Council planning record

the importation, storage and processing of inert construction and demolition waste, and operation of an aggregate recycling facility on land at Shipton on Cherwell Quarry, Shipton on Cherwell, Oxfordshire. Retention of the existing weighbridge, site office and wheelwash to facilitate the operation of the proposed recycling facility

Shipton On Cherwell Quarry, Shipton-on-Cherwell, Oxfordshire

Application DecidedReference: MW.0119/11Oxfordshire County Council

Last published check: 28 Sept 2026, 14:53. Check the council record for more recent changes.

Application location

Shipton On Cherwell Quarry, Shipton-on-Cherwell, Oxfordshire

This record has no verified map location.

Application summary

Status
Application Decided
Application type
Planning Application
Received
Not published
Validated
26 Aug 2011
Determination deadline
Not published
Local authority
Oxfordshire County Council

Application overview

the importation, storage and processing of inert construction and demolition waste, and operation of an aggregate recycling facility on land at Shipton on Cherwell Quarry, Shipton on Cherwell, Oxfordshire. Retention of the existing weighbridge, site office and wheelwash to facilitate the operation of the proposed recycling facility

Proposal details

Reference
MW.0119/11
Agent
Kevin Parr

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 68 of 68

DocumentPublishedAction
Approved Offices and Parking Areas Plan - Drawing No. SHIPTSV1610 DG2 Rev A by NMA dated 01/03/17Application Documents1 Mar 2017View
Approved Lighting DocumentApplication Documents12 Feb 2015View
Approved Appendix F Reptile & Amphibian Translocation Method Statement (November 2009 Update)Application Documents12 Feb 2015View
Approved Appendix F Letter to Camilla BurrowApplication Documents12 Feb 2015View
Approved Appendix D Drainage PathsApplication Documents12 Feb 2015View
Approved Appendix C Transport StatementApplication Documents12 Feb 2015View
Approved Appendix C Cycle and Walking IsochronesApplication Documents12 Feb 2015View
Approved Appendix C Site Location PlanApplication Documents12 Feb 2015View
Approved Appendix C Site Layout Plan - Post PDi BuildingApplication Documents12 Feb 2015View
Approved Appendix C Bus Routes & TimetableApplication Documents12 Feb 2015View
Approved Appendix B Noise Monitoring Locations - Figure 2Application Documents12 Feb 2015View
Approved Appendix BApplication Documents12 Feb 2015View
EIA Screening OpinionApplication Documents17 Feb 2015View
Additional information 08/02/12 Phased scenario & traffic no.s 2.2.12 v2Application Documents8 Feb 2012View
Consultation Responses on additional info received 28.11.2011Application Documents27 Jan 2012View
Thames Water Consultation ResponseApplication Documents3 Jan 2012View
Oxford Green Belt Consultation ResponseApplication Documents3 Jan 2012View
OCC Archaeology Consultation Response 03/01/12Application Documents3 Jan 2012View
Network Rail Consultation ResponseApplication Documents3 Jan 2012View
MOD Consultation ResponseApplication Documents3 Jan 2012View
Highways Agency Consultation ResponseApplication Documents3 Jan 2012View
EA Consultation Response 29/12/11Application Documents3 Jan 2012View
CPRE Consultation ResponseApplication Documents3 Jan 2012View
Cherwell DC Planning Committee MinutesApplication Documents3 Jan 2012View
S73 Planning Application Letter from Agent dated 28.11.11Application Documents23 Dec 2011View
Cherwell DC EHO Consultation responseApplication Documents14 Oct 2011View
Site Layout Plan - Phased Operations PlanApplication Documents6 Sept 2011View
Decision Notice with NMA Approval letter dated 01/03/17Application Documents1 Mar 2017View
Approved Portacabin DimensionsApplication Documents12 Feb 2015View
Approved Agents letter confirming revised operational period of 10 years 27 February 2012Application Documents12 Feb 2015View
Approved Site Location PlanApplication Documents12 Feb 2015View
Approved Indicative Site Layout PlanApplication Documents12 Feb 2015View
Approved Appendix H Access Plan & Vehicle RoutingApplication Documents12 Feb 2015View
Approved Appendix C Local Road NetworkApplication Documents12 Feb 2015View
Approved Appendix C Advisory Lorry Routing SignApplication Documents12 Feb 2015View
Approved Appendix C Bunkers Hill DataApplication Documents12 Feb 2015View
Approved Appendix A Warrior 1400 Jack Up Screenbox SpecificationApplication Documents12 Feb 2015View
Revised HGV Shedule and Amendments to Drawings 27March2012Application Documents17 Apr 2012View
Departure FormApplication Documents17 Feb 2015View
Planning Application Boundary and Site OwnershipApplication Documents6 Sept 2011View
Approved Supporting Planning Statement Revision AApplication Documents12 Feb 2015View
Approved Development Construction Programme - Phase 1Application Documents12 Feb 2015View
Approved Boundary Plan - Drawing No. CRM 026 001 D002Application Documents12 Feb 2015View
Approved Application FormApplication Documents12 Feb 2015View
Approved Appendix G Green Belt StatementApplication Documents12 Feb 2015View
Approved Appendix F Reptile & Amphibian Risk AreasApplication Documents12 Feb 2015View
Approved Appendix E Landscape and Visual Impact StatementApplication Documents12 Feb 2015View
Approved Appendix D Flood Risk Assessment and Drainage StrategyApplication Documents12 Feb 2015View
Approved Appendix B Noise Level - Figure 3Application Documents12 Feb 2015View
Approved Appendix B Noise Impact AssessmentApplication Documents12 Feb 2015View
Approved Appendix A Terex Pegson XR400S SpecificationApplication Documents12 Feb 2015View
Approved Advisory Lorry Routing (October 2012)Application Documents12 Feb 2015View
Email Correspondance 22nd & 23rd March 2012Application Documents17 Apr 2012View
Change of ownership letterApplication Documents25 Apr 2012View
Additional information 08/02/12- Planning Application Letter 2.2.12Application Documents8 Feb 2012View
Shipton-on-Cherwell and Thrupp PC Consultation Response 27/01/2012Application Documents27 Jan 2012View
WODC Planning Consultation ResponseApplication Documents3 Jan 2012View
Shipton-on-Cherwell and Thrupp PC Consultation ResponseApplication Documents3 Jan 2012View
OCC Archaeology Consultation Response 14/09/11Application Documents3 Jan 2012View
Natural England Consultation ResponseApplication Documents3 Jan 2012View
Kidlington Parish Council Consultation ResponseApplication Documents3 Jan 2012View
Gosford and Water Eaton Parish Council Consultation ResponseApplication Documents3 Jan 2012View
EA Consultation Response 28/09/11Application Documents3 Jan 2012View
Cherwell DC Consultation ResponseApplication Documents3 Jan 2012View
BBOWT Consultation ResponseApplication Documents14 Oct 2011View
OCC Drainage Consultation ResponseApplication Documents14 Oct 2011View
Site Layout Plan - Post PDI BuildingApplication Documents6 Sept 2011View
Statement of Community InvolvementApplication Documents6 Sept 2011View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Valid date

    Published milestoneCouncil source
  2. Consults Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  3. Determination Date

    Published milestoneCouncil source
  4. Target committee date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Decision date

    Published milestoneCouncil source

Decision & conditions

Approved
Decision Notice with NMA Approval letter dated 01/03/17
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.