Council planning record

Proposed extension to the consented Astley Gorse Solar Farm (PAP/2021/0651) to include ground mounted solar PV panels, ancillary infrastructure and equipment, landscaping and access arrangements

Land North Of Park Lane Farm Park Lane Astley

Application ApprovedReference: PAP/2024/0577North Warwickshire Borough Council

Last published check: 10 Oct 2026, 08:58. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Issue Date

    Published milestoneCouncil source

Application summary

Status
Application Approved
Application type
Not published
Received
20 Dec 2024
Validated
Not published
Determination deadline
Not published
Local authority
North Warwickshire Borough Council

Application overview

Proposed extension to the consented Astley Gorse Solar Farm (PAP/2021/0651) to include ground mounted solar PV panels, ancillary infrastructure and equipment, landscaping and access arrangements

Proposal details

Reference
PAP/2024/0577
Agent
Mr Steve Boundy

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Land North Of Park Lane Farm Park Lane Astley

This record has no verified map location.

Documents 63 of 63

DocumentPublishedAction
Decision Notice- RedactedDecisionNot publishedView
23-684 Astley Gorse II Solar PV Scheme, Astley - Noise Assessment for Planning v5 ArBy ISSUEPlansNot publishedView
AEM044-SP-01_rev03 Site Location Plan- ApprovedLocation PlanNot publishedView
Astley Gorse Solar Farm Extension - BNG plan 4.12.24PlansNot publishedView
LVIA Astley Gorse - Appendix 8.1 Landscape Plans - Rev D_Part1PlansNot publishedView
LVIA Astley Gorse - Appendix 8.1 Landscape Plans - Rev D_Part2PlansNot publishedView
AEM044-PL-01_rev04 Proposed Site Layout Plan- ApprovedPlansNot publishedView
23-684 Astley Gorse II Solar PV Scheme Astley - Noise Assessment for Planning v4 ISSUEPlansNot publishedView
AEM044-PL-00_rev03 Existing Site Layout PlanPlansNot publishedView
SPP06 Mitigation Plan D- ApprovedPlansNot publishedView
2399-R003 - Astley Gorse Solar Farm Extension - Planning Statement v3PlansNot publishedView
2401-028_CTMP01_Astley Gorse Solar FarmSupporting DocumentsNot publishedView
Astley Gorse Solar Farm Extension - Skylark mitigation strategy 10.02.25.Supporting DocumentsNot publishedView
LC2798_1 - Astley Gorse Solar Farm Extension FRA AddendumSupporting DocumentsNot publishedView
2399-6491 - Astley Gorse II - Greybelt updateSupporting DocumentsNot publishedView
2399-6492 - Astley Gorse II - Cumulative Impacts Note Revision 2Supporting DocumentsNot publishedView
Board report 20 May 2025Supporting DocumentsNot publishedView
Appendix F - Ground Elevation ProfileSupporting DocumentsNot publishedView
Appendix G - Solar Module Glare and Reflectance Technical MemoSupporting DocumentsNot publishedView
Astley Gorse Extension - SCI v1.1Supporting DocumentsNot publishedView
Astley Gorse Solar Farm Extension - BBS report 12.12.24Supporting DocumentsNot publishedView
Astley Gorse Solar Farm Extension - EcIA 12.12.24Supporting DocumentsNot publishedView
Astley Gorse Solar Farm Extension - GCN surveys 4.12.24Supporting DocumentsNot publishedView
2399-R004 - Astley Gorse Solar Farm Extension - Design and Access Statement v5Supporting DocumentsNot publishedView
2399-R005 - Astley Gorse Solar Farm Extension - Greenbelt Assessment v4Supporting DocumentsNot publishedView
Glint and Glare AssessmentSupporting DocumentsNot publishedView
The_Statutory_Biodiversity_Metric_Calculation_Tool_-_Macro_enabled_tool_23.07.2024(1)Supporting DocumentsNot publishedView
AOC Report__40842_Astley Gorse__archaeological_geophysical_report_v03_Part1Supporting DocumentsNot publishedView
AOC Report__40842_Astley Gorse__archaeological_geophysical_report_v03_Part2Supporting DocumentsNot publishedView
P24-209_Astley Gorse_solar_farm_extension_DBA_v1.2wr_issued_06122024_Part1Supporting DocumentsNot publishedView
RC2798_2 - Astley Gorse Solar Farm Extension FRA-FULL_Part2Supporting DocumentsNot publishedView
RC2798_2 - Astley Gorse Solar Farm Extension FRA-FULL_Part3Supporting DocumentsNot publishedView
RC2798_2 - Astley Gorse Solar Farm Extension FRA-FULL_Part4Supporting DocumentsNot publishedView
AEM044-SD-01_rev02-20ft Solar Inverter- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-02_rev01-Deer Fence and Gate- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-03_rev01-Access Track- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-04_rev01-CCTV Camera- ApprovedSupporting DocumentsNot publishedView
Arboricultural Impact Assessment BHA_5969_AIA_Astley Gorse Solar Farm Extension_JR_December_2024Supporting DocumentsNot publishedView
C1093_v3 - ALC Astley Gorse Solar Farm ExtensionSupporting DocumentsNot publishedView
Figure 1 - Residential ReceptorsSupporting DocumentsNot publishedView
Figure 2 - Road ReceptorsSupporting DocumentsNot publishedView
Figure 3 - Rail ReceptorsSupporting DocumentsNot publishedView
Figure 4 - Proposed MitigationSupporting DocumentsNot publishedView
Figure 5 - Coventry Airport Aerodrome ChartSupporting DocumentsNot publishedView
Figure 6 - Birmingham Airport Aerodrome ChartSupporting DocumentsNot publishedView
LVIA Astley Gorse - Rev DSupporting DocumentsNot publishedView
2399-R002 - Astley Gorse Solar Farm Extension - Submission Drawing PackSupporting DocumentsNot publishedView
2401-028_CTMP01_Astley Gorse Solar FarmSupporting DocumentsNot publishedView
AEM044-SD-05_rev01-40ft Storage Container- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-06_rev01-40ft Customer Switchgear- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-07_rev01-DNO Substation- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-08_rev03-PV Detail- ApprovedSupporting DocumentsNot publishedView
AEM044-SD-09_rev01-Palisade Fence and Gate- ApprovedSupporting DocumentsNot publishedView
P24-209_Astley Gorse_solar_farm_extension_DBA_v1.2wr_issued_06122024_Part2Supporting DocumentsNot publishedView
RC2798_2 - Astley Gorse Solar Farm Extension FRA-FULL_Part1Supporting DocumentsNot publishedView
2399-R001 Astley Gorse Solar Farm Extension Submission LetterSupporting DocumentsNot publishedView
Appendix B - Residential Receptor Glare ResultsSupporting DocumentsNot publishedView
Appendix C - Road Receptor Glare ResultsSupporting DocumentsNot publishedView
Appendix D - Aviation Receptor Glare ResultsSupporting DocumentsNot publishedView
Appendix E - Visibility Assessment EvidenceSupporting DocumentsNot publishedView
Board report - February 2025Supporting DocumentsNot publishedView
Appendix 8.3 Viewpoint Photomontages Rev BPhotographNot publishedView
Application Form-Not publishedView

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Granted Subject to Conditions
Decision Notice- Redacted
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.