Council planning record

Extension to Caversham sand and gravel quarry with restoration to agriculture and flood plain habitats using suitable imported inert restoration material and construction of a new access off the A4155

Caversham Quarry, Sonning Eye, Reading, RG4 6TX

Application DecidedReference: MW.0158/11Oxfordshire County Council

Last published check: 28 Sept 2026, 21:05. Check the council record for more recent changes.

Application location

Caversham Quarry, Sonning Eye, Reading, RG4 6TX

This record has no verified map location.

Application summary

Status
Application Decided
Application type
Planning Application
Received
Not published
Validated
8 Dec 2011
Determination deadline
Not published
Local authority
Oxfordshire County Council

Application overview

Extension to Caversham sand and gravel quarry with restoration to agriculture and flood plain habitats using suitable imported inert restoration material and construction of a new access off the A4155

Proposal details

Reference
MW.0158/11
Agent
David L. Walker

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 136 of 136

DocumentPublishedAction
Approved under condition 8-Application Form dated 20/01/2021Application Documents1 Apr 2021View
Approved under condition 8-Sonning Quarry Phase C Statement to Discharge Condition 8, dated January 2021Application Documents1 Apr 2021View
Hydrometric Monitoring Report Data September 2019 to March 2020Application Documents23 Oct 2020View
Conditions 50 & 62 - Approved July 2017 - Revised Trigger Level DetailsApplication Documents16 Jan 2019View
Conditions 50 & 62 - Approved Hydrometric Monitoring Report Nov 2018Application Documents16 Jan 2019View
Conditions 50 & 62 - Approved July 2017 - Revised Recharge TrenchApplication Documents16 Jan 2019View
DP Approval Letter for Conds 50 & 62 dated 16/01/19Application Documents16 Jan 2019View
Conditions 50 & 62 - Approved Letter outlining Additional Mitigation Nov 2018Application Documents16 Jan 2019View
Conditions 50 & 62 - Approved Further information from applicant June 2018Application Documents16 Jan 2019View
DP Approval Letter Conds 52, 53, 54 & 55 dated 22/12/16Application Documents22 Dec 2016View
DP Approval Letter for Cond. 36 dated 22/12/16Application Documents22 Dec 2016View
DP Approval Letter for Conds 50 & 62 dated 22/12/16Application Documents22 Dec 2016View
DP Approval Letter for Cond. 21 dated 21/12/16Application Documents21 Dec 2016View
Decision NoticeApplication Documents19 Aug 2014View
Environmental Statement Volume 1 Environmental Statement Approved - Scheme of soils handling, management and replacement (Section 2.4) Dust Management Plan (paragraphs 2.6.2 - 2.6.4) Design Statement and Restoration Scheme (Section 3)Application Documents19 Aug 2014View
Section 106 legal agreementApplication Documents12 Aug 2014View
Additional Information September 2012 Appendix 3 - Addendum to Landscape and Visual Assessment August 2012 Part 1Application Documents7 Aug 2014View
Additional Information September 2012 Viewpoint 5 - Appendix 3 - Addendum to Landscape and Visual Assessment Part 7Application Documents7 Aug 2014View
Letter from DCLG 24/06/2014Application Documents25 Jun 2014View
Article 25 letterApplication Documents29 Jan 2014View
Representation - Mineral Products AssociationApplication Documents5 Nov 2013View
Sequential TestApplication Documents4 Nov 2013View
Consultation Response - Natural England Oct 2012Application Documents9 Oct 2013View
Consultation Response - Environment Agency final response Sept 2013Application Documents23 Sept 2013View
Letter from SEA to EAApplication Documents28 Jun 2013View
Letter from EA dated 5th June 2013Application Documents5 Jun 2013View
Consultation Response - Ecologist Planner Further Comments Otter SurveyApplication Documents5 Jun 2013View
Environment Agency Response 04.04.13 OttersApplication Documents4 Apr 2013View
Otter Report PhotosApplication Documents22 Mar 2013View
Applicant response to queries on infillApplication Documents22 Mar 2013View
Otter Report Figure 1Application Documents22 Mar 2013View
Environment Agency response to SEAG March 13Application Documents7 Mar 2013View
Abington Consulting further response March 2013Application Documents7 Mar 2013View
Ecologist Planner Response March 2013Application Documents7 Mar 2013View
Additional information letter 26/02/2013Application Documents28 Feb 2013View
SUPERSEDED - Details of plant site layoutApplication Documents28 Feb 2013View
Additional information letter (acoustic consultant) 21/02/2013Application Documents28 Feb 2013View
Non-Technical Summary part 1 of 12Application Documents19 Feb 2013View
Abington Consulting response to January 2013 consultationApplication Documents15 Feb 2013View
SEAG Response to January 2013 consultationApplication Documents13 Feb 2013View
Details of conveyor crossing over Spring LaneApplication Documents12 Feb 2013View
Letter from applicant responding to EA queriesApplication Documents12 Feb 2013View
Highways Authority response to further information - January 2013Application Documents1 Feb 2013View
Environmental Health Officer response to further information - January 2013Application Documents25 Jan 2013View
Non-Technical Summary part 7 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 9 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 2 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 4 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 6 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 1 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 11 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 10 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 12 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 3 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 5 of 12Application Documents17 Jan 2013View
Non-Technical Summary part 8 of 12Application Documents17 Jan 2013View
Environment Agency Response to further information - January 2013Application Documents16 Jan 2013View
Sonning Eye Parish Council response Oct 2012Application Documents24 Oct 2012View
Environment Agency Response 22.10.12Application Documents22 Oct 2012View
Ecologist Planner response October 2012Application Documents22 Oct 2012View
Environmental Health Officer response on amended scheme Oct 2012Application Documents19 Oct 2012View
Sonning and Sonning Eye Society ResponseApplication Documents11 Oct 2012View
Abington/SEAG response to further informationApplication Documents10 Oct 2012View
Additional Information September 2012 Appendix 5 Existing Features - Drawing No: C1/PL10/02Application Documents19 Sept 2012View
Additional Information Sept12 Appendix 2 - a) Flood Modelling Results b) Processing Plant FRAApplication Documents19 Sept 2012View
Additional Information September 2012 Appendix 5 Location Plan - Drawing No: C1/PL10/01Application Documents19 Sept 2012View
Additional Information Sept12 Appendix 1 - Sequential TestApplication Documents19 Sept 2012View
Additional Information Sept12 Appendix 4 - Addendum to Noise AssessmentApplication Documents19 Sept 2012View
Additional Information September 2012 Appendix 5 Restoration - Drawing No: C1/PL10/04Application Documents19 Sept 2012View
SUPERSEDED - Environmental Statement Volume 1 Working Proposals - Drawing No: C1/PL10/03Application Documents18 Sept 2012View
Lafarge letter dated 26 April responding to objections from SEAGApplication Documents3 Jul 2012View
Further Response from Environment Agency June 2012Application Documents22 Jun 2012View
Environment Agency response to Abington Consultants 15th May 2012Application Documents15 May 2012View
Environment Agency further response 14th May 2012Application Documents14 May 2012View
Further information from applicant following publication of National Planning Policy FrameworkApplication Documents25 Apr 2012View
Abington Consulting Engineers Further Letter 20 April 2012Application Documents20 Apr 2012View
Thames Water final responseApplication Documents17 Apr 2012View
Further Information on Landscape dated 4th April 2012Application Documents17 Apr 2012View
Environment Agency letter dated 5th April 2012Application Documents5 Apr 2012View
The Chilterns Conservation Board Response to Further InformationApplication Documents4 Apr 2012View
Abington Consulting Engineers - Objection letter on behalf of SEAG 19th MarchApplication Documents20 Mar 2012View
Abington Consulting Engineers - Objection letter on behalf of SEAG 25th JanApplication Documents20 Mar 2012View
Further Information from applicant -Response to objection by SEAG / Abington ConsultingApplication Documents16 Mar 2012View
Further Information from applicant - LVIA Supplementary Information DrawingApplication Documents8 Mar 2012View
Further Information from applicant - LVIA Supplementary InformationApplication Documents8 Mar 2012View
Environment Agency Second ResponseApplication Documents1 Mar 2012View
Chilterns Conservation Board ResponseApplication Documents28 Feb 2012View
Eye and Dunsden Parish Council responseApplication Documents28 Feb 2012View
Highway Authority Comments - Updated commentsApplication Documents23 Feb 2012View
Further information from applicant - letter to EAApplication Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2 Figure 2Application Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 1Application Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2 Figure 1Application Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2 Groundwater DataApplication Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2 Figure 3Application Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2Application Documents22 Feb 2012View
Further information from applicant - letter to EA Appendix 2 Water MonitoringApplication Documents22 Feb 2012View
Sonning Eye Action Group CommentsApplication Documents15 Feb 2012View
SODC ResponseApplication Documents13 Feb 2012View
Thames Water ResponseApplication Documents10 Feb 2012View
Natural England ResponseApplication Documents10 Feb 2012View
Environmental Health Officer ResponseApplication Documents8 Feb 2012View
Biodiversity and Landscape ResponseApplication Documents8 Feb 2012View
Sonning and Sonning Eye Society CommentsApplication Documents6 Feb 2012View
Highway Authority CommentsApplication Documents30 Jan 2012View
Environment Agency response 25/01/12Application Documents25 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 4 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 2 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 1- Hydrogeological Impact Assessment & Flood Risk AssessmentApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 7 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 5 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Response from Henley Town CouncilApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 6 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 4 Part 3 - Hydrogeological Impact Assessment & Flood RiskApplication Documents24 Jan 2012View
Annexure 4 part 1 - Hydrogeological and Flood Risk AssessmentApplication Documents24 Jan 2012View
Response from Shiplake Parish CouncilApplication Documents24 Jan 2012View
Environmental Statement Volume 2 Technical Reports Contents PageApplication Documents18 Jan 2012View
Consultation response - countryside accessApplication Documents12 Jan 2012View
Consultation response - BBOWTApplication Documents12 Jan 2012View
Consultation response - archaeologyApplication Documents12 Jan 2012View
Consultation response - rights of way field officerApplication Documents12 Jan 2012View
Environmental Statement Volume 2 Technical Reports Annexure 5 - Archaeological AssessmentApplication Documents29 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 2 Part 1 - Landscape and Visual Impact AssessmentApplication Documents19 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 2 Part 3 - Landscape and Visual Impact AssessmentApplication Documents19 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 2 Part 2 - Landscape and Visual Impact AssessmentApplication Documents19 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 3 - Agricultural Use and Quality, Soil Resources and DrainageApplication Documents19 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 9 - Market ApprasialApplication Documents19 Dec 2011View
Environmental Statement Volume 2 Technical Reports Annexure 1 - Scoping Response Letter from Oxfordshire County Council dated 12 October 2009Application Documents14 Dec 2011View
Environmental Statement Volume 1 Location Plan - Drawing No: C1/PL10/01Application Documents13 Dec 2011View
Environmental Statement Volume 1 Existing Features - Drawing No: C1/PL10/02Application Documents13 Dec 2011View
DP Approval agent letter MW.0008/21Application Documents1 Apr 2021View
Approved under MW.0111/20-- Covering Letter from David L Walker Ltd dated 03 November 2020 for a Non-material amendment to revise the working order of Phases 5 to 12 as stipulated in conditions 1, 8 and 9 of planning permission MW.0158/11 (P11/E2133/CM)Application Documents29 Dec 2020View
Approved under MW.0111-20-Email to Emma Bolster from Dan Walker dated 16 December 2020 titled “MW.0111/20 - Sonning Quarry NMA. Revised conditions 8 and 9” confirming further amendments to the working order of phases originally set out in NMA Covering letter dated 03 November 2020Application Documents29 Dec 2020View
Approved under MW.0111/20-Location Plan – Caversham Quarry Phase C Quarry Extension drawing noApplication Documents29 Dec 2020View
Approved under MW.0111/20-Approved Working Plan drawing noApplication Documents29 Dec 2020View
Decision notice with NMA agent approva letter MWApplication Documents29 Dec 2020View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Valid date

    Published milestoneCouncil source
  2. Determination Date

    Published milestoneCouncil source
  3. Consults Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Target committee date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Decision date

    Published milestoneCouncil source

Decision & conditions

Approved
Decision Notice Decision notice with NMA agent approva letter MW
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.