Council planning record

Variation of Conditions 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 20, 21 and 24 of planning application 22/00592/FUL to vary building sizes due to the reuse of steel frames from existing dismantled buildings (circular economy practices) and minor changes to landscape and drainage schemes following technical design development

Land At Langar Industrial Estate Langar Lane Harby

DecidedReference: 24/00532/VACMelton Borough Council

Last published check: 28 Sept 2026, 07:02. Check the council record for more recent changes.

Application location

Land At Langar Industrial Estate Langar Lane Harby

This record has no verified map location.

View council map

Application summary

Status
Decided
Application type
Variation of Condition
Received
22 May 2024
Validated
30 May 2024
Determination deadline
29 Aug 2024
Local authority
Melton Borough Council

Application overview

Variation of Conditions 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 20, 21 and 24 of planning application 22/00592/FUL to vary building sizes due to the reuse of steel frames from existing dismantled buildings (circular economy practices) and minor changes to landscape and drainage schemes following technical design development

Proposal details

Reference
24/00532/VAC
Alternative references
PP-13086705
Ward
Long Clawson And Stathern
Parish
Clawson Hose And Harby
Agent
HSSP Architects Limited

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 79 of 79

DocumentPublishedAction
AppraisalOfficer Notes · PDF25 Oct 2024View
Decision noticeDecision · PDF25 Oct 2024View
Ecology comments 26.09.2024Consultation replies · PDF26 Sept 2024View
Addendum to landscape management spec 16.09.2024Application Documents · PDF16 Sept 2024View
Lcc ecology comments 05.09.24Consultation replies · PDF5 Sept 2024View
Proposed external lighting 28.08.2024Forms and plans · PDF28 Aug 2024View
Lcc forestry comments, 27.08.2024Consultation replies · PDF27 Aug 2024View
Llfa comments 19.08.2024Consultation replies · PDF19 Aug 2024View
Environment agency comments, 08.08.2024Consultation replies · PDF8 Aug 2024View
Amended - jit landscaping plan 5.8.24Forms and plans · PDF5 Aug 2024View
Additional - below ground drainage typical details (sheet 6) 5.8.24Forms and plans · PDF5 Aug 2024View
Lcc highways comments, 30.07.2024Consultation replies · PDF30 Jul 2024View
Amended plans - proposed s278 works visability splays 19.07.24Forms and plans · PDF19 Jul 2024View
Lcc highways comments, 12.07.2024Consultation replies · PDF12 Jul 2024View
Rushcliffe district borough council response, 11.07.2024Consultation replies · PDF11 Jul 2024View
Lcc ecology comments, 04.07.2024Consultation replies · PDF4 Jul 2024View
Landscaping plan 03.07.2024Forms and plans · PDF3 Jul 2024View
Site access route plan 03.07.2024Forms and plans · PDF3 Jul 2024View
Construction phasing plan 03.07.2024Forms and plans · PDF3 Jul 2024View
Llfa comments, 28.06.2024Consultation replies · PDF28 Jun 2024View
Lcc forestry comments, 28.06.2024Consultation replies · PDF28 Jun 2024View
Lcc highways comments, 26.06.2024Consultation replies · PDF26 Jun 2024View
Mbc environmental health officer comments, 17.06.2024Consultation replies · PDF17 Jun 2024View
Lcc obligations/planning control (minerals) comments, 12.06.2024Consultation replies · PDF12 Jun 2024View
Environment agency comments, 10.06.2024Consultation replies · PDF10 Jun 2024View
N.a.t.s consultation reply, 07.06.2024Consultation replies · PDF7 Jun 2024View
Jit boundary treatment plan 30.05.2024Forms and plans · PDF30 May 2024View
Jit site plan phase 1 30.05.2024Forms and plans · PDF30 May 2024View
Jit parking and ev charging plan 30.05.2024Forms and plans · PDF30 May 2024View
Block plan proposed 30.05.2024Forms and plans · PDF30 May 2024View
Jit site plan 30.05.2024Forms and plans · PDF30 May 2024View
Block plan existing 30.05.2024Forms and plans · PDF30 May 2024View
Site plan existing 30.05.2024Forms and plans · PDF30 May 2024View
Application form without personal data 29.05.2024Forms and plans · PDF29 May 2024View
Application summary and proposed conditions 29.05.2024Application Documents29 May 2024View
External services layout 29.05.2024Forms and plans · PDF29 May 2024View
Proposed external lighting 29.05.2024Forms and plans · PDF29 May 2024View
3d visual 22.05.2024Application Documents · PDF22 May 2024View
Construction method statement 22.05.2024Application Documents · PDF22 May 2024View
Surface water management plan 22.05.2024Application Documents · PDF22 May 2024View
External works specification 22.05.2024Application Documents · PDF22 May 2024View
Specification for below ground drainage 22.05.2024Application Documents · PDF22 May 2024View
Below ground drainage 22.05.2024Application Documents · PDF22 May 2024View
Drainage documentation 22.05.2024Application Documents · PDF22 May 2024View
Below ground drainage report 22.05.2024Application Documents · PDF22 May 2024View
External works typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Below ground drainage typical details 22.05.2024Forms and plans · PDF22 May 2024View
Proposed external levels 22.05.2024Forms and plans · PDF22 May 2024View
Proposed construction joint layout 22.05.2024Forms and plans · PDF22 May 2024View
Manhole schedule 22.05.2024Application Documents · PDF22 May 2024View
Below ground drainage general arrangement 22.05.2024Forms and plans · PDF22 May 2024View
Proposed works typical details 22.05.2024Forms and plans · PDF22 May 2024View
Propoed works site clearance 22.05.2024Forms and plans · PDF22 May 2024View
General arrangement and setting out 22.05.2024Forms and plans · PDF22 May 2024View
Desk study and investigation report 22.05.2024Application Documents · PDF22 May 2024View
Biodiversity metric calculation tool 22.05.2024Application Documents22 May 2024View
Biodiversity survey and report 22.05.2024Application Documents · PDF22 May 2024View
Landscaping details 22.05.2024Application Documents · PDF22 May 2024View
Tree survey 22.05.2024Application Documents · PDF22 May 2024View
Baseline onsite habitat survey report (pre-development) 22.05.2024Application Documents · PDF22 May 2024View
Baseline onsite habitat survey report (pre-development) 22.05.2024Application Documents · PDF22 May 2024View
Site access route plan 22.05.2024Forms and plans · PDF22 May 2024View
Substation plans and elevations 22.05.2024Forms and plans · PDF22 May 2024View
Building 3 elevations/sections 22.05.2024Forms and plans · PDF22 May 2024View
Building 2 elevations/sections 22.05.2024Forms and plans · PDF22 May 2024View
Building 2 elevations/sections 22.05.2024Forms and plans · PDF22 May 2024View
Building 2 roof plan 22.05.2024Forms and plans · PDF22 May 2024View
Building 2 floor plans 22.05.2024Forms and plans · PDF22 May 2024View
Building 1 elevations/sections 22.05.2024Forms and plans · PDF22 May 2024View
Building 1 elevations/sections 22.05.2024Forms and plans · PDF22 May 2024View
Building 1 roof plan 22.05.2024Forms and plans · PDF22 May 2024View
Building 1 floor plans 22.05.2024Forms and plans · PDF22 May 2024View
Street scene/context plan - proposed 22.05.2024Forms and plans · PDF22 May 2024View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  4. Last Site Notice Posted Date

    Published milestoneCouncil source
  5. Last Advertised In Press Date

    Published milestoneCouncil source
  6. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Standard Consultation Date

    Published milestoneCouncil source
  10. Latest Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  11. Agreed Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  12. Decision Issued Date

    Published milestoneCouncil source
  13. Decision Made Date

    Published milestoneCouncil source
  14. Permission Expiry Date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Permit
Decision notice

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.