Council planning record

An application submitted under Section 96a of the Town & Country Planning Act 1990 for a Non-Material Amendment to vary Conditions 2 (Approved Plans), 10 (Maximum Floor Space Restrictions), Condition 60 (District Heat Network), 61 (Energy Centre (EC) ? Communal/District Heating Network (DHN)/ Connection to Kidbrooke site wide DHN EC and Decarbonisation) and 62 (Energy and CO2) of Planning Permission 23/3976/F in relation to Phase 5 Building A and B comprising amendments to the following: Site Plan Arrangements: Reduction of footprint from wall buildup (from 476mm to 310mm). Apartment layout and mix revisions from changes to building footprint. Rearrangement of building location on site to reflect footprint reduction. Layout Changes: Core revisions to comply with fire regulations. Placement of substation on ground floor of Building A. Re-location of substation in Building B3 to Building B1 Lower ground floor changes from updated plant room strategy and ramp access widening Refuse stores amendments Cycle store amendments Building Massing: All typical levels floor to floor height reduced from 3075mm to 3000mm resulting in reduced building 'AOD' height. All upper-level terraces removed. Facade Alterations: Balcony doors changed from sliding (2 pane windows/doors) to inward opening swing (3 pane windows/doors). Window positioning adjusted Facade changes at ground level to reflect relocation of substation. Facade changes at ground level to reflect updated plant room strategy and ramp access widening. Balconies amended from top fix balustrading to side fix balustrading. Use of Sustainabrick at first floor level and above.

Phase 5, Building A and B, Kidbrooke Village

DecidedReference: 25/4113/NMRoyal Borough of Greenwich

Last published check: 10 Oct 2026, 14:37. Check the council record for more recent changes.

Application location

Phase 5, Building A and B, Kidbrooke Village

This record has no verified map location.

View council map

Application summary

Status
Decided
Application type
Non Material
Received
9 Dec 2025
Validated
9 Dec 2025
Determination deadline
Not published
Local authority
Royal Borough of Greenwich

Application overview

An application submitted under Section 96a of the Town & Country Planning Act 1990 for a Non-Material Amendment to vary Conditions 2 (Approved Plans), 10 (Maximum Floor Space Restrictions), Condition 60 (District Heat Network), 61 (Energy Centre (EC) ? Communal/District Heating Network (DHN)/ Connection to Kidbrooke site wide DHN EC and Decarbonisation) and 62 (Energy and CO2) of Planning Permission 23/3976/F in relation to Phase 5 Building A and B comprising amendments to the following: Site Plan Arrangements: Reduction of footprint from wall buildup (from 476mm to 310mm). Apartment layout and mix revisions from changes to building footprint. Rearrangement of building location on site to reflect footprint reduction. Layout Changes: Core revisions to comply with fire regulations. Placement of substation on ground floor of Building A. Re-location of substation in Building B3 to Building B1 Lower ground floor changes from updated plant room strategy and ramp access widening Refuse stores amendments Cycle store amendments Building Massing: All typical levels floor to floor height reduced from 3075mm to 3000mm resulting in reduced building 'AOD' height. All upper-level terraces removed. Facade Alterations: Balcony doors changed from sliding (2 pane windows/doors) to inward opening swing (3 pane windows/doors). Window positioning adjusted Facade changes at ground level to reflect relocation of substation. Facade changes at ground level to reflect updated plant room strategy and ramp access widening. Balconies amended from top fix balustrading to side fix balustrading. Use of Sustainabrick at first floor level and above.

Proposal details

Reference
25/4113/NM
Alternative references
PP-14390067
Ward
KIDBROOKE VILLAGE & SUTCLIFFE
Parish
Eltham & Kidbrooke
Agent
Stantec UK Limited

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 51 of 51

DocumentPublishedAction
Decision noticeDecision Notice · PDF29 Apr 2026View
Officer reportReport · PDF28 Apr 2026View
Revised energy, overheating and sustainability strategy v3Document · PDF17 Mar 2026View
Energy condition noteDocument · PDF17 Mar 2026View
CorrespondanceCorrespondence · PDF6 Jan 2026View
S96a energy, overheating and sustainability strategy - v2Document · PDF19 Dec 2025View
Accessibility statementDocument · PDF19 Dec 2025View
Townscape and visual noteDocument · PDF19 Dec 2025View
Wind microclimate statementDocument · PDF19 Dec 2025View
Daylight and sunlight addendumDocument · PDF19 Dec 2025View
Eia compliance noteDocument · PDF19 Dec 2025View
Archaeology and built heritage statementDocument · PDF19 Dec 2025View
Transport addendumDocument · PDF9 Dec 2025View
Daylight sunlight addendumDocument · PDF9 Dec 2025View
Addendum fire safety reportDocument · PDF9 Dec 2025View
Covering letterDocument · PDF9 Dec 2025View
Site arrangement drawingsDrawing · PDF9 Dec 2025View
Approved plans part 2Drawing · PDF9 Dec 2025View
Design note part 2Document · PDF9 Dec 2025View
Schedules of accommodationDocument · PDF9 Dec 2025View
Design note part 3Document · PDF9 Dec 2025View
Approved plans part 1Drawing · PDF9 Dec 2025View
Approved plans part 3Drawing · PDF9 Dec 2025View
Proposed building b elevations part 1Drawing · PDF9 Dec 2025View
Illustrative masterplanDrawing · PDF9 Dec 2025View
Proposed site elevationsDrawing · PDF9 Dec 2025View
Approved plans part 4Drawing · PDF9 Dec 2025View
Proposed building a plansDrawing · PDF9 Dec 2025View
Proposed building b elevations part 2Drawing · PDF9 Dec 2025View
Design noteDocument · PDF9 Dec 2025View
DrawingDrawing · PDF9 Dec 2025View
Proposed ga elevation a buildings northDrawing · PDF9 Dec 2025View
Proposed building a sectionsDrawing · PDF9 Dec 2025View
Communal podium gardensDrawing · PDF9 Dec 2025View
DrawingDrawing · PDF9 Dec 2025View
Proposed building a elevations - part 1Drawing · PDF9 Dec 2025View
Proposed ga elevation a2 buildings southDrawing · PDF9 Dec 2025View
Design note - part 4Document · PDF9 Dec 2025View
Proposed building a sections part 2Drawing · PDF9 Dec 2025View
Proposed building b plansDrawing · PDF9 Dec 2025View
Proposed ga sections b buildingDrawing · PDF9 Dec 2025View
Building a unit type plansDrawing · PDF9 Dec 2025View
Proposed reference plans part 1Drawing · PDF9 Dec 2025View
Proposed building a unit plansDrawing · PDF9 Dec 2025View
Proposed building b sections - part 1Drawing · PDF9 Dec 2025View
Tree planting planDrawing · PDF9 Dec 2025View
Building b unit typesDrawing · PDF9 Dec 2025View
Proposed sitewide drawingsDrawing · PDF9 Dec 2025View
Application form (redacted)Application Form · PDF9 Dec 2025View
Proposed building b unit typeDrawing · PDF9 Dec 2025View
Proposed reference plans part 2Drawing · PDF9 Dec 2025View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated

    Published milestoneCouncil source
  3. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Standard Consultation Date

    Published milestoneCouncil source
  7. Agreed Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Decision Issued Date

    Published milestoneCouncil source
  9. Decision Made Date

    Published milestoneCouncil source

Decision & conditions

Approve
Decision notice
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.