Council planning record

Demolition of existing structures and erection of a Sustainable Aviation Fuel (SAF) production facility, including the production of green hydrogen and sustainable diesel, enclosed ground flare, storage tanks, installation of pipework and electrical, processing and utility equipment, administration, warehouse and laboratory buildings, new access, car parking and transport infrastructure including a truck loading area and associated works, hard and soft landscaping, areas for temporary construction laydown, and associated development.

Crown Wharf Port Talbot Docks Port Talbot SA13 1RA

WithdrawnReference: P2023/0858Neath Port Talbot County Borough Council

Last published check: 4 Oct 2026, 00:12. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Environmental Impact Assessment Received

    Published milestoneCouncil source
  2. Application Received Date

    Published milestoneCouncil source
  3. Application Validated Date

    Published milestoneCouncil source
  4. Last Site Notice Posted Date

    Published milestoneCouncil source
  5. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  6. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Standard Consultation Date

    Published milestoneCouncil source
  9. Last Advertised In Press Date

    Published milestoneCouncil source
  10. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  11. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  12. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  13. Agreed Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  14. Decision Issued Date

    Published milestoneCouncil source
  15. Decision Made Date

    Published milestoneCouncil source

Application summary

Status
Withdrawn
Application type
Full Plans
Received
13 Nov 2023
Validated
13 Nov 2023
Determination deadline
3 Mar 2024
Local authority
Neath Port Talbot County Borough Council

Application overview

Demolition of existing structures and erection of a Sustainable Aviation Fuel (SAF) production facility, including the production of green hydrogen and sustainable diesel, enclosed ground flare, storage tanks, installation of pipework and electrical, processing and utility equipment, administration, warehouse and laboratory buildings, new access, car parking and transport infrastructure including a truck loading area and associated works, hard and soft landscaping, areas for temporary construction laydown, and associated development.

Proposal details

Reference
P2023/0858
Ward
Margam & Taibach
Parish
Port Talbot
Agent
Turley

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Crown Wharf Port Talbot Docks Port Talbot SA13 1RA

This record has no verified map location.

View council map

Documents 274 of 274

DocumentPublishedAction
Decision NoticeDecisionNot publishedView
COMMITTEE REPORT Application Number P20230858 - Crown Wharf Port Talbot DocksDecisionNot publishedView
Proposed Zone 6 Plant Elevations - Process Modules - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0506 - P8 - 6th November 2023Drawings - PlansNot publishedView
Site Location Plan - EIA Boundary Shown - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0227 - P9 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 14 Plant Elevations - Sub. 2000 & Liq. Nitr. St. - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0514 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 13 Plant Elevations - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0513 - P6 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 1) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0201 - P8 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 2) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0202 - P9 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Key Plan - EIA Boundary Shown - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0228 - P8 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Key Plan - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0200 - P11 - 6th November 2023Drawings - PlansNot publishedView
Proposed Amenity Shelter 1 Plans and Elevations - Project Dragon - 2143.01-IA-10-ZZ-DR-A-0300 - P3 - 6th November 2023Drawings - PlansNot publishedView
Proposed Amenity Shelter 2 Plans and Elevations - Project Dragon - 2143.01-IA-11-ZZ-DR-A-0300 - P3 - 6th November 2023Drawings - PlansNot publishedView
Proposed Gatehouse 2 Plans and Elevations - Project Dragon - 2143.01-IA-04-ZZ-DR-A-0300 - P7 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Sections - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0400 - P9 - 6th November 2023Drawings - PlansNot publishedView
Proposed Admin Building Plans and Elevations - Project Dragon - 2143.01-IA-09-ZZ-DR-A-0300 - P8 - 6th November 2023Drawings - PlansNot publishedView
Proposed Laboratory Plans and Elevations - Project Dragon - 2143.01-IA-02-ZZ-DR-A-0300 - P8 - 6th November 2023Drawings - PlansNot publishedView
Proposed Process Control Building Elevations - Project Dragon - 2143.01-IA-01-ZZ-DR-A-0301 - P7 - 6th November 2023Drawings - PlansNot publishedView
Proposed PDZ Layout & Equipment List - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0215 - P18 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 4) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0204 - P9 - 6th November 2023Drawings - PlansNot publishedView
Proposed Process Control Building Plans - Project Dragon - 2143.01-IA-01-ZZ-DR-A-0300 - P7 - 6th November 2023Drawings - PlansNot publishedView
Proposed PDZ Layout - External Surface Finishes - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0216 - P8 - 6th Nov 2023Drawings - PlansNot publishedView
Proposed Site Key Plan - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0210 - P14 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Sections - Sheet 1 of 2 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0401 - P11 - 6th November 2023Drawings - PlansNot publishedView
Proposed Warehouse Store Elevations - Project Dragon - 2143.01-IA-06-ZZ-DR-A-0301 - P1 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 3 Plant Elevations - Substation 3000 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0502 - P7 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 4 Plant Elevations - Tanker Loading - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0503 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 11 Plant Elevations - Metering & Water Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0511 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 12 Plant Elevations - Water Package & Tank - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0512 - P6 - 6th November 2023Drawings - PlansNot publishedView
Site Location Plan - Ownership Boundaries - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0101 - P8 - 6th November 2023Drawings - PlansNot publishedView
Site Location Plan - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0100 - P13 - 6th November 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 3) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0203 - P8 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Fencing Layout - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0240 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Plan - PDZ & Temp. Construction Areas - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0217 - P10 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 2) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0212 - P15 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Key Plan - EIA Boundary Shown - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0220 - P13 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 3) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0213 - P13 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 1) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0211 - P13 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 4) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0214 - P15 - 6th November 2023Drawings - PlansNot publishedView
Proposed Site Sections - Sheet 2 of 2 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0402 - P11 - 6th November 2023Drawings - PlansNot publishedView
Proposed Warehouse Store Plans - Project Dragon - 2143.01-IA-06-ZZ-DR-A-0300 - P8 - 6th November 2023Drawings - PlansNot publishedView
Proposed Workshop Plans and Elevations - Project Dragon - 2143.01-IA-05-ZZ-DR-A-0300 - P9 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 1 Plant Elevations - Enclosed Ground Flare - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0500 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 2 Plant Elevations - Collection Basin - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0501 - P7 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 10 Plant Elevations - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0510 - P8 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 9 Plant Elevations - Hydrogen Generation - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0509 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 7 Plant Elevations - Sustainable Aviation Fuel Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0507 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 5 Plant Elevations - Ethanol Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0505 - P6 - 6th November 2023Drawings - PlansNot publishedView
Proposed Zone 8 Plant Elevations - Sustainable Diesel Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0508 - P6 - 6th November 2023Drawings - PlansNot publishedView
LANT3006 - Green Infrastructure Statement - 6 February 2024Supporting DocumentNot publishedView
Project Dragon - NRW Clarification Note - 6 February 2024Supporting DocumentNot publishedView
Project Dragon - NPT Clarification Note - 6 February 2024Supporting DocumentNot publishedView
ES V2 Appendix 13.1 Evaluation of Marine Ecology Effects - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
Archaeological and Heritage Assessment - Project Dragon - edp7470_r003 - Aug 2023 - Part 1Supporting DocumentNot publishedView
Transport Assessment - Project Dragon - CT-220352-TA-04_04 - Nov 2023 - Part 2Supporting DocumentNot publishedView
Site Location Plan - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0100 - P13 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 3 Plant Elevations - Substation 3000 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0502 - P7 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 6 Plant Elevations - Process Modules - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0506 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 7 Plant Elevations - Sustainable Aviation Fuel Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0507 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Warehouse Store Plans - Project Dragon - 2143.01-IA-06-ZZ-DR-A-0300 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Workshop Plans and Elevations - Project Dragon - 2143.01-IA-05-ZZ-DR-A-0300 - P9 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Sections - Sheet 1 of 2 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0401 - P11 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Fencing Layout - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0240 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Key Plan - EIA Boundary Shown - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0220 - P13 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 2) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0212 - P15 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed PDZ Layout Equipment List - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0215 - P18 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Process Control Building Plans - Project Dragon - 2143.01-IA-01-ZZ-DR-A-0300 - P7 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Amenity Shelter 2 Plans and Elevations - Project Dragon - 2143.01-IA-11-ZZ-DR-A-0300 - P3 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Gatehouse 1 Plans and Elevations - Project Dragon - 2143.01-IA-03-ZZ-DR-A-0300 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Cycle Store Plans and Elevations - Project Dragon - 2143.01-IA-12-ZZ-DR-A-0300 - P3 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Amenity Shelter 1 Plans and Elevations - Project Dragon - 2143.01-IA-10-ZZ-DR-A-0300 - P3 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Key Plan - Project Dragon- 2143.01-IA-ZZ-ST-DR-A-0200 - P11 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 4) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0204 - P9 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 2) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0202 - P9 - 6 Nov 2023Drawings - PlansNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 1Supporting DocumentNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 1Supporting DocumentNot publishedView
PDZ GI Report - Project Dragon - 2111006.003.01D - Aug 2023 - Part1Supporting DocumentNot publishedView
PDZ GI Report - Project Dragon - 2111006.003.01D - Aug 2023 - Part3Supporting DocumentNot publishedView
PDZ GI Desk Study - Project Dragon - 2111006.002.01G - Oct 2023 - Part4Supporting DocumentNot publishedView
PDZ GI Desk Study - Project Dragon - 2111006.002.01G - Oct 2023 - Part1Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 6Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 5Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 1Supporting DocumentNot publishedView
Odour Briefing Note - Project Dragon - Rev 1 - 7 July 2023Supporting DocumentNot publishedView
Margam Wharf GI Report - Project Dragon - 2111006.006.02A - Oct 2023 - Part 2Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part5Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part1Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part6Supporting DocumentNot publishedView
Lighting Assessment and Strategy - Project Dragon - Oct 2023Supporting DocumentNot publishedView
Green Infrastructure and Landscape Strategy - Project Dragon - edp7470_d010-O - Nov 2023Supporting DocumentNot publishedView
Geoenvironmental Assessment - Project Dragon - 2111006.005.01B - Oct 2023Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 5Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 2Supporting DocumentNot publishedView
ES V2 Appendix 13.2 UWN Modelling Report - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 2.1 EIA Scoping Report - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.29 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.28 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.27 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.22 - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.21 - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.19 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.20 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.17 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.14 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.2.5 LANDMAP Cultural Landscape - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 8.2.3 LANDMAP Visual and Sensory - Project Dragon - 08 November r 2023Supporting DocumentNot publishedView
ES V1 Figure 8.5 Townscape Designations - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 8.2.1 LANDMAP Geological Landscapes - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 7.2 Habitat Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.13 Proposed Site Plan (Area 4) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.7 Proposed Site Plan - PDZ Temporary Construction Area - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.1 Site Location Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.3 Existing Site Plan (Area 1) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.4 Existing Site Plan (Area 2) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Contents Page - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 14 Assessment of Cumulative Effects - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 11 Air Quality - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 9 Socio-Economics and Human Health - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 6 Major Accidents and Disasters - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 5 Consideration of Alternatives - Project Dragon - 08 NovSupporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 3Supporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 2Supporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 6Supporting DocumentNot publishedView
Detailed UXO Assessment - Project Dragon - DRA-23-1532 - Rev. 2 - Sept 2023_Part1Supporting DocumentNot publishedView
Design and Access Statement - Project Dragon - 2143.01-IA-XX-XX-RP-A-0910 P11 - Part 1Supporting DocumentNot publishedView
Design and Access Statement - Project Dragon - 2143.01-IA-XX-XX-RP-A-0910 P11 - Part 3Supporting DocumentNot publishedView
Archaeological and Heritage Assessment - Project Dragon - edp7470_r003 - Aug 2023 - Part 2Supporting DocumentNot publishedView
Arboricultural Baseline Note - Project Dragon - edp7470_r002-E - Oct 2023Supporting DocumentNot publishedView
Transport Assessment - Project Dragon - CT-220352-TA-04_04 - Nov 2023 - Part 5Supporting DocumentNot publishedView
Transport Assessment - Project Dragon - CT-220352-TA-04_04 - Nov 2023 - Part 1Supporting DocumentNot publishedView
Sustainability and Energy Statement - Project Dragon - Rev I - 1 Nov 2023Supporting DocumentNot publishedView
Economic and Social Value Statement - Project Dragon - Nov 2023 (1)Supporting DocumentNot publishedView
Proposed Zone 10 Plant Elevations - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0510 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 14 Plant Elevations - Project Dragon - 2143.01-IA-ZZ-DR-A-0514 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Site Location Plan - Ownership Boundaries - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0101 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 9 Plant Elevations - Hydrogen Generation - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0509 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 12 Plant Elevations - Water Package Tank - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0512 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 13 Plant Elevations - Project Dragon -2143.01-IA-ZZ-ZZ-DR-A-0513 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 11 Plant Elevations - Metering Water Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0511 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 3) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0213 - P13 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 4 Plant Elevations - Tanker Loading - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0503 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 2 Plant Elevations - Collection Basin - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0501 - P7 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Process Control Building Elevations - Project Dragon - 2143.01-IA-01-ZZ-DR-A-0301 - P7 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Warehouse Store Elevations - Project Dragon - 2143.01-IA-06-ZZ-DR-A-0301 - P1 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Plan - PDZ Temp Construction Areas - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0217 - P10 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Key Plan - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0210 - P14 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Laboratory Plans and Elevations - Project Dragon - 2143.01-IA-02-ZZ-DR-A-0300 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Gatehouse 2 Plans and Elevations - Project Dragon - 2143.01-IA-04-ZZ-DR-A-0300 - P7 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Admin Building Plans and Elevations -Project Dragon - 2143.01-IA-09-ZZ-DR-A-0300 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Key Plan - Project Dragon - EIA Boundary Shown - 2143.01-IA-ZZ-ST-DR-A-0228 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 1) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0201 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Plan (Area 3) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0203 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 2Supporting DocumentNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 2Supporting DocumentNot publishedView
PDZ GI Desk Study - Project Dragon - 2111006.002.01G - Oct 2023 - Part2Supporting DocumentNot publishedView
PDZ GI Desk Study - Project Dragon - 2111006.002.01G - Oct 2023 - Part5Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 4 Appendix CSupporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 2Supporting DocumentNot publishedView
Margam Wharf GI Report - Project Dragon - 2111006.006.02A - Oct 2023 - Part 3Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part4Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part2Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 4Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 6Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 3Supporting DocumentNot publishedView
Fire Strategy Report - Project Dragon - PJD-PTB-ZZ-XX-RP-FE-1001 - Issue 2 - Nov 2023Supporting DocumentNot publishedView
FCEMP - Project Dragon - 8 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 8.2 Ocean CGI AVR Supporting doc Method Statement - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 8.1 LVIA Appendix 6 - Supporting Figures - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 7.1 Preliminary Ecological Appraisal - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 12.2 Operational Noise Impact Assessment - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 12.3 Construction Noise Impact Assessment - Project Dragon - 08 Nov2023Supporting DocumentNot publishedView
ES V4 Non-Technical Summary - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 7.2 Phase 2 Species Survey Report - Project Dragon - 08 Nov 2023 Part 1Supporting DocumentNot publishedView
ES V3 Environmental Management Plan - Project Dragon - 08 Nov 2023-1Supporting DocumentNot publishedView
ES V1 Figure 14.1 Location of Approved Projects - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 14.1 Approved Projects ZOI - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 13.1 The Marine Ecology Study Area - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 6.1 HSE Design Philosophy - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 9.1 Supply Chain Employment - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 2.3 Natural Resource Wales (NRW) Response - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 1.1 Statement of Technical Competence - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 12.1 Noise Survey and Receptor Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.15 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.12 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.13 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.11 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.9 Summer Viewpoint Photography - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.7 ZTV 5km - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.8 Representative viewpoint location - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 9.1 Socio-Economic Study Area Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.6 Landform and features - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 11.7 Location of Monitoring Sites in Port Talbot - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.6 Building and Emission Stack Locations- Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.2 Ecological Receptors - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.1 Human Receptors - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.5 Terrain Data Used in Modelling - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.3 Kenfig SAC SSSI Receptors used in Roads Modelling - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.9 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.8 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.4 Wind Rose for Mumbles Head 2018 - 2022 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.10 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.16 Green Infrastructure and Landscape Strategy - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 7.1 Harbourside Site Areas Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.2.4 LANDMAP Historic Landscape - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 8.3 Borough Landscape Character Areas - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 8.2.2 LANDMAP Landscape Habitats - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Figure 8.1 Site Location and Study Area - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 7.3 TCA East Building Location Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 5.1 Alternative Sites - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.15 External Lighting Layout Drawing - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.8 Proposed PDZ Layout - EIA Boundary Shown - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.14 Proposed PDZ Layout - External Surface Finishes - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.12 Proposed Site Plan (Area 3) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.2 Existing Site Key Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.10 Proposed Site Plan (Area 1) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.11 Proposed Site Plan (Area 2) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.6 Existing Site Plan (Area 4) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 4.5 Existing Site Plan (Area 3) - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 12 Noise and Vibration - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 13 Marine Ecology - Project Dragon - 08 November 2023Supporting DocumentNot publishedView
ES V1 Chapter 10 Climate Change - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 7 Terrestrial Ecology - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 4 Development Specification - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 2 Approach to EIA - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 3 Site Context - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 1 Introduction - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 5Supporting DocumentNot publishedView
Waste Management Plan - Project Dragon - R6716-IE-0006 - Issue A8 - 9 Nov 2023Supporting DocumentNot publishedView
Transport Assessment - Project Dragon - CT-220352-TA-04_04 - Nov 2023 - Part 4Supporting DocumentNot publishedView
Transport Assessment - Project Dragon - CT-220352-TA-04_04 - Nov 2023 - Part 3Supporting DocumentNot publishedView
Site Location Plan - EIA Boundary Shown - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0227 - P9 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 5 Plant Elevations - Ethanol Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0505 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 8 Plant Elevations - Sustainable Diesel Tanks - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0508 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Sections - Sheet 2 of 2 - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0402 - P11 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 4) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0214 - P15 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Zone 1 Plant Elevations - Enclosed Ground Flare - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0500 - P6 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed Site Plan (Area 1) - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0211 - P13 - 6 Nov 2023Drawings - PlansNot publishedView
Proposed PDZ Layout - External Surface Finishes - Project Dragon - 2143.01-IA-ZZ-ST-DR-A-0216 - P8 - 6 Nov 2023Drawings - PlansNot publishedView
Existing Site Sections - Project Dragon - 2143.01-IA-ZZ-ZZ-DR-A-0400 - P9 - 6 Nov 2023Drawings - PlansNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 3Supporting DocumentNot publishedView
Pre-Application Consultation Report - Project Dragon - Rev B - Oct 2023 - Part 3Supporting DocumentNot publishedView
Planning Statement - Project Dragon - 8 Nov 2023Supporting DocumentNot publishedView
PDZ GI Report - Project Dragon - 2111006.003.01D - Aug 2023 - Part2Supporting DocumentNot publishedView
PDZ GI Desk Study - Project Dragon - 2111006.002.01G - Oct 2023 - Part3Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 3Supporting DocumentNot publishedView
Outline Drainage Strategy - Project Dragon - Rev F - Nov 2023 - Part 4Supporting DocumentNot publishedView
Margam Wharf GI Report - Project Dragon - 2111006.006.02A - Oct 2023 - Part 1Supporting DocumentNot publishedView
Margam Wharf GI Desk Study - Project Dragon - 2111006.006.01C - Oct 2023 - Part3Supporting DocumentNot publishedView
Flood Consquences Assessment - Project Dragon - Rev G - Nov 2023 - Part 1Supporting DocumentNot publishedView
ES V2 Appendix 7.3 BBS WBS Assessment Report - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 11.1 - 11.8 Air Quality Appendices - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 12.1 Baseline Noise Survey - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 2.4 Water Framework Directive Assessment - Project Dragon - 08 Nov 23Supporting DocumentNot publishedView
ES V2 Appendix 7.5 Invertebrate Survey 2023 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 7.4 Invertebrate Assessment - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 2.2 Environmental Topics which are Not Significant - Project Dragon- 08 Nov 2023Supporting DocumentNot publishedView
ES V2 Appendix 7.2 Phase 2 Species Survey Report - Project Dragon - 08 Nov 2023 Part 2Supporting DocumentNot publishedView
ES V1 Figure 11.30 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.26 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.25 - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.24 - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.23 - Project Dragon -08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.18 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 11.16 - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Figure 8.4 Local Landscape Character Areas - Project Dragon - 08 November2023Supporting DocumentNot publishedView
ES V1 Figure 4.9 Proposed Site Key Plan - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 8 Landscape and Visual - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
ES V1 Chapter 15 Summary of ES - Project Dragon - 08 Nov 2023Supporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 4Supporting DocumentNot publishedView
EcIA - Project Dragon - Rev 2 - Nov 2023 - Part 1Supporting DocumentNot publishedView
Detailed UXO Assessment - Project Dragon - DRA-23-1532 - Rev. 2 - Sept 2023_Part2Supporting DocumentNot publishedView
Design and Access Statement - Project Dragon - 2143.01-IA-XX-XX-RP-A-0910 P11 - Part 2Supporting DocumentNot publishedView
Covering Letter - Project Dragon - 16 Nov 2023Supporting DocumentNot publishedView
Planning Statement - Project Dragon - 16 Nov 2023Supporting DocumentNot publishedView
Project Dragon Application - RedactedForms and CertificatesNot publishedView

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Withdrawn
Decision Notice COMMITTEE REPORT Application Number P20230858 - Crown Wharf Port Talbot Docks
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.