Non-Material Amendment to Condition 34 of planning permission 2014/1440/02 is sought to allow a delay in the delivery of the reclamation scheme approved via this condition until either 12 months following construction of the ERF or by 31st March 2022.

BIFFA WASTE SERVICES, CHARNWOOD QUARRY, ASHBY ROAD EAST, SHEPSHED, LEICESTERSHIRE

Leicestershire County CouncilReference 2017/NMA/0011/LCC

Last published check: 7 Nov 2026, 09:56. Check the council record for more recent changes.

Status and dates

Last published check: 7 Nov 2026, 09:56 (UK)

  1. DoneReceived11 Jan 2017
  2. DoneValidated13 Jan 2017
  3. Not publishedConsultationNo date on council record
  4. Not publishedTarget decision dateNo date on council record
  5. DecidedApprovedNot published

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (2)
  1. Received

    Published milestoneCouncil source
  2. Valid

    Published milestoneCouncil source
Documents
2 published

Proposal

Non-Material Amendment to Condition 34 of planning permission 2014/1440/02 is sought to allow a delay in the delivery of the reclamation scheme approved via this condition until either 12 months following construction of the ERF or by 31st March 2022.

Reference
2017/NMA/0011/LCC

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • Non Material Amendment Report_Redacted.pdfNon Material Amendment Report_Redacted.pdf (91 kb)Not publishedView
  • Non Material Amendment Decision.pdfNon Material Amendment Decision.pdf (47 kb)Not publishedView

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Approved
Non Material Amendment Decision.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.