Proposed new electric substation and switchgear enclosure; provision of a new gate within the existing boundary wall to provide a vehicular access to the substation; relocation of existing pedestrian gate and relocation and replacement of the guard rail between the pedestrian access and the road
Proposed new electric substation and switchgear enclosure; provision of a new gate within the existing boundary wall to provide a vehicular access to the substation; relocation of existing pedestrian gate and relocation and replacement of the guard rail between the pedestrian access and the road
Reference
KCC/GR/0102/2018
Alternative references
GR/18/681
Agent
Bailey Partnership
Sign in to view all collected council fields and recorded changes.
Supporting Statement (2).pdfApplication Documents13 Jun 2018View
Application form (2).pdfApplication Documents13 Jun 2018View
MGS-BPC-XX-XX-DR-A-050004_P1 Site Plan Electric Substation & New Gates in existing wall.pdfApplication Plans & Drawings17 Aug 2018View
MGS BPC XX XX DR A 050001 P1 Site Plan New Electric Substation and Switchgear Enclosure.pdfApplication Plans & Drawings13 Jun 2018View
MGS BPC XX XX DR A 050003 P1 Block Plan New Electric Substation and Switchgear Enclosure.pdfApplication Plans & Drawings13 Jun 2018View
MGS BPC XX XX DR A 050002 P1 Layout Plan Section and Elevations New Electric Substation and Switchgear Enclosure.pdfApplication Plans & Drawings13 Jun 2018View
DECISION NOTICE_KCC-GR-0102-2018(6)(1).pdfDecision23 Aug 2018View
SITE NOTICE_KCC-GR-0102-2018.docPublicity22 Jun 2018View
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.