The development shall begin not later than five years from the date of this decision. Reason: Required to be imposed pursuant to Section 91 (1) of the Town and Country Planning Act 1990 (as amended).
The development shall be carried out in accordance with the following approved plans and documents: • Drawing ref: 02 Proposed Block Plan & Location Plan received 08/05/2026 • Drawing ref: 03A Proposed Elevations and Floor Plan received 16/06/2026 • Cover Letter received 08/05/2026 • Green Infrastructure Statement received 08/05/2026 Reason: In order to be clear on the approved scheme of development in the interests of protecting visual amenity and the special qualities of the National Park. Policy: Local Development Plan 2 – Policies 1 (National Park Purposes and Duty), 8 (Special Qualities), 14 (Conservation of the Pembrokeshire Coast National Park) and 29 (Sustainable Design).
No development shall take place until a qualified and competent archaeologist has submitted a written scheme of investigation (WSI) for approval in writing by the local planning authority. This WSI will describe the different stages of the work and demonstrate that it has been fully resourced and given adequate time. On behalf of the local planning authority, their archaeological advisors (Heneb The Trust for Welsh Archaeology - DM) will monitor all aspects of this work through to the final discharging of the condition. This work will not be deemed complete until all aspects of the WSI have been addressed and the final report submitted and approved. Reason: To protect historic environment interests whilst enabling development.
Notwithstanding the submitted plans, either matt black or dark grey box profile sheeting shall be used for the sides of the approved building. If any other colour is proposed, a sample should first be submitted for approval to the Local Planning Authority and such colour as is agreed shall be implemented and retained thereafter. Reason: In order to provide a recessive colour scheme and to limit the visual impact of the development in accordance with Policies 29 & 30 of the Local Development Plan.
In the first available planting and seeding seasons following the first use, or substantial completion, of the development, planting must be implemented according to the Green Infrastructure Statement and drawing 03A Proposed elevations and floor plan. Any existing plants retained or translocated; or new plants planted or seeded in accordance with the approved scheme which, within a period of 5 years after implementation of the approved development are removed, die, become diseased or damaged to such extent that, in the opinion of the Local Planning Authority, the function in relation to this planning approval is no longer delivered, shall be replaced with plants of similar size and specification. Any variations to the details of the documents and plans must only be undertaken after the proposed variations have been formally agreed in writing by the LPA. Reason: To prevent detrimental impact to trees, hedges and other landscape features which contribute to the amenity, landscape & biodiversity of the site and surrounding area. Local Development Plan 2 - Policies: 1 (National Park Purposes and Duty), 8 (Special Qualities), 14 (Conservation and enhancement of the Pembrokeshire Coast National Park), 30 (Amenity), SPG 12 - Biodiversity, Technical Advice Note (TAN) 5: Nature Conservation and Planning (2009), Technical Advice Note (TAN) 10: Tree Preservation Orders (1997).
The bat boxes and sparrow terraces shall be installed in full adherence to the details submitted to this authority (03A Proposed elevations and floor plan) within 6 months of the other works hereby approved being completed. Any variations to the details of the documents and plans must only be undertaken after the proposed variations have been agreed in writing by the LPA. Reason: To prevent detrimental impact to trees, hedges and other landscape features which contribute to the amenity, landscape & biodiversity of the site and surrounding area. Local Development Plan 2 – Policies: 1 (National Park Purposes and Duty), 8 (Special Qualities), 14 (Conservation and enhancement of the Pembrokeshire Coast National Park), 30 (Amenity), SPG 12 – Biodiversity, Technical Advice Note (TAN) 5: Nature Conservation and Planning (2009), Technical Advice Note (TAN) 10: Tree Preservation Orders (1997).
There shall be no external lighting on the approved building or curtilage unless a lighting scheme and mitigation strategy is first submitted for approval to the Local Planning Authority, including measures to reduce light spillage onto foraging habitats for bats and to reduce light pollution. Such scheme as is approved in writing by the local planning authority shall not be added to without further consents being sought. The development shall be carried out in accordance with the approved details. Reason: To ensure that animal and plant species and habitats listed under the Conservation of Habitats and Species Regulations 2010 are adequately protected, and to protect and enhance the character and appearance of the site and its setting within the Pembrokeshire Coast National Park. Policy: Local Development Plan 2 - Policies 1 (National Park Purposes and Duty), 8 (Special Qualities), 9 (Light Pollution),12 (Local Areas of Nature Conservation or Sites of Geological Interest) and 14 (Conservation of the Pembrokeshire Coast National Park).
INFORMATIVE: SuDS Approving Body (SAB) Pembrokeshire County Council as SuDS Approving Body (SAB) considers that by virtue of the fact that the construction area having drainage implications appears to be in excess of 100 square metres / more than one property; the proposed works will require SAB approval prior to the commencement of any works on site relating to this application. The applicant should be made aware that if there is a breach of the requirement for SAB approval (i.e. when construction work is commenced without SAB approval); the SAB may at any time issue an enforcement notice. The failure to obtain SAB approval may have a detrimental effect upon the future sale of the properties, which could also result in insurance applications and or flood event settlements being compromised. Please see www.pembrokeshire.gov.uk/planning-contacts/sustainable-drainage-approving-bodysab for more information.
Related records
No related records were published in this section.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.