Status on council recordCouncil status: Determined

Non-material amendment (slab levels) to planning permission 23/00423/FUL

Plots 7 And 8 Fletton Quays Peterborough PE2 8TZ

Peterborough City CouncilReference 26/00126/NONMATNon-Material Amendment

Last published check: 3 Oct 2026, 18:53. Check the council record for more recent changes.

Open council website

Status and dates

Last published check: 3 Oct 2026, 18:53 (UK)

  1. DoneReceived29 Jan 2026
  2. Not publishedValidatedNo date on council record
  3. ClosedConsultationEnded 19 Feb 2026
  4. Date set by councilTarget decision date26 Feb 2026
  5. Not yet publishedDecisionNo decision on council record

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (9)
  1. Received date

    Published milestoneCouncil source
  2. Registration date

    Published milestoneCouncil source
  3. Dispatch date

    Published milestoneCouncil source
  4. Decision date

    Published milestoneCouncil source
  5. Consultation expiry date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Statutory expiry date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Decision due date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Application date

    Published milestoneCouncil source
  9. Decision expiry date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
Application type
Non-Material Amendment
Ward
Fletton & Stanground
Parish
Peterborough
Development type
Non Material Amendments

Proposal

Non-material amendment (slab levels) to planning permission 23/00423/FUL

Reference
26/00126/NONMAT
Alternative references
PP-14663503
Development type
Non Material Amendments
Ward
Fletton & Stanground
Parish
Peterborough
UPRN
100091524438

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • Previous/Parent decision noticeDCPRDEC29 Jan 2026View
  • Plans: 2628 AP0003 P11 - Location Plan and Site Masterplan as ProposedDCPLANS29 Jan 2026View
  • DecisionDCDEC17 Feb 2026View
  • Application Form: ApplicationDCAPFORM29 Jan 2026View
  • Application Supporting Document: C26 Non Material AmendmentDCSUPDOC29 Jan 2026View

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Determined
Previous/Parent decision notice Decision
Planning conditions
  1. Under Section 96A of the Town and Country Planning Act 1990 (as amended), the alterations to Condition 26 are acceptable as non-material amendments to the development approved under planning reference 23/00423/FUL. The amendments vary the original C26 which limited the development above slab level for Buildings 1 and 2 until the redevelopment of the Mill is not complete. The Applicant has justified the variation of this condition to allow for an efficient building process, whilst also ensuring that key building interventions (steels, roof, window/doors etc) are complete on the Mill alongside the development of the new buildings to ensure that the Mill is redeveloped in a timely manner without adversely impacting the viability of the proposed development. Accordingly, Condition 26 of planning permission reference 23/00423/FUL is therefore updated to read as below. This notice shall be appended to planning permission 23/00423/FUL and all other conditions attached thereto remain in place and in force.
  2. The proposed development shall be carried out in strict accordance with the following phasing: - The development of Building 2 shall not continue above Level 00 FFL until the internal steel structure has been installed inside the Mill - The development of Building 1 shall not continue beyond Level 00 FFL until the Mill has the new roof structure complete as per the approved plans - The development of Building 2 shall not achieve completion until the Mill is watertight with completed roof and all windows installed/reinstated as per the approved plans - The development of Building 1 shall not achieve completion prior to the full completion of all required work on the Mill and the Mill achieves completion For the purposes of the above 'completion' shall be defined as a Building Regulations Completion Certificate being issued. The Building numbers are set out in drawing 'Location Plan and Site Masterplan as Proposed' AP0003 Revision P11. Reason: In order to ensure that the locally listed Mill building is renovated to a standard where it can be brought back into use, in the interests of enhancing a valuable local heritage asset in accordance with Policy LP19 of the Peterborough Local Plan (2019).
Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.