Time Limit The development to which this permission relates must be begun not later than the expiration of three years beginning with the date on which this permission is granted. Reason: In order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended).
Materials - Matching The materials to be used in the construction of the external surfaces (including windows) of the development hereby permitted shall match those used in the existing building, or shall be in accordance with details to be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved details. Reason: To ensure the use of appropriate materials in the interests of the visual amenities of the area having regard for policies DC1, CS4 and CS5 of the Local Plan and section 12 of the NPPF.
The development hereby approved shall be carried out in complete accordance with the plans and specifications detailed below and shall relate to no other plans: a) Proposed floor plans 03, received 13 September 2022 b) Proposed sectional plans 05, received 13 September 2022 c) Proposed elevation plans 04, received 13 September 2022 d) Site plan, received 5 October 2022 e) Location plan, received 13 September 2022 Reason: To ensure a satisfactory form of development and for the avoidance of doubt.
The development must be carried out in accordance with the approved details. In particular the garage must be created on the ground floor as per plans 03 received on13 September 22 and retained in perpetuity for use as a garage, at a size of no less than 6m by 3m as measured internally. Reason: To retain adequate in curtilage parking provision in the interests of amenity and highway safety having regard for policies CS4, CS5, DC1 and sections 9 and 12 of the NPPF.
It is considered that the proposal is in accordance with the Policies within the Local Development Framework Core Strategy and Development Policies document in that the scale, design and materials proposed are appropriate to the site location and there will be no demonstrable adverse impact on adjacent residential amenity. The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including LDF Policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out in the National Planning Policy Framework.
The applicant is reminded that building materials shall not be deposited on the highway without the specific consent of the Highway Authority.
Deliveries to Site It should be ensured that, during construction, deliveries to the site do not obstruct the highway. If deliveries are to be made which may cause an obstruction then early discussion should be had with the Highway Authority on the timing of these deliveries and measures that may be required so as to mitigate the effect of the obstruction to the general public.
Rights of Access/Encroachment This planning approval does not permit any person to access another person’s land/property to enable the works to be completed, without their consent. Any encroachment into another person’s land/property above or below ground is a civil matter to be resolved between the relevant parties.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.