Council planning record

SUBMISSION OF DETAILS FOR REQUIREMENT 26 (ARCHAEOLOGY) PARTS 1, 2 & 3 FOR STAGE 8 & 9 OF TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPECIFIED IN PA...

LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION

ApprovedReference: R/2021/0090/CDRedcar and Cleveland Borough Council

Last published check: 28 Sept 2026, 08:49. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Decision Date

    Published milestoneCouncil source

Application summary

Status
Approved
Application type
Condition Discharge
Received
4 Feb 2021
Validated
4 Feb 2021
Determination deadline
Not published
Local authority
Redcar and Cleveland Borough Council

Application overview

SUBMISSION OF DETAILS FOR REQUIREMENT 26 (ARCHAEOLOGY) PARTS 1, 2 & 3 FOR STAGE 8 & 9 OF TWO OFFSHORE WIND TURBINE GENERATING STATIONS AND ASSOCIATED INFRASTRUCTURE IN THE DOGGER BANK ZONE AND THE BOROUGH OF REDCAR AND CLEVELAND. THE FULL DESCRIPTION OF THE AUTHORISED DEVELOPMENT IS SPECIFIED IN PA...

Proposal details

Reference
R/2021/0090/CD
Agent
Arcus Consultancy Services Ltd

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

LAND ALONG THE DOGGER BANK C AND SOFIA OFFSHORE WIND FARMS CABLE CORRIDOR BETWEEN LANDFALL NEAR MARSKE BY THE SEA AND LACKENBY NATIONAL GRID SUBSTATION

This record has no verified map location.

Documents 17 of 17

DocumentPublishedAction
ApplicationFormRedacted.pdfApplication Form4 Feb 2021View
NEAR EMAIL.pdfConsultee response - Archaeological Consultant4 Mar 2021View
Compliance Decision Notice_R20210090CD.pdfCompliance Decision Notice R20210090cd9 Mar 2021View
Compliance Officer report _R20210090CD(1).pdfCompliance Officer Report R20210090cd(1)17 Mar 2021View
CL_DBC_Rq26_Parts 1.2 and 3_ St8 and 9_v1-4_KM_02022021.pdfRequirement 26 - Covering Letter4 Feb 2021View
1_Archaeological Mitigation Written Scheme of Investigation.pdfRequirement 26 - Written Scheme Of Investigation4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 1 of 10.pdfRequirement 26 - Archaeological Evalutation4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 2 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Appenidx 14 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 3 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Appenidx 24 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 4 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 5 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 6 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 7 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 8 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 9 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Photos4 Feb 2021View
2_Dogger Bank C Offshore Wind Farm and Sofia Offshore Wind Farm_ Archaeological Evaluation report 5403 November 2020_Part 10 of 10 (REF).pdfRequirement 26 - Archaeological Evalutation Figures 1-124 Feb 2021View
3_Archaeological Mitigation Written Scheme of Investigation 21022PC 190121 Phase 2 (REF)(1).pdfRequirement 26 - Archaeological Mitigation Written Scheme Of Investigation Phase 24 Feb 2021View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

CONDITION DISCHARGE GRANTED
Compliance Decision Notice_R20210090CD.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.