGORD ROAD (2018096PPF)- CONDITION 6&7Discharge of Condition(s) · PDF11 Sept 2019View
APPENDIX A - PMPDischarge of Condition(s) · PDF6 Sept 2019View
APPENDIX B - PMPDischarge of Condition(s) · PDF6 Sept 2019View
EMAIL RE CONDITION 6 PEAT MANAGEMENT PLANDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 1 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 2 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 3 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 4A - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 4B - PMPDischarge of Condition(s) · PDF6 Sept 2019View
PEAT MANAGEMENT PLANDischarge of Condition(s)6 Sept 2019View
APPENDIX A - PMPDischarge of Condition(s) · PDF6 Sept 2019View
APPENDIX B - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 1 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 2 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 3 - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 4A - PMPDischarge of Condition(s) · PDF6 Sept 2019View
FIGURE 4B - PMPDischarge of Condition(s) · PDF6 Sept 2019View
PEAT MANAGEMENT PLANDischarge of Condition(s)6 Sept 2019View
DISCHARGE CONDITION 15 ECOWDischarge of Condition(s) · PDF31 Jul 2019View
DISCHARGE OF CONDITION 15 - EMAIL 31.7.2019 15.29Decision · PDF31 Jul 2019View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF22 Jul 2019View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF22 Jul 2019View
CONSULTEE COMMENT - SNHConsultee Comment · PDF19 Jul 2019View
CONSULTEE COMMENT - SNHConsultee Comment · PDF19 Jul 2019View
EMAIL REQUEST TO DISCHARGE CONDITIONSDischarge of Condition(s) · PDF9 Jul 2019View
WRITTEN SCHEME OF INVESTIGATION- VIKING WIND FARMSuperseded Supporting Documents9 Jul 2019View
WSI- REGIONAL ARCHEAOLOGIST COMMENTSDischarge of Condition(s) · PDF9 Jul 2019View
EMAIL RE DISCHARGING CONDITIONSDischarge of Condition(s) · PDF9 Jul 2019View
WRITTEN SCHEME OF INVESTIGATION- VIKING WIND FARMDischarge of Condition(s)9 Jul 2019View
WSI- REGIONAL ARCHEAOLOGIST COMMENTSDischarge of Condition(s) · PDF9 Jul 2019View
APPENDIX 1- MBEC- ANDY MCKENZIE CVDischarge of Condition(s) · PDF9 Jul 2019View
EMAIL KERGORD ROAD- CONDITION DISCHARGE ECOWDischarge of Condition(s) · PDF9 Jul 2019View
ECOW COVER LETTERDischarge of Condition(s) · PDF9 Jul 2019View
APPENDIX 1- MBEC- ANDY MCKENZIE CVDischarge of Condition(s) · PDF9 Jul 2019View
EMAIL KERGORD ROAD- CONDITION DISCHARGE ECOWDischarge of Condition(s) · PDF9 Jul 2019View
KERGORD ROAD- ECOW COVER LETTERDischarge of Condition(s) · PDF9 Jul 2019View
DECISION NOTICEDecision · PDF29 Apr 2019View
ROAD ALIGNMENTApproved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 1 OF 7Approved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 2 OF 7Approved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 3 OF 7Approved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 4 OF 7Approved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 5 OF 7Approved Plans · PDF29 Apr 2019View
PLAN AND PROFILE 6 OF 7Approved Plans · PDF29 Apr 2019View
LOCATION PLANApproved Plans · PDF29 Apr 2019View
TYPICAL CROSS SECTIONSApproved Plans · PDF29 Apr 2019View
TYPICAL CROSS SECTIONApproved Plans · PDF29 Apr 2019View
APPENDIX 2 TO 15.4.2019 PLANNING COMMITTEE REPORTCommittee Report · PDF8 Apr 2019View
APPENDIX 3 TO 15.4.2019 PLANNING COMMITTEE REPORTCommittee Report8 Apr 2019View
APPENDIX 4 TO 15.4.2019 PLANNING COMMITTE REPORTCommittee Report · PDF8 Apr 2019View
APPLICANT/AGENT INVITE TO 15.4.2019 PLANNING COMMITTEECorrespondence · PDF8 Apr 2019View
EMAIL TO AGENT - 8.4.2019 16.52Correspondence · PDF8 Apr 2019View
SUSTAINABLE SHETLAND INVITE TO 15.4.2019 PLANNING COMMITTEECorrespondence · PDF8 Apr 2019View
J & E MORRISON INVITE TO 15.4.2019 PLANNING COMMITTEECorrespondence · PDF8 Apr 2019View
15.4.2019 PLANNING COMMITTEE REPORTCommittee Report · PDF8 Apr 2019View
APPENDIX 1 TO 15.4.2019 PLANNING COMMITTEE REPORTCommittee Report · PDF8 Apr 2019View
CORRESPONDENCE FROM TWW CCCorrespondence · PDF20 Feb 2019View
EMAIL TO CLERK TO COMMUNITY COUNCIL - 22.1.2019 11.28Correspondence · PDF22 Jan 2019View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF18 Jan 2019View
EMAIL TO SNH QUERYING CLASS 1 AND CLASS 2 CARBON RICH SOIL ETC CONSIDERATION INCorrespondence · PDF14 Jan 2019View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF10 Jan 2019View
EMAIL TO APPLICANT FOLLOWING UP ON WHEREABOUTS OF AMENDED PLANS FOR V1, REV 1 PECorrespondence · PDF6 Dec 2018View
NHO RESPONSE (VEWF COMMENTS)Consultee Comment · PDF5 Dec 2018View
RESPONSE TO RSPB COMMENTSCorrespondence · PDF4 Dec 2018View
EMAIL TO APPLICANT REGARDING APPARENT CHANGE IN SITE BOUNDARY - 27.11.2018 11.1Correspondence · PDF27 Nov 2018View
EMAIL FROM APPLICANT ADVISING SITE BOUNDARY CHANGE MADE IN ERROR - 27.11.2018 1Correspondence · PDF27 Nov 2018View
EMAIL FROM APPLICANT: RESPONSE TO SEPA OBJECTION - 26.11.2018 15.34Correspondence · PDF26 Nov 2018View
APPLICANT REPONSE TO SEPA OBJECTIONSupporting Documents · PDF26 Nov 2018View
PEAT MANAGEMENT PLAN NOV 2018Supporting Documents · PDF26 Nov 2018View
FIGURE 1 KERGORD TRACK ALIGNMENTDrawing · PDF26 Nov 2018View
FIGURE 2 KERGORD TRACK ALIGNMENTDrawing · PDF26 Nov 2018View
EXCAVATED PEAT VOLUMESDrawing · PDF26 Nov 2018View
EXCAVATED AND FLOATING ROAD PEAT VOLUMESDrawing · PDF26 Nov 2018View
PEAT CONTOUR PLAN KERGORD SSEDrawing · PDF26 Nov 2018View
PEAT CONTOUR PLAN KERGORD SSEDrawing · PDF26 Nov 2018View
SCHEMATIC RESTORATION PROFILESDrawing · PDF26 Nov 2018View
EMAIL TO AGENT I NOVEMBER RE INFORMATIONCorrespondence · PDF7 Nov 2018View
CONSULTATION RESPONSE - CCConsultee Comment · PDF31 Oct 2018View
CONSULTATION RESPONSE - NHOConsultee Comment19 Oct 2018View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF12 Oct 2018View
EMAIL TO APPLICANT ACKNOWLEDGIING RECEIPT OF SUPPORTING INFORMATION - 4.10.2018Correspondence · PDF4 Oct 2018View
EMAIL FROM APPLICANT PROVIDING FURTHER INFORMATION - 2.10.2018 16.48Correspondence · PDF2 Oct 2018View
SUPPORTING INFORMATION SUBMITTED BY APPLICANT IN RESPONSE TO SEPA OBJECTIONSupporting Documents · PDF2 Oct 2018View
CORRESPONDENCE FROM TWW COMMUNITY COUNCILCorrespondence · PDF26 Sept 2018View
ROADS CONSULTATION RESPONSEConsultee Comment11 Sept 2018View
CONSULTATION RESPONSE - RSPBConsultee Comment · PDF16 Aug 2018View
CONSULTATION RESPONSE - SEPAConsultee Comment · PDF30 Jul 2018View
CONSULTEE REQUEST - MORE TIME AND ACKCorrespondence · PDF20 Jul 2018View
CONSULTEE REQUEST - MORE TIME AND ACKCorrespondence · PDF20 Jul 2018View
REPRESENTATIONRepresentation · PDF18 Jul 2018View
REPRESENTATIONRepresentation · PDF17 Jul 2018View
CONSULTATION RESPONSE - OUTDOOR ACCESSConsultee Comment · PDF16 Jul 2018View
CONSULTATION RESPONSE - SCOTTISH WATERConsultee Comment · PDF16 Jul 2018View
CONSULTATION RESPONSE - SHETLAND ARCHAEOLOGYConsultee Comment · PDF12 Jul 2018View
CONSULTEE COMMENT - DRAINAGE/FLOODConsultee Comment · PDF11 Jul 2018View
CONSULTATION RESPONSE - SNHConsultee Comment · PDF11 Jul 2018View
SCREENING LETTERCorrespondence · PDF6 Jul 2018View
SCREENING EMAILCorrespondence · PDF6 Jul 2018View
LOCATION PLANSuperseded Drawing · PDF18 Jun 2018View
TYPICAL CROSS SECTIONSuperseded Drawing · PDF18 Jun 2018View
CROSS SECTIONSuperseded Drawing · PDF18 Jun 2018View
DRAWING ISSUE SHEETOther · PDF18 Jun 2018View
DRAWING ISSUE SHEETOther · PDF18 Jun 2018View
OVERVIEW PLANDrawing · PDF7 May 2018View
APPLICATION FORMApplication Form · PDF17 Apr 2018View
ENVIRONMENTAL APPRAISAL FIGURES PART 1 OF 2Drawing · PDF17 Apr 2018View
ENVIRONMENTAL APPRAISAL FIGURES PART 2 OF 2Drawing · PDF17 Apr 2018View
ENVIRONMENTAL APPRAISAL REPORT PART 1 OF 3Drawing · PDF17 Apr 2018View
APP F BASELINE BIRD SURVEYSDrawing · PDF17 Apr 2018View
APP K PEAT MANAGEMENT PLANDrawing · PDF17 Apr 2018View
PREVIOUSLY SUBMITTED APPLICATION FORM THAT SHOWS THAT THIS APPLICATION IS MATERIOther · PDF17 Apr 2018View
SUPPORTING OUTLINE PLANNING STATEMENTDrawing · PDF17 Apr 2018View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  4. Last Advertised In Press Date

    Published milestoneCouncil source
  5. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Actual Committee Date

    Published milestoneCouncil source
  9. Decision Made Date

    Published milestoneCouncil source
  10. Decision Issued Date

    Published milestoneCouncil source
  11. Permission Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Grant subject to conditions
DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION - APPROVED DISCHARGE OF CONDITION 15 - EMAIL 31.7.2019 15.29 DECISION NOTICE
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.