Council planning record

Erect 48 wind turbines with blade tip height between 130 and 176 metres with installed capacity in excess of 50MW at

Clash Gour Wind Farm

UnknownReference: 18/01591/S36Moray

Application location

Clash Gour Wind Farm

This record has no verified map location.

View council map

Application summary

Status
Unknown
Application type
Dealt With By Scottish Executive
Received
17 Dec 2018
Validated
17 Dec 2018
Determination deadline
1 Jan 2019
Local authority
Moray

Application overview

Erect 48 wind turbines with blade tip height between 130 and 176 metres with installed capacity in excess of 50MW at

Proposal details

Reference
18/01591/S36
Ward
Speyside Glenlivet
Agent
SLP Consulting Limited

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 604 of 604

DocumentPublishedAction
23/01996/DISCON - DISCHARGE OF COND 27 - ACCEPTEDCorrespondence from Council · PDF18 Dec 2023View
DECISION LETTERDecision · PDF24 Oct 2022View
PI REPORTReport · PDF24 Oct 2022View
SITE LAYOUTDrawing · PDF24 Oct 2022View
DEVELOPMENT PLANSConsultation Response6 Dec 2019View
SI FIGURE 3.1 - PROPOSED LAYOUT PLANSupporting Document · PDF29 Oct 2019View
SI FIGURE 3.2A - PROPOSED SITE INFRASTRUCTURE SHEET 1Supporting Document · PDF29 Oct 2019View
SI FIGURE 3.2B - PROPOSED SITE INFRASTRUCTURE SHEET 2Supporting Document · PDF29 Oct 2019View
SI FIGURE 3.2C - PROPOSED SITE INFRASTRUCTURE SHEET 3Supporting Document · PDF29 Oct 2019View
SI FIGURE 3.2D - PROPOSED SITE INFRASTRUCTURE SHEET 4Supporting Document · PDF29 Oct 2019View
SI FIGURE 3.3 - TYPICAL TURBINE ELEVATIONSSupporting Document · PDF29 Oct 2019View
SI FIGURE 3.3C - TURBINE TYPE 3Supporting Document · PDF29 Oct 2019View
SI FIGURE 3.7C - TYPICAL DRAINAGE DETAILSSupporting Document · PDF29 Oct 2019View
SI FIGURE 3.23 - COMPARISON OF FLOATED TRACKSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.5 - DESIGNATIONS_45KMSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.5A - MORAY_DESIG_REVIEWSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.8A - BT_ZTV_A_A3Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.8C - BT_ZTV_A_A1Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.8E - BT_CZTV_A1Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.8F - BT_CZTV_EIAR_A1Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.15A - ZTV_A_20KM_A1Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.16A - CWF_20KMSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.16B - CZTV_BERRYBURNIISupporting Document · PDF29 Oct 2019View
SI FIGURE 7.16C - CZTV_ROTHESIIISupporting Document · PDF29 Oct 2019View
SI FIGURE 7.22C - SEQANALYSIS_A95Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.22D - SEQANALYSIS_CWF_A95Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.22I - SEQANALYSIS_DAVAWAYSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.22J - SEQANALYSIS_CWF_DAVAWAYSupporting Document · PDF29 Oct 2019View
SI FIGURE TA7-4-2 - RESI_ZTV_BT_ASupporting Document · PDF29 Oct 2019View
SI FIGURE 8.2A-K - NVC_HABITATSupporting Document · PDF29 Oct 2019View
SI FIGURE 8.2L-V - NVC_HABITATSupporting Document · PDF29 Oct 2019View
SI FIGURE 8.4A-J - GWDTE_HABITATSupporting Document · PDF29 Oct 2019View
SI FIGURE 8.4K-U - GWDTE_HABITATSupporting Document · PDF29 Oct 2019View
SI FIGURE 8.16 - OUTLINE HABITAT MANAGEMENT PLANSupporting Document · PDF29 Oct 2019View
SI FIGURE 9.20 - CUMULATIVE WIND FARMSSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.5_SITE_PEAT_OVERVIEWSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.5A_SITE_PEAT_SOUTHERNSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.5B_SITE_PEAT_NORTHERNSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.5C_SITE_PEAT_EASTERNSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.6D_GWDTE_OVERVIEWSupporting Document · PDF29 Oct 2019View
SI FIGURE - 10.6E_GWDTE_AREA1Supporting Document · PDF29 Oct 2019View
SI FIGURE - 10.6G_GWDTE_AREA3Supporting Document · PDF29 Oct 2019View
SI FIGURE - 10.6H_GWDTE_AREA4Supporting Document · PDF29 Oct 2019View
SI FIGURE - 10.6I_GWDTE_AREA8Supporting Document · PDF29 Oct 2019View
SI_FIGURE - 10.6F_GWDTE_AREA2Supporting Document · PDF29 Oct 2019View
SI FIGURE 11.1 - DALLASDHU_ZTVSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.3 - KNOCKANDO_ZTVSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.5 - LOCHINDORB_ZTVSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.6A - LOCHINDORB_CZTV_BERRYBURNSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.6B - LOCHINDORB_CZTV_TOMNANCLACHSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.6C - BERRYBURN2 & CG AT LOCHINDORB CSTLESupporting Document · PDF29 Oct 2019View
SI FIGURE 11.6D - CAIRNDUHIE & CG AT LOCHINDORB CSTLESupporting Document · PDF29 Oct 2019View
SI FIGURE 16.1 - SHADOW FLICKER ANALYSISSupporting Document · PDF29 Oct 2019View
CONTENTS PAGE FOR FIGURES VOL2Supporting Document · PDF29 Oct 2019View
CONTENTS PAGE FOR TAS VOL2Supporting Document · PDF29 Oct 2019View
SI TECHNCIAL APPENDIX 10.7 - SOIL AND PEAT MANAGEMENT PLANSupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 3.4 - LANDOWNER LETTERSSupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 8.6 - OUTLINE HABITAT MANAGEMENT PLANSupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 10.3 - GWDTESupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 10.8 - CARBON REPORTSupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 10.9 - BORROW PIT REPORTSupporting Document · PDF29 Oct 2019View
SI TECHNICAL APPENDIX 15.1 - RADAR ASSESSMENTSupporting Document · PDF29 Oct 2019View
TECHNICAL APPENDIX 9.1 ORNITHOLOGY SURVEY METHODS & RESULTS INC ANNEX E&FSupporting Document · PDF29 Oct 2019View
SI VOLUME 2 FRONT_COVERSupporting Document · PDF29 Oct 2019View
CONTENTS PAGE FOR VISUALS VOL3Supporting Document · PDF29 Oct 2019View
SI FIGURE 7.23 - 7.50 - VISUALISATIONSSupporting Document · PDF29 Oct 2019View
SI FIGURE 7.54A-L - CUMULATIVE WIRESSupporting Document · PDF29 Oct 2019View
SI FIGURE 11.2_11.4_11.7 - WIRESSupporting Document · PDF29 Oct 2019View
SI VOLUME 3 FRONT COVERSupporting Document · PDF29 Oct 2019View
DESIGN AND ACCESS STATEMENT - PART 1Supporting Document · PDF28 Oct 2019View
DESIGN AND ACCESS STATEMENT - PART 2Supporting Document · PDF28 Oct 2019View
DESIGN AND ACCESS STATEMENT - PART 3Supporting Document · PDF28 Oct 2019View
PRE APPLICATION CONSULTATION REPORT - PART 1Supporting Document · PDF28 Oct 2019View
PRE APPLICATION CONSULTATION REPORT - PART 2Supporting Document · PDF28 Oct 2019View
PLANNING STATEMENTSupporting Document · PDF28 Oct 2019View
NON-TECHNICAL SUMMARYSupporting Document · PDF28 Oct 2019View
EIA REPORT - CONTECTSSupporting Document · PDF28 Oct 2019View
EIA REPORT - FRONT COVERSupporting Document · PDF28 Oct 2019View
EIA REPORT - ACRONYMS AND ABBREVIATIONSSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 1 INTRODUCTIONSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 2 DESCRIPTION AND DESIGN EVOLUTIONSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 3 DESCRIPTION OF DEVELOPMENTSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 4 RENEWABLVE ENERGY AND PLANNING POLICYSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 5 ENVIRONMENTAL IMPACT ASSESSMENTSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 6 SCOPING AND CONSULTATIONSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 7 LVIASupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER9 ORNITHOLOGY REPORTSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 10 SOILS AND THE WATER ENVIRONMENTSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 11 CULTRUAL HERITAGE AND ARCHAEOLOGYSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 12 NOISE AND VIBRATIONSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 13 SITE ACCESS TRAFFIC AND TRANSPORTSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 14 SOCIO ECONOMICSSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 15 AVIATIONSupporting Document · PDF28 Oct 2019View
EIA REPORT -CHAPTER 16 OTHER ENVIRONMENTAL ISSUESSupporting Document · PDF28 Oct 2019View
EIA REPORT - CHAPTER 17 SCHEDULE OF MITIGATIONSupporting Document · PDF28 Oct 2019View
CHAPTERS 1- 6 FIGURES - FRONT PAGESupporting Document · PDF28 Oct 2019View
CHAPTERS 1- 6 - CONTENTSSupporting Document · PDF28 Oct 2019View
FIGURE 1.1 SITE CONTEXTSSupporting Document · PDF28 Oct 2019View
FIGURE 1.2 APPLICATION BOUNDARYSupporting Document · PDF28 Oct 2019View
FIGURE 1.3 AERIAL CONTEXTSupporting Document · PDF28 Oct 2019View
FIGURE 2.1 ENVIRONMENTAL DESIGNATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 2.2 DESIGN CONSTAINTSSupporting Document · PDF28 Oct 2019View
FIGURE 2.3 TRAFFIC LIGHT CONSTAINTSSupporting Document · PDF28 Oct 2019View
FIGURE 2.4A SITE LAYOUT EVOLUTIONSupporting Document · PDF28 Oct 2019View
FIGURE 2.4B SITE LAYOUT EVOLUTIONSupporting Document · PDF28 Oct 2019View
FIGURE 3.1 PROPOSED SITE LAYOUTSupporting Document · PDF28 Oct 2019View
FIGURE 3.2A PROPOSED SITE INFRASTRUCTURE SHEET 1Supporting Document · PDF28 Oct 2019View
FIGURE 3.2B PROPOSED SITE INFRASTRUCTURE SHEET 2Supporting Document · PDF28 Oct 2019View
FIGURE 3.2C PROPOSED SITE INFRASTRUCTURE SHEET 3Supporting Document · PDF28 Oct 2019View
FIGURE 3.2D PROPOSED SITE INFRASTRUCTURE SHEET 4Supporting Document · PDF28 Oct 2019View
FIGURE 3.2E PROPOSED SITE INFRASTRUCTURE SHEET 5Supporting Document · PDF28 Oct 2019View
FIGURE 3.2F PROPOSED SITE INFRASTRUCTURE SHEET 6Supporting Document · PDF28 Oct 2019View
FIGURE 3.3 TYPICAL TURBINE ELEVATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 3.3A TURBINE TYPE 1Supporting Document · PDF28 Oct 2019View
FIGURE 3.3B TURBINE TYPE 2Supporting Document · PDF28 Oct 2019View
FIGURE 3.3C TURBINE TYPE 3Supporting Document · PDF28 Oct 2019View
FIGURE 3.3D TURBINE TYPE 4Supporting Document · PDF28 Oct 2019View
FIGURE 3.3E TURBINE TYPE 5Supporting Document · PDF28 Oct 2019View
FIGURE 3.10 CRANE HARDSTANDING LAYOUTSSupporting Document · PDF28 Oct 2019View
FIGURE 3.11 CABLE TRENCH DETAILSSupporting Document · PDF28 Oct 2019View
FIGURE 3.12A BORROW PIT PLANS AND PROFILE BP01Supporting Document · PDF28 Oct 2019View
FIGURE 3.12B BORROW PIT PLANS AND PROFILE BP02Supporting Document · PDF28 Oct 2019View
FIGURE 3.12C BORROW PIT PLANS AND PROFILE BP03Supporting Document · PDF28 Oct 2019View
FIGURE 3.12D BORROW PIT PLANS AND PROFILE BP04Supporting Document · PDF28 Oct 2019View
FIGURE 3.12E BORROW PIT PLANS AND PROFILE BP05Supporting Document · PDF28 Oct 2019View
FIGURE 3.12F BORROW PIT PLANS AND PROFILE BP06Supporting Document · PDF28 Oct 2019View
FIGURE 3.12G BORROW PIT PLANS AND PROFILE BP07Supporting Document · PDF28 Oct 2019View
FIGURE 3.12H BORROW PIT PLANS AND PROFILE BP08Supporting Document · PDF28 Oct 2019View
FIGURE 3.12I BORROW PIT PLANS AND PROFILE BP09Supporting Document · PDF28 Oct 2019View
FIGURE 3.12J BORROW PIT PLANS AND PROFILE BP10Supporting Document · PDF28 Oct 2019View
FIGURE 3.12K BORROW PIT PLANS AND PROFILE BP11Supporting Document · PDF28 Oct 2019View
FIGURE 3.13 SITE ENTRANCE LAYOUTSupporting Document · PDF28 Oct 2019View
FIGURE 3.14 A TYPICAL SUBSTATION LAYOUT COMPOUND S1ASupporting Document · PDF28 Oct 2019View
FIGURE 3.14 B TYPICAL SUBSTATION LAYOUT COMPOUND S1BSupporting Document · PDF28 Oct 2019View
FIGURE 3.14 C TYPICAL SUBSTATION LAYOUT COMPOUND S2Supporting Document · PDF28 Oct 2019View
FIGURE 3.14 D TYPICAL SUBSTATION LAYOUT COMPOUND S3Supporting Document · PDF28 Oct 2019View
FIGURE 3.14 E TYPICAL BUILDING ELEVATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 3.15 TYPICAL CONSTRUCTION COMPOUND LAYOUTSupporting Document · PDF28 Oct 2019View
FIGURE 3.16 SITE ENTRANCE COMPOUNDSupporting Document · PDF28 Oct 2019View
FIGURE 3.17 INDICATIVE PERMANENT ANEMOMETER MASTSSupporting Document · PDF28 Oct 2019View
FIGURE 3.18A TEMPORARY POWER PERFORMANCE M,ASTS 93.5MSupporting Document · PDF28 Oct 2019View
FIGURE 3.18B TEMPORARY POWER PERFORMANCE M,ASTS 112.5MSupporting Document · PDF28 Oct 2019View
FIGURE 3.20 FELLING NECESSARY FOR CONSTRUCTION AND PHASE OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE 3.20A FELLING NECESSARY FOR CONSTRUCTION AND FELLING PHASESSupporting Document · PDF28 Oct 2019View
FIGURE 3.20B FELLING NECESSARY FOR CONSTRUCTION AND FELLING PHASESSupporting Document · PDF28 Oct 2019View
FIGURE 3.20C FELLING NECESSARY FOR CONSTRUCTION AND FELLING PHASESSupporting Document · PDF28 Oct 2019View
FIGURE 3.21 RESTOCKING PLAN OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE 3.21A RESTOCKING PLANSupporting Document · PDF28 Oct 2019View
FIGURE 3.21B RESTOCKING PLANSupporting Document · PDF28 Oct 2019View
FIGURE 3.21C RESTOCKING PLANSupporting Document · PDF28 Oct 2019View
FIGURE 3.22 COMPENSATORY PLANTING PLANSupporting Document · PDF28 Oct 2019View
VISUALISATIONS - FRONT COVERSupporting Document · PDF28 Oct 2019View
VISUALISATIONS CONTENTSSupporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP1-2Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP3Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP4Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP5-6Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP7-8Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP9-10Supporting Document · PDF28 Oct 2019View
VISUALISATIONS FRONT COVERSupporting Document · PDF28 Oct 2019View
VISUALISATIONS CONTENTSSupporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP11-12Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP13-14Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP15-16Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP17-18Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP19-20Supporting Document · PDF28 Oct 2019View
VISUALISATIONS FRONT COVERSupporting Document · PDF28 Oct 2019View
VISUALISATIONS CONTENTSSupporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP21-22Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP23-24Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP25-26Supporting Document · PDF28 Oct 2019View
VISUALISATIONS PROPOSED DEVELOPMENT VP27-28Supporting Document · PDF28 Oct 2019View
VISUALISATIONS FRONT COVERSupporting Document · PDF28 Oct 2019View
VISUALISATIONS CONTENTSSupporting Document · PDF28 Oct 2019View
VISUALISATIONS 3F WIRELINE VIEWS ADDITIONAL VP A HSupporting Document · PDF28 Oct 2019View
VISUALISATIONS 3G LIGHTING PART 1Supporting Document · PDF28 Oct 2019View
VISUALISATIONS 3G LIGHTING PART 2Supporting Document · PDF28 Oct 2019View
VISUALISATIONS 3H AND I FRONT COVERSupporting Document · PDF28 Oct 2019View
VISUALISATIONS 3H AND I CONTENTSSupporting Document · PDF28 Oct 2019View
VISUALISATIONS 3H WIREVIEWS COMPARATIVE VP 1-28Supporting Document · PDF28 Oct 2019View
VISUALISATIONS 3I SCERAIO B PHOTOMONTAGES PART 1Supporting Document · PDF28 Oct 2019View
VISUALISATIONS 3I SCERAIO B PHOTOMONTAGES PART 2Supporting Document · PDF28 Oct 2019View
FIGURES CH 8-17 FRONT COPVERSupporting Document · PDF28 Oct 2019View
FIGURES CH 8-17 CONTENTSSupporting Document · PDF28 Oct 2019View
FIGURES 8.1 ECOLOGICAL DESIGNATED SITES WITHIN 5K OF SITESupporting Document · PDF28 Oct 2019View
FIGURES 8.2A-K KNVC STUDY AREA REDUCEDSupporting Document · PDF28 Oct 2019View
FIGURE 8.2 L-V NVC STUDY AREA REDUCEDSupporting Document · PDF28 Oct 2019View
FIGURE 8.5 CARBON AND PEATLAND 2016Supporting Document · PDF28 Oct 2019View
FIGURE 8.14A-C FISH SURVEY STAUDY AREA REDUCEDSupporting Document · PDF28 Oct 2019View
FIGURE 8.15A-C FISH SURVEY RESULTS REDUCEDSupporting Document · PDF28 Oct 2019View
FIGURE 8.16 OHMP MANAGEMENT AREASSupporting Document · PDF28 Oct 2019View
FIGURE 9.1 ORNITHOLOGICAL DESIGNATED SITES WITHIN 20K OF SITESupporting Document · PDF28 Oct 2019View
FIGURE 9.2 SITE BOUNDARY AND STUDY AREASupporting Document · PDF28 Oct 2019View
FIGURE 9.3 FLIGHT ACTIVITY SURVEY VANTAGE POINTS AND VIEWSHEDSSupporting Document · PDF28 Oct 2019View
FIGURE 10.1 SITE ELEVATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 10.2 SITE BEDROCK GEOLOGYSupporting Document · PDF28 Oct 2019View
FIGURE 10.3 SITE SUPERFICIAL GEOLOGYSupporting Document · PDF28 Oct 2019View
FIGURE 10.4 SITE SOILSSupporting Document · PDF28 Oct 2019View
FIGURE 10.5 SITE PEAT OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE 10.5A SITE PEAT DEPTH (SOUTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.5B SITE PEAT DEPTH (NORTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.5C SITE PEAT DEPTH (EASTERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.6 SITE GWDTE OVERVOEWSupporting Document · PDF28 Oct 2019View
FIGURE 10.6A SITE GWDTE (SOUTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.6B SITE GWTE (NORTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.6C SITE GWDTE (EASTERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.7 SITE HYDROLOGY OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE 10.7A SITE DETAILED HYDROLOGY (SOUTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.7B SITE DETAILED HYDROLOGY (NORTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.7C SITE DETAILED HYDROLOGY (EASTERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.8 SITE PRIVATE WATER SUPPLIES OVERVIEW REDUCEDSupporting Document · PDF28 Oct 2019View
FIGURE 10.8A SITE PRIVATE WATER SUPPLIES (SOUTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.8B SITE PRIVATE WATER SUPPIES (NORTHERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.8C SITE PRIVATE WATER SUPPLIES (EASTERN)Supporting Document · PDF28 Oct 2019View
FIGURE 10.8D SITE PRIVATE WATR SUPPLY HALF DAVOCH ROADSupporting Document · PDF28 Oct 2019View
FIGURE 10.8E SITE PRIVATE WATER SUPPLIES HALF DAVOCH ROADSupporting Document · PDF28 Oct 2019View
FIGURE 11.1A HERITAGE ASSETS WITHIN THE INNER STUDY AREASupporting Document · PDF28 Oct 2019View
FIGURE 11.1B HERITAGE ASSETS WITHIN INNES STUDY AREAREASupporting Document · PDF28 Oct 2019View
FIGURE 11.1C HERITAGE ASSETS WITHIN INNER STUDY AREASupporting Document · PDF28 Oct 2019View
FIGURE 12.1 NOISE MONITORING AND ASSESSMENT LOCATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 12.2 RESIDENTIAL PROPERTIES NEAR HALF DAVOCH ROADSupporting Document · PDF28 Oct 2019View
FIGURE 12.3 PREDICTED NOISE LEVELS PROPOSED DEVELOPMENT ALONESupporting Document · PDF28 Oct 2019View
FIGURE 12.4 PREDICTED CUMULATIVE NOISE LEVLESSupporting Document · PDF28 Oct 2019View
FIGURE 13.1 TRAFFIC COUNT AND SPEED SURVEY LOCATIONSSupporting Document · PDF28 Oct 2019View
FIGURE 13.2 PROPOSED TURBINE DELIVERY ROUTESupporting Document · PDF28 Oct 2019View
FIGURE 14.1 SOCIO ECONOMIC RECEPTORS IN THE LOCAL AREA OF INFLUENCESupporting Document · PDF28 Oct 2019View
FIGURE 14.2 PROPOSED PATH NETWORKSupporting Document · PDF28 Oct 2019View
FIGURE 15.1 LOSSIMOUTH PAR VISIBILITYSupporting Document · PDF28 Oct 2019View
FIGURE 16.1 SHADOW FLICKER ANALYSIS FOR 10 TIMES ROTOR DIAMETERSupporting Document · PDF28 Oct 2019View
TAS CONTENTSSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING A REPORTSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING B FIGS 3.19 TO 3.20Supporting Document · PDF28 Oct 2019View
TAS APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING B FIGS 3.21 TO 3.22Supporting Document · PDF28 Oct 2019View
TAS APPENDIX 3.2 OUTLINE CONSTRUCTION ENVIRONMENTAL PLANSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 3.3 OUTLINE DECOMMISSIONING AND RESTRORATION PLANSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 4.1 LEGISLATION POLICY GUIDANCESupporting Document · PDF28 Oct 2019View
TAS APPENDIX 6.1 CONSULTEE KEY ISSUES AND CONSULTATION COMMENTSSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 6.2 CONSULTEE MEETINGS KEY ISSUESSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.1 LVIA METHODOLOGYSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.2 DETAILED ASSESSMENT OF VIEWPOINTSSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.3 CNP SPECIAL QUALITIESSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.4 RESIDENTIAL VISUAL AMENITY SURVEY PART 1Supporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.4 RESIDENTIAL VISUAL AMENITY SURVEY PART 2Supporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.4 RESIDENTIAL VISUAL AMENITY SURVEY PART 3Supporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.5 LVIA FUTURE BASELINE ASSESSMENTSupporting Document · PDF28 Oct 2019View
TAS APPENDIX 7.6 NIGHT TIME ASSESSMENTSupporting Document · PDF28 Oct 2019View
FIGURE10.2.1 BEDROCK GEOLOGYSupporting Document · PDF28 Oct 2019View
FIGURE10.2.2 SUPERFICALIAL GEOLOGYSupporting Document · PDF28 Oct 2019View
FIGURE10.2.3 HYDROLOGYSupporting Document · PDF28 Oct 2019View
FIGURE10.2.4 AERIALSupporting Document · PDF28 Oct 2019View
FIGURE10.2.5 PEAT OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.5A PEAT SOUTHERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.5B PEAT NORTHERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.5C PEAT EASTERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.6 PEAT CORE LOCATIONSSupporting Document · PDF28 Oct 2019View
FIGURE10.2.7 FACTOR OF SAFETYSupporting Document · PDF28 Oct 2019View
FIGURE10.2.7A FACTOR OF SAFETY SOUTHERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.7B FACTOR OF SAFETY NORTHERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.7C FACTOR OF SAFETY EASTERNSupporting Document · PDF28 Oct 2019View
FIGURE10.2.8 INITIAL LIKELYHOOD OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.9 COSEQUENCE OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.10 INITIAL RISK OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.11 DETAILED ASSESSMENT AREAS OVRVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.12 GEOMORPHOLOGY OVERVIEWSupporting Document · PDF28 Oct 2019View
FIGURE10.2.13 REVISED RISK OVERVIEWSupporting Document · PDF28 Oct 2019View
PLANNING STATEMENT ADDENDUM - FINAL - PART 1Supporting Document · PDF28 Oct 2019View
PLANNING STATEMENT ADDENDUM - FINAL - PART 2Supporting Document · PDF28 Oct 2019View
STAND ALONE NON TECHNICAL SUMMARY - NTS SI FRONT COVERSupporting Document · PDF28 Oct 2019View
STAND ALONE NON TECHNICAL SUMMARY - SI NTS STAND ALONESupporting Document · PDF28 Oct 2019View
CHAPTER 1 - SI FRONT COVER PREFACE CONTENTS NTS AND CHAPTER 1Supporting Document · PDF28 Oct 2019View
SI CHAPTER 2 - SITE DESCRIPTION AND DESIGN EVOLUTIONSupporting Document · PDF28 Oct 2019View
SI CHAPTER 3 - DESCRIPTION OF THE DEVELOPMENTSupporting Document · PDF28 Oct 2019View
SI CHAPTER 4 - RENEWABLE ENERGY AND PLANNING POLICYSupporting Document · PDF28 Oct 2019View
SI CHAPTER 5 - ENVIRONMENTAL IMPACT ASSESSMENTSupporting Document · PDF28 Oct 2019View
SI CHAPTER 6 - SCOPING AND CONSULTATIONSupporting Document · PDF28 Oct 2019View
SI CHAPTER 7 - LANDSCAPE AND VISUALSupporting Document · PDF28 Oct 2019View
SI CHAPTER 8 - ECOLOGYSupporting Document · PDF28 Oct 2019View
SI CHAPTER 9 - ORNITHOLOGYSupporting Document · PDF28 Oct 2019View
SI CHAPTER 10 - SOILS GEOLOGY AND WATER ENVIRONMENTSupporting Document · PDF28 Oct 2019View
SI CHAPTER 11 - CULTURAL HERITAGE AND ARCHAEOLOGYSupporting Document · PDF28 Oct 2019View
SI CHAPTER 12 - NOISE AND VIBRATIONSupporting Document · PDF28 Oct 2019View
SI CHAPTER 13 - SITE ACCESS TRAFFIC AND TRANSPORTSupporting Document · PDF28 Oct 2019View
SI CHAPTER 14 - SOCIO ECONOMICSSupporting Document · PDF28 Oct 2019View
SI CHAPTER 15 - AVIATIONSupporting Document · PDF28 Oct 2019View
SI CHAPTER 16 - OTHER ENVIRONMENTAL ISSUESSupporting Document · PDF28 Oct 2019View
SI CHAPTER 17 - SCHEDULE OF MITIGATIONSupporting Document · PDF28 Oct 2019View
ENVIRONMENTAL HEALTHConsultation Response · PDF21 May 2019View
TRANSPORTATION MANAGER - UPDATEDConsultation Response · PDF18 Mar 2019View
TRANSPORTATION MANAGERConsultation Response · PDF14 Mar 2019View
TECNHICAL APPENDIX 9.1 ANNEX ESupporting Document · PDF28 Feb 2019View
TECHNICAL APPENDIX 9.1 ANNEX FSupporting Document · PDF28 Feb 2019View
MORAY FLOOD RISK MANAGEMENTConsultation Response · PDF30 Jan 2019View
PRIVATE WATER SUPPLIESConsultation Response · PDF24 Jan 2019View
ABERDEENSHIRE ARCHAEOLOGY SERVICEConsultation Response · PDF24 Jan 2019View
BUILDING STANDARDSConsultation Response · PDF18 Jan 2019View
CONTAMINATED LANDConsultation Response · PDF14 Jan 2019View
FIGURE 10.2.1 - BEDROCK GEOLOGYSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.2 SUPERFICIAL GEOLOGYSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.3 HYDROLOGYSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.4 AERIALSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.5 PEAT OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.5A PEAT SOUTHERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.5B PEAT NORTHERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.5C PEAT EASTERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.6 PEAT CORE LOCATIONSSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.7 FACTOR AND SAFETYSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.7A FACTOR AND SAFETY SOUTHERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.7B FACTOR AND SAFETY NORTHERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.7C FACTOR AND SAFETY EASTERNSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.8 INITIAL LIKELIHOOD OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.9 CONSEQUENCE OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.10 INITIAL RISK OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.11 DETAILED ASSESSMENT AREA OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.12 GEOMORPHOLOGY OVERVIEWSupporting Document · PDF24 Dec 2018View
FIGURE 10.2.13 REVISED RISK OVERVIEWSupporting Document · PDF24 Dec 2018View
CONTENTS TECHNICAL APPENDICIESSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.1 PHOTOGRAPHS AND DIAGRAMSSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.2 PEAT STABILITY ASSESSMENT REPORTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.2 PEAT STABILITY ASSESSMENT ANNEX BSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.3 GWDTESupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.4 HYDROCHEMISTRY REPORTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.5 PRIVATE WATER SUPPLIESSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.6 WATERCOURSE CROSSING REPORTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.7 SOIL AND PEAT MANAGEMENT PLANSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.8 CARBON BALANCE REPORTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 10.9 BORROW PIT AREA ASSESSMENTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 11.1 GAZETTEER OF HERITIAGE ASSETSSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 12.1 NOISE & VIBRATION ASSESSMENTSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 13.1 CONSTRUCTION VEHICLE CALCULATIONSSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 13.2 BLADE NEHICLE CONFIGURATIONSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 13.3 BLADE TRANSPORT VEHICLE SWEPT PATH ANALYSIS - MAJOR ROASupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 13.4 BLADE TRANSPORT VEHICLE SWEPT PATH - HALF DAVOCH ROAD ASupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 13.4 BLADE TRANSPORT VEHICLE SWEPT PATH - HALF DAVOCH ROAD BSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 14.1 SOCIO-ECONOMIC DATA SOURCESSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 14.2 ACCOMMODATION BUSINESSESSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 14.3 DRAFT PAMPSupporting Document · PDF24 Dec 2018View
TECHNICAL APPENDIX 15.1 AVIATION ASSESSMENTSupporting Document · PDF24 Dec 2018View
ELECTRICITY (APPLICATION FOR CONSENT) REGS 1990Correspondence to Council · PDF24 Dec 2018View
DESIGN AND ACCESS STATEMENT - PART 1Supporting Document · PDF17 Dec 2018View
DESIGN AND ACCESS STATEMENT - PART 2Supporting Document · PDF17 Dec 2018View
DESIGN AND ACCESS STATEMENT - PART 3Supporting Document · PDF17 Dec 2018View
PRE APPLICATION CONSULTATION REPORT - PART 1Supporting Document · PDF17 Dec 2018View
PRE APPLICATION CONSULTATION REPORT - PART 2Supporting Document · PDF17 Dec 2018View
PLANNING STATEMENTSupporting Document · PDF17 Dec 2018View
NON TECHNICAL SUMMARYSupporting Document · PDF17 Dec 2018View
EIA REPORT - CONTENTSSupporting Document · PDF17 Dec 2018View
EIA REPORT - FRONT COVERSupporting Document · PDF17 Dec 2018View
EIA REPORT - ACRONMYMS AND ABBREVIATIONSSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 1 INTRODUCTIONSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 2 SITE DESCRIPTION & DESIGN EVOLUTIONSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 3 DESCRIPTION OF DEVELOPMENTSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 4 RENEWABLE ENERGY & PLANNING POLICYSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 5 ENVIRONMENTAL IMPACT ASSESSMENTSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 6 SCOPING & CONSULTATIONSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 7 LVIASupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 8 ECOLOGYSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 9 ORNITHOLOGYSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 10 SOILS & THE WATER ENVIRONMENTSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 11 CULTURAL HERTIGATE & ARCHAEOLOGYSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 12 NOISE AND VIBRATIONSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 13 SITE ACCESS TRAFFIC & TRANSPORTSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 14 SOCIO ECONOMICSSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 15 AVIATIONSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 16 OTHER ENVIRONMENTAL ISSUESSupporting Document · PDF17 Dec 2018View
EIA REPORT - CHAPTER 17 SCHEDULE OF MITIGATIONSupporting Document · PDF17 Dec 2018View
VOL 3A FRONT COVERSupporting Document · PDF17 Dec 2018View
CONTENTS VOL 3A CHAPTER 1-6Supporting Document · PDF17 Dec 2018View
FIGURE 1.1 CONTEXTSupporting Document · PDF17 Dec 2018View
FIGURE 1.2 APPLICATION BAOUNDARYSupporting Document · PDF17 Dec 2018View
FIGURE 1.3 AERIAL CONTEXTSupporting Document · PDF17 Dec 2018View
FIGURE 2.1 ENVIRONMENTAL DESIGNATIONSSupporting Document · PDF17 Dec 2018View
FIGURE 2.2 DESIGN CONSTRIANTSSupporting Document · PDF17 Dec 2018View
FIGURE 2.3 TRAFFIC LIGHT CONSTRAINTSSupporting Document · PDF17 Dec 2018View
FIGURE 2.4A SITE LAYOUT EVOLUTIONSupporting Document · PDF17 Dec 2018View
FIGURE 2.4B SITE LAYOUT EVOLUTIONSupporting Document · PDF17 Dec 2018View
FIGURE 3.1 PROPOSED SITE LAYOUTSupporting Document · PDF17 Dec 2018View
FIGURE 3.2A PROPOSED SITE INFRASTRUCTURE SHEET 1Supporting Document · PDF17 Dec 2018View
FIGURE 3.2B PROPOSED SITE INFRASTRUCTURE SHEET 2Supporting Document · PDF17 Dec 2018View
FIGURE 3.2C PROPOSED SITE INFRASTRUCTURE SHEET 3Supporting Document · PDF17 Dec 2018View
FIGURE 3.2D PROPOSED SITE INFRASTRUCTURE SHEET 4Supporting Document · PDF17 Dec 2018View
FIGURE 3.2E PROPOSED SITE INFRASTRUCTURE SHEET 5Supporting Document · PDF17 Dec 2018View
FIGURE 3.2F PROPOSED SITE INFRASTRUCTURE SHEET 6Supporting Document · PDF17 Dec 2018View
FIGURE 3.3 TYPICAL TURBINE ELEVATIONSSupporting Document · PDF17 Dec 2018View
FIGURE 3.3A TURBINE TYPE 1Supporting Document · PDF17 Dec 2018View
FIGURE 3.3B TURBINE TYPE 2Supporting Document · PDF17 Dec 2018View
FIGURE 3.3C TURBINE TYPE 3Supporting Document · PDF17 Dec 2018View
FIGURE 3.3D TURBINE TYPE 4Supporting Document · PDF17 Dec 2018View
FIGURE 3.3E TURBINE TYPE 5Supporting Document · PDF17 Dec 2018View
FIGURE 3.4 INDICATIVE EXTERNAL TRANSFORMERSupporting Document · PDF17 Dec 2018View
FIGURE 3.5 TYPICAL TURBINE FOUNDATIONSupporting Document · PDF17 Dec 2018View
FIGURE 3.6A TYPICAL TRACK DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.6B TYPICAL TRACK DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.7A TYPICAL DRAINAGE DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.7B TYPICAL DRAINAGE DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.8A TYPICAL CULVERT CONSTRUCTION DETAILS SHEET 1Supporting Document · PDF17 Dec 2018View
FIGURE 3.8B TYPICAL CULVERT CONSTRUCTION DETAILS SHEET 2Supporting Document · PDF17 Dec 2018View
FIGURE 3.9 TYPICAL BRIDGE CONSTRUCTION DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.10 CRANE HARDSTANDING LAYOUTSupporting Document · PDF17 Dec 2018View
FIGURE 3.11 CABLE TRENCH DETAILSSupporting Document · PDF17 Dec 2018View
FIGURE 3.12A BORROW PIT PLANS & PROFILES BP01Supporting Document · PDF17 Dec 2018View
FIGURE 3.12B BORROW PIT PLANS & PROFILES BP02Supporting Document · PDF17 Dec 2018View
FIGURE 3.12C BORROW PIT PLANS & PROFILES BP03Supporting Document · PDF17 Dec 2018View
FIGURE 3.12D BORROW PIT PLANS & PROFILES BP04Supporting Document · PDF17 Dec 2018View
FIGURE 3.12E BORROW PIT PLANS & PROFILES BP05Supporting Document · PDF17 Dec 2018View
FIGURE 3.12F BORROW PIT PLANS & PROFILES BP06Supporting Document · PDF17 Dec 2018View
FIGURE 3.12G BORROW PIT PLANS & PROFILES BP07Supporting Document · PDF17 Dec 2018View
FIGURE 3.12H BORROW PIT PLANS & PROFILES BP08Supporting Document · PDF17 Dec 2018View
FIGURE 3.12I BORROW PIT PLANS & PROFILES BP09Supporting Document · PDF17 Dec 2018View
FIGURE 3.12J BORROW PIT PLANS & PROFILES BP10Supporting Document · PDF17 Dec 2018View
FIGURE 3.12K BORROW PIT PLANS & PROFILES BP11Supporting Document · PDF17 Dec 2018View
FIGURE 3.13 SITE ENTRANCE LAYOUTSupporting Document · PDF17 Dec 2018View
FIGURE 3.14A TYPICAL SUBSTATION LAYOUT COMPOUND S1ASupporting Document · PDF17 Dec 2018View
FIGURE 3.14B TYPICAL SUBSTATION LAYOUT COMPOUND S2Supporting Document · PDF17 Dec 2018View
FIGURE 3.14D TYPICAL SUBSTATION LAYOUT COMPOUND S3Supporting Document · PDF17 Dec 2018View
FIGURE 3.14E SITE ENTRANCE LAYOUTSupporting Document · PDF17 Dec 2018View
FIGURE 3.15 TYPICAL CONSTRUCTION COMPOUND LAYOUTSupporting Document · PDF17 Dec 2018View
FIGURE 3.16 SITE ENTRANCE COMPOUNDSupporting Document · PDF17 Dec 2018View
FIGURE 3.17 INDICATIVE PERMANENT ANEMOMETER MASTSupporting Document · PDF17 Dec 2018View
FIGURE 3.18A TEMPORARY POWER PERFORMANCE MAST 93.5MSupporting Document · PDF17 Dec 2018View
FIGURE 3.18B TEMPORARY POWER PERFORMANCE MAST 112.5MSupporting Document · PDF17 Dec 2018View
FIGURE 3.20 FELLING NECESSARY FOR CONSTRUCTION & PHASES OVERVIEWSupporting Document · PDF17 Dec 2018View
FIGURE 3.20A FELLING NECESSARY FOR CONSTRUCTION & PHASESSupporting Document · PDF17 Dec 2018View
FIGURE 3.20B FELLING NECESSARY FOR CONSTRUCTION & PHASESSupporting Document · PDF17 Dec 2018View
FIGURE 3.20C FELLING NECESSARY FOR CONSTRUCTION & PHASESSupporting Document · PDF17 Dec 2018View
FIGURE 3.21 RESTOCKING PLAN OVERVIEWSupporting Document · PDF17 Dec 2018View
FIGURE 3.21A RESTOCKING PLANSupporting Document · PDF17 Dec 2018View
FIGURE 3.21B RESTOCKING PLANSupporting Document · PDF17 Dec 2018View
FIGURE 3.21C RESTOCKING PLANSupporting Document · PDF17 Dec 2018View
FIGURE 3.22 COMPENSATORY PLANTING PLANSupporting Document · PDF17 Dec 2018View
FIGURE 4.1 WIND FARM SPACIAL FRAMEWORK EXTRACT MORAY ONSHORE WIND ENERGYSupporting Document · PDF17 Dec 2018View
FIGURE 4.2 EXTRACT MAP 1 POLICY GUIDANCE MAP FOR LARGE TYPOLOGIESSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - FRONT COVERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - CONTENTSSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.1 SITE LOCATIONSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.2 LANDFORMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.3 SITE LAYOUTSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.4A LCA 45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.4B LCA 20KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.4C LCA LEGENDSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.5 DESIGNATIONS 45MSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.6 WILDERNESSSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.7A VISRECEPTORS 45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.7B VR LOCAL 5KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.7C LOCAL FORESTRYSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.8A BT_ZVT_ASupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.8B BT_ZVT_BSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.8C BT_ZTV_ASupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.8D BT_ZTV_BSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.8E BT_CVZTVSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.9A HH_ZTV_ASupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.9B HH_ZTV_BSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.9C HH_ZTV_ASupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.9D HH_ZTV_BSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.9E HH_ZTV_A1Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.10A HORI ZTV ASupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.10B HORI ZTV BSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.11 HRI CZTVSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.12 ZTV LCA 45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.13 ZTV DESIGNATIONS 45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.14 ZTV VISRECEPTORS 45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.15A ZTV _A_20KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.15B ZTV _B_20KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.16_CWF_45KMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.17_CZTV_OP_UCSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18A_CZTV_BERRYBURNSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18B_HILLOF GLASCHYLESupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18C_CZTV_PAULSHILLSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18D_CZTV_ROTHESI&IISupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18E_CZTV_BOGNIEFARMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18F_CZTV_CLUNYFARMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18G_CZTV_FINDHORNSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18H_CZTV_HUNTHILLSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18I_CZTV_CULISSESupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18J_CZTV_NE CLUSTERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18K_CZTV_E CLUSTERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18L_CZTV_SE CLUSTERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18M_CZTV_SW CLUSTERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18N_CZTV_DORENELLSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18O_CZTV_GLENKYLLACHSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.18P_CZTV_TOMNACLACHSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19A_CZTV_ABERDERSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19B_CZTV_AULTMORESupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19C_CZTV_CAIRNDUHIESupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19D_CZTV_DRODLANDSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19E_CZTV_GREENMYRESFARMSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19F_CZTV_HILLOFTOWIEIISupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19G_CZTV_KELLASSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.19H_CZTV_MEIKLEHILLSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.20_CZTV_PAULSHILLIISupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.21_SEQROUTES-OVERVIEWSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22A_SEQANALYSIS_A940Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22B_SEQANALYSIS_CWF_A940Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22C_SEQANALYSIS_CWF_A95Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22D_SEQANALYSIS_CWF_A95Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22E_SEQANALYSIS_A96Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22F_SEQANALYSIS_CWF_A96Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22G_SEQANALYSIS_B9007Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22H_SEQANALYSIS_CWF_B9007Supporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22I_SEQANALYSIS_DAVAWATSupporting Document · PDF17 Dec 2018View
CHAPTER 7 - LVIA FIGURE 7.22J_SEQANALYSIS_CWF_DAVAWAYSupporting Document · PDF17 Dec 2018View
FRONT COVERSupporting Document · PDF17 Dec 2018View
CONTENTSSupporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP1-2Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP3Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP4Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP5-6Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP7-8Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP9-10Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - FRONT COVERSupporting Document · PDF17 Dec 2018View
VISUALISATIONS - CONTENTSSupporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP11-12Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP13-14Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP15-16Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP17-18Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP19-20Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - FRONT COVERSupporting Document · PDF17 Dec 2018View
VISUALISATIONS - CONTENTSSupporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP21-22Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP23-24Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP25-26Supporting Document · PDF17 Dec 2018View
VISUALISATIONS - PROPOSED DEVELOPMENT VP27-28Supporting Document · PDF17 Dec 2018View
FRONT COVERSupporting Document · PDF17 Dec 2018View
CONTENTSSupporting Document · PDF17 Dec 2018View
3F WIRELINE VIEWS_ ADDITIONAL_VP_A_HSupporting Document · PDF17 Dec 2018View
3G TA7.6_VISUALISATION_LIGHTING_PART 1Supporting Document · PDF17 Dec 2018View
3G TA7.6_VISUALISATION_LIGHTING_PART 2Supporting Document · PDF17 Dec 2018View
FRONT COVERSupporting Document · PDF17 Dec 2018View
CONTENTSSupporting Document · PDF17 Dec 2018View
3H_WIRELINES VIEWS_COMPARATIVE_VP_1-28Supporting Document · PDF17 Dec 2018View
3I_VISUALISATIONS_SCENARIOB_PHOTOMONTAGE_PART 1Supporting Document · PDF17 Dec 2018View
3I_VISUALISATIONS_SCENARIOB_PHOTOMONTAGE_PART 2Supporting Document · PDF17 Dec 2018View
COVERSupporting Document · PDF17 Dec 2018View
CONTENTS CHAPETER 8-16Supporting Document · PDF17 Dec 2018View
FIGURE 8.1 ECOLOGICAL DESIGNATED SITES WITHIN 5K OF SITESupporting Document · PDF17 Dec 2018View
FIGURE 8.2A - K NVC STUDY AREA REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.2I - V NVC STUDY AREA REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.4A-N POTENTIAL GWDTE STUDY AREA AND RESULTS REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.4O-U POTENTIAL GWDTE STUDY AREA AND RESULTS REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.5 CARBON AND PEATLANDSupporting Document · PDF17 Dec 2018View
FIGURE 8.14A-C FISH SURVEY STUDY AREA REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.15A-C FISH SURVEY STUDY REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 8.16 OHMP MANAGEMENT AREASSupporting Document · PDF17 Dec 2018View
FIGURE 9.1 ORNITHOLOGICAL DESIGNATED SITES WITHIN 20K OF SITESupporting Document · PDF17 Dec 2018View
FIGURE 9.2 SITE BOUNDARY AND STUDY AREASSupporting Document · PDF17 Dec 2018View
FIGURE 9.3 FLIGHT ACTIVITY SURVEY VANTAGE POINTS AND VIEWSHEDSupporting Document · PDF17 Dec 2018View
FIGURE 9.20 CUMULATIVE WIND FARMS WITHIN NATURAUL HERITAGE ZONE 10Supporting Document · PDF17 Dec 2018View
FIGURE 10.1 SITE ELEVATIONWITHIN NATURAUL HERITAGE ZONE 10Supporting Document · PDF17 Dec 2018View
FIGURE 10.2 SITE BEDROCK GEOLOGYSupporting Document · PDF17 Dec 2018View
FIGURE 10.3 SITE SUPERFICIAL GEOLOGYSupporting Document · PDF17 Dec 2018View
FIGURE 10.4 SITE SOILSSupporting Document · PDF17 Dec 2018View
FIGURE 10.5 SITE PEAT OVERVIEWSupporting Document · PDF17 Dec 2018View
FIGURE 10.5A SITE PEAT DEPTH (SOUTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.5B SITE PEAT DEPTH (NORTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.5C SITE PEAT DEPTH (EASTERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.6 SITE GWDTE OVERVIEWSupporting Document · PDF17 Dec 2018View
FIGURE 10.6A SITE GWDTE (SOUTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.6B SITE GWDTE (NORTHERNSupporting Document · PDF17 Dec 2018View
FIGURE 10.6C SITE GWDTE (EASTERNSupporting Document · PDF17 Dec 2018View
FIGURE 10.7 SITE HYSROLOGY OVERVIEWSupporting Document · PDF17 Dec 2018View
FIGURE 10.7A SITE DETAILED HYDROLOGY (SOUTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.7B SITE DETAILED HYDROLOGY (NORTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.7C SITE DETAILED HYDROLOGY (EASTERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.7B SITE DETAILED HYDROLOGY (NORTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.7C SITE DETAILED HYDROLOGY (EASTERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.8 SITE PRIVATE WATER SUPPLY OVERVIEW REDUCEDSupporting Document · PDF17 Dec 2018View
FIGURE 10.8A SITE PRIVATE WATER SUPPLIES (SOUTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.8B SITE PRIVATE WATER SUPPLIES (NORTHERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.8C SITE PRIVATE WATER SUPPLIES (EASTERN)Supporting Document · PDF17 Dec 2018View
FIGURE 10.8D SITE PRIVATE WATER SUPPLIES HALF DAVOCH ROADSupporting Document · PDF17 Dec 2018View
FIGURE 10.8E SITE PRIVATE WATER SUPPLIES HALF DAVOCHSupporting Document · PDF17 Dec 2018View
FIGURE 11.1A HERTIAGE ASSETS WITHINTHE INNES STUDY AREASupporting Document · PDF17 Dec 2018View
FIGURE 11.1B HERTIAGE ASSETS WITHINTHE INNES STUDY AREASupporting Document · PDF17 Dec 2018View
FIGURE 11.1C HERTIAGE ASSETS WITHINTHE INNES STUDY AREASupporting Document · PDF17 Dec 2018View
FIGURE 11.2A DESIGNATED HERITAGE ASSESTS WITHIN STUDY AREA AND ZTVSupporting Document · PDF17 Dec 2018View
FIGURE 11.2B DESIGNATED HERITAGE ASSESTS WITHIN STUDY AREA AND ZTVSupporting Document · PDF17 Dec 2018View
FIGURE 11.3 DESIGNATED HERITAGE ASSETS WITHIN STUDY AREA AND ZTVSupporting Document · PDF17 Dec 2018View
FIGURE 11.4 -11.5B VIEWPOINTS 1 AND 2Supporting Document · PDF17 Dec 2018View
FIGURE 12.1 NOISE MONITORING AND ASSESSMENT LOCATIONSSupporting Document · PDF17 Dec 2018View
FIGURE 12.2 RESIDENTAIL PROPERTIES NEAR HALF DAVOCH ROADSupporting Document · PDF17 Dec 2018View
FIGURE 12.3 PREDICTED NOISE LEVELS PROPOSED DEVELOPMENT ALONGSupporting Document · PDF17 Dec 2018View
FIGURE 12.4 PREDICTED CUMULATIVE NOISE LEVELSSupporting Document · PDF17 Dec 2018View
FIGURE 13.1 TRAFFIC COUNT AND SPEED SURVEY LOCATIONSSupporting Document · PDF17 Dec 2018View
FIGURE 13.2 PROPOSED TURBINE DELIVERY ROUTESupporting Document · PDF17 Dec 2018View
FIGURE 14.1 SOCIO ECONOMIC RECEPTORS IN LOCAL AREA OF INFLUENCESupporting Document · PDF17 Dec 2018View
FIGURE 14.2 PROPOSED PATH NETWORKSupporting Document · PDF17 Dec 2018View
FIGURE 15.1 LOSSIEMOUTH PAR VISIBILITYSupporting Document · PDF17 Dec 2018View
FIGURE 16.1 SHADOW FLICKER ANALYSIS FOR 10 TIMES ROTOR DIAMETERSupporting Document · PDF17 Dec 2018View
CONTENTSSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING - A REPORTSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING - B FIGS 3.19 TO 3.Supporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 3.1 WOODLAND MANAGEMENT AND TREE FELLING - B FIGS 3.21 TO 3.Supporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 3.2 OUTLINE CONSTRUCTION ENVIRONMENTAL PLANSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 3.3 OUTLINE DECOMMISSIONING AND RESTRORATION PLANSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 4.1 LEGISLATION POLICY GUIDANCESupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 6.1 CONSULTEE KEY ISSUES ABD CONSULTANT COMMENTSSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 6.2 CONSULKTEE MEETINGS KEY ISSUESSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.1 LVIA METHODOLOGYSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.2 DETAILED ASSESSSMENT OF VIEWPOINTSSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.3 CNP SPECIAL QUALITIESSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.4 RESIDENTIAL VISUAL AMEINTY SURVEY PART 1Supporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.4 RESIDENTIAL VISUAL AMEINTY SURVEY PART 2Supporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.4 RESIDENTIAL VISUAL AMEINTY SURVEY PART 3Supporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.5 LVIA FUTURE BASELINE ASSESSMENTSupporting Document · PDF17 Dec 2018View
TECHNICAL APPENDIX 7.6 NIGHT TIME ASSESSMENTSupporting Document · PDF17 Dec 2018View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Expiry Date for Comments

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Decision Issued Date

    Published milestoneCouncil source
  6. Decision Made Date

    Published milestoneCouncil source
  7. Standard Consultation Date

    Published milestoneCouncil source
  8. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Objections
DECISION LETTER
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.