Council planning record

DISCHARGE OF CONDITION 12 (CTMP & CTP)) OF PLANNING PERMISSION R/2020/0355/FFM FOR STAGE TCPA2) FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND AS...

LAND ALONG THE SOFIA OFFSHORE WIND FARM CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION

ApprovedReference: R/2022/0115/CDRedcar and Cleveland Borough Council

Last published check: 21 Sept 2026, 23:38. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Decision Date

    Published milestoneCouncil source

Application summary

Status
Approved
Application type
Condition Discharge
Received
10 Feb 2022
Validated
11 Mar 2022
Determination deadline
Not published
Local authority
Redcar and Cleveland Borough Council

Application overview

DISCHARGE OF CONDITION 12 (CTMP & CTP)) OF PLANNING PERMISSION R/2020/0355/FFM FOR STAGE TCPA2) FOR INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND AS...

Proposal details

Reference
R/2022/0115/CD
Agent
Royal HaskoningDHV

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

LAND ALONG THE SOFIA OFFSHORE WIND FARM CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION

This record has no verified map location.

Documents 21 of 21

DocumentPublishedAction
ApplicationFormRedacted.pdfApplication Form10 Feb 2022View
PC3329 SOWF DOC C12 Cover Letter draft.pdfCovering Letter10 Feb 2022View
Highways 0115.pdfConsultee response - Engineering Team (Highways)6 Apr 2022View
Compliance Decision Notice_R20220115CD.pdfCompliance Decision Notice R20220115cd14 Apr 2022View
CTMP - Appendix 2.2 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 2.2 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Appendix 4.1 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 4.1 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Appendix 4.2 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 4.2 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Stage 2 + 4 FINAL.pdfCondition 12 - Construction Travel Management Plan Stages 2 + 410 Feb 2022View
CTMP - Appendix 1.1 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 1.1 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Appendix 1.2 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 1.2 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Appendix 1.3 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 1.3 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
CTMP - Appendix 2.1 - Landfall HDD + HVDC Cable Works - Stages 2 + 4.pdfCondition 12 - Ctmp Appendix 2.1 Landfall Hdd + Hvdc Cable Works Stages 2 + 410 Feb 2022View
R 2020 0355 FFM Decision Notice.pdfR 2020 0355 FFM Decision Notice10 Feb 2022View
CTP - Appendix 2.1 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 2.1 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 2.2 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 2.2 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 4.1 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 4.1 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 4.2 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 4.2 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 4.3 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 4.3 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 4.4 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 4.4 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
CTP - Appendix 4.5 - Landfall HDD + HVDC Cable Works - Stages 2 + 4(1).pdfCondition 12 - Ctp Appendix 4.5 Landfall Hdd + Hvdc Cable Works Stages 2 + 4(1)11 Mar 2022View
Travel Plan - Stage 2 + 4 FINAL(1).pdfCondition 12 - Construction Travel Plan Stages 2 + 411 Mar 2022View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

CONDITION DISCHARGE GRANTED
Compliance Decision Notice_R20220115CD.pdf R 2020 0355 FFM Decision Notice.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.