Installation and operation of a battery energy storage system (BESS) facility incorporating batteries, transformers, inverters, switchrooms, substation, water tank, other associated infrastructure plus cable ducts, fencing, access track, landscaping and drainage infrastructure.

Land North Of Stevenage Road Titmore Green Little Wymondley Hertfordshire

UnknownReference: 25/01349/FPNorth Hertfordshire District Council

Last published check: 1 Oct 2026, 20:29. Check the council record for more recent changes.

Application location

Land North Of Stevenage Road Titmore Green Little Wymondley Hertfordshire

This record has no verified map location.

View council map

Application summary

Status
Unknown
Application type
Full Planning Permission
Received
20 May 2025
Validated
20 May 2025
Determination deadline
Not published
Local authority
North Hertfordshire District Council

Application overview

Installation and operation of a battery energy storage system (BESS) facility incorporating batteries, transformers, inverters, switchrooms, substation, water tank, other associated infrastructure plus cable ducts, fencing, access track, landscaping and drainage infrastructure.

Proposal details

Reference
25/01349/FP
Alternative references
PP-13920241
Ward
Graveley, St Ippolyts And Wymondley Ward
Parish
Wymondley Parish Council
Agent
Mrs Jennifer Gordon

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 58 of 58

DocumentPublishedAction
HCC Lead Local Flood Authority Consultee ResponseConsultee Response PublishedNot publishedView
CPRE Consultee ResponseConsultee Response PublishedNot publishedView
NHC Environmental Health (Contaminated Land and Air) Consultee ResponseConsultee Response PublishedNot publishedView
Environmental Agency Consultee ResponseConsultee Response PublishedNot publishedView
Place Services Consultee ResponseConsultee Response PublishedNot publishedView
HCC Highways Consultee ResponseConsultee Response PublishedNot publishedView
HCC Archaeological Consultee ResponseConsultee Response PublishedNot publishedView
NHC Ecologist Consultee ResponseConsultee Response PublishedNot publishedView
Consultee Response - National GasConsultee Response PublishedNot publishedView
Natural England Consultee ResponseConsultee Response PublishedNot publishedView
Site NoticeSite NoticeNot publishedView
National Gas Consultee ResponseConsultee Response PublishedNot publishedView
HCC - Fire Service and Protection Consultee Response (Attachment 1)Consultee Response PublishedNot publishedView
Flood Risk Assessment and Surface Water Drainage Strategy_Part-3Supporting DocumentsNot publishedView
Flood Risk Assessment and Surface Water Drainage Strategy_Part-2Supporting DocumentsNot publishedView
Flood Risk Assessment and Surface Water Drainage Strategy_Part-1Supporting DocumentsNot publishedView
Outline Fire Risk Safety StatementSupporting DocumentsNot publishedView
Arboricultural Impact AssessmentSupporting DocumentsNot publishedView
Historic Environment Desk-Based AssessmentSupporting DocumentsNot publishedView
Noise Impact AssessmentSupporting DocumentsNot publishedView
L100-Rev A - Landscape Strategy PlanPlansNot publishedView
Sequential and Alternative Sites Appraisal Assessment_Part-1Supporting DocumentsNot publishedView
Sequential and Alternative Sites Appraisal Assessment_Part-2Supporting DocumentsNot publishedView
Sequential and Alternative Sites Appraisal Assessment_Part-3Supporting DocumentsNot publishedView
Construction Traffic Mangement PlanSupporting DocumentsNot publishedView
Landscape and Visual AppraisalSupporting DocumentsNot publishedView
L101-Rev-A - Landscape SpecificationsSupporting DocumentsNot publishedView
Planning Design and Access Statement_Part-1Supporting DocumentsNot publishedView
Planning Design and Access Statement_Part-2Supporting DocumentsNot publishedView
Planning Design and Access Statement_Part-3Supporting DocumentsNot publishedView
Cover Letter_FINALSupporting DocumentsNot publishedView
Ecological Impact Assessment _ Part-1Supporting DocumentsNot publishedView
Ecological Impact Assessment _ Part-2Supporting DocumentsNot publishedView
WYM-EDFR-BESS-LAND-PLN-150.05 - Site Location PlanPlansNot publishedView
Application Form RedactedApplication FormsNot publishedView
402.065238.00001.0023.1 - Site Location - Strategic PlanPlansNot publishedView
402.065238.00001.0026.1 - Block PlanPlansNot publishedView
402-065238-00001-CIV-001-Rev-P04 - Proposed Site LevelsPlansNot publishedView
402-065238-00001-CIV-002-Rev-P02 - Proposed Site SectionsPlansNot publishedView
402-065238-00001-CIV-003-Rev-P02 - Proposed Site ElevationsPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-360.00 - PCS and Transformer ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-361.00 - Battery ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-362.01 - Spare Parts Container ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-363.00 - DNO Incomer Substation ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-364.00 - Fencing Gate and CCTV ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-365.01 - BESS 33kV Switch Room ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-366.00 - Auxiliary and Earthing Transformer ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-367.01 - LV Switch Room Control Room and Welfare Unit ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-369.00 - EV Charge Point ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-369.01 - Water Tank ArrangementPlansNot publishedView
WYM-EDFR-BESS-ARC-DRG-372.00 - Harmonic Filter ArrangementPlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-250.11 - Site Constraints PlanPlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-300.08 - Site Layout PlanPlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-340.02 - Site Cable Route - Sheet 1PlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-341.02 - Site Cable Route - Sheet 2PlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-342.02 - Site Cable Route - Sheet 3PlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-343.02 - Site Cable Route - Sheet 4PlansNot publishedView
WYM-EDFR-BESS-CIV-PLN-344.02 - Site Cable Route - Sheet 5PlansNot publishedView

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Decision Issued Date

    Published milestoneCouncil source
  8. Decision Made Date

    Published milestoneCouncil source
  9. Permission Expiry Date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Withdrawn
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.