Council planning record

INSTALLATION OF 49.9 MEGAWATT SOLAR FARM WITH ASSOCIATED INFRASTRUCTURE INCLUDING: SERIES OF SOLAR PHOTOVOLTAIC MODULES IN ARRAYS WITH STRING CONVERTERS, TRANSFORMERS, SUBSTATION, FENCING AND THERMAL CCTV CAMERAS, ACCESS TRACKS, CABLING, LANDSCAPING AND OTHER HABITAT CREATION

CLIFTON MARSH FARM PRESTON NEW ROAD NEWTON WITH CLIFTON PRESTON PR4 0XE

Granted Subject to S106 & BNGReference: 24/0414Fylde Borough Council

Application location

CLIFTON MARSH FARM PRESTON NEW ROAD NEWTON WITH CLIFTON PRESTON PR4 0XE

This record has no verified map location.

Application summary

Status
Granted Subject to S106 & BNG
Application type
Full Planning Permission
Received
11 Jul 2024
Validated
22 Jul 2024
Determination deadline
Not published
Local authority
Fylde Borough Council

Application overview

INSTALLATION OF 49.9 MEGAWATT SOLAR FARM WITH ASSOCIATED INFRASTRUCTURE INCLUDING: SERIES OF SOLAR PHOTOVOLTAIC MODULES IN ARRAYS WITH STRING CONVERTERS, TRANSFORMERS, SUBSTATION, FENCING AND THERMAL CCTV CAMERAS, ACCESS TRACKS, CABLING, LANDSCAPING AND OTHER HABITAT CREATION

Proposal details

Reference
24/0414
Ward
Rural East Fylde
Parish
Newton with Clifton, Freckleton
Agent
Megan Griffiths, Natural Power

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 183 of 183

DocumentPublishedAction
Decision NoticeDecision4 Aug 2026View
S106 Unilateral Undertaking Dated 03.08.26. redactedSection 106 Legal Agreement3 Aug 2026View
NE response Agricultural land classificationConsultee Comment6 Nov 2025View
Environmental Statement Vol 3: Appendix 6.1 Agricultural Land Classification (revision)Background Documents22 Oct 2025View
United UtilitiesConsultee Comment16 Oct 2025View
MoDConsultee Comment7 Oct 2025View
Highway AuthorityConsultee Comment6 Oct 2025View
Electricity North WestConsultee Comment1 Oct 2025View
Natural EnglandConsultee Comment30 Sept 2025View
GMEU EcologistsConsultee Comment25 Sept 2025View
Freckleton parish councilConsultee Comment24 Sept 2025View
UU commentConsultee Comment15 Sept 2025View
Newton with Clifton Parish CouncilConsultee Comment8 Sept 2025View
LLFA Response.Consultee Comment28 Aug 2025View
Blackpool AirportConsultee Comment27 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 2.1 Amended Site ConstraintsAmended Plan20 Aug 2025View
LCC Archaeology August 2025Consultee Comment20 Aug 2025View
Environment Agency August 2025Consultee Comment20 Aug 2025View
National Gas TransmissionConsultee Comment18 Aug 2025View
British Pipeline Agency CommentsConsultee Comment13 Aug 2025View
British Pipeline Agency PlanConsultee Comment13 Aug 2025View
Objection - National Gas TransmissionConsultee Comment11 Aug 2025View
National Gas TransmissionConsultee Comment7 Aug 2025View
NATS SafeguardingConsultee Comment7 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.11 Wintering Bird Survey (Dec 24-Feb 25)Initial Drawing6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.12 Autumn Bird Survey (Sept 24-Nov 24)Initial Drawing6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.13 Spring Bird Survey (March 25-May 25)Initial Drawing6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.10 Post Construction Biodiversity PlanAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.9 Baseline Biodiversity AssessmentAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 5.8 Biodiversity Enhancement PlanAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 3.1 Indicative Panel & Access DetailsAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 3.3 Indicative SubstationAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 3.6 Indicative Storage ContainerAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 4.7 Amended Outline Landscape PlanAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 6.3 Amended Flood Zone OverviewAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 6.4 Amended Fluvial Flood RiskAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 6.5 Amended Topographic Wetness IndexAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 6.6 Amended Flow AccumulationAmended Plan6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 4: Front Cover Non technical SummaryBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 4: Non technical SummaryBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Front Cover and Table of ContentsBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Section 1 (Introduction)Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Section 5 (Ecology & Ornithology)Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Section 7 (Traffic and Transport Statement)Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Section 9 (Other Matters (Utilities & pipelines)Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 1: Section 11 (Schedule of Mitigation)Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Supporting Figures Front Cover and Table of ContentsBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Front Cover and Table of ContentsBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 5.2 Updated Shadow Habitat Regulations AssessmentBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 5.4 Updated Outline Habitat Management PlanBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 5.5 Marine Conservation Zone AssessmentBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 6.1 Amended Agricultural Land ClassificationBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 6.1a Agricultural Land Classification - Natural England Soils ConsultationBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 6.2 Amended Flood Risk Assessment and Drainage StrategyBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 6.4 Flood Risk Sequential TestBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 7.1 Construction Traffic Management PlanBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 7.2 Vehicle swept path drawingsBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.3 Updated Cumulative AssessmentBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.4 updated Site Capacity LetterBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 1Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 2Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 3Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 4Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 5Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 6Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 9.5 Arboricultural Assessment Part 7Background Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 10.2 Written Scheme of Investigation for Geophysical SurveyBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 10.3 Geophysical Survey ReportBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 10.4 Letter Issued to LCC Archaeology to address additional responseBackground Documents6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 3: Appendix 5.3 Amended Biodiversity Net Gain Assessment (metric)Biodiversity Net Gain Metric6 Aug 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 2.1 Amended Site ConstraintsSuperseded6 Aug 2025View
Agent ALC response to NE commentBackground Documents22 Jul 2025View
Supplementary Environmental Information - Env Statement Vol 2: Fig 1.2a Site LayoutAmended Plan6 Jul 2025View
(Revised) Environmental Statement Vol 3: Appendix 6.1 Agricultural Land ClassificationBackground Documents30 Apr 2025View
ALC supporting letter from AgentBackground Documents30 Apr 2025View
SABIC UK Petrochemicals LtdConsultee Comment20 Feb 2025View
Ecology response from AgentBackground Documents28 Nov 2024View
BAEConsultee Comment12 Nov 2024View
Natural England (agricultural land comment)Consultee Comment30 Sept 2024View
Ministry of DefenceConsultee Comment30 Sept 2024View
Public Rights of WayConsultee Comment24 Sept 2024View
Additional comments Historic Environment TeamConsultee Comment24 Sept 2024View
GMEU (2) re GCNConsultee Comment18 Sept 2024View
GMEU (1)Consultee Comment11 Sept 2024View
Natural EnglandConsultee Comment5 Sept 2024View
LCC Highways (August 24)Consultee Comment30 Aug 2024View
United UtilitiesConsultee Comment29 Aug 2024View
LCC Historic Environment TeamConsultee Comment29 Aug 2024View
Fylde Bird ClubConsultee Comment28 Aug 2024View
National GridConsultee Comment27 Aug 2024View
Newton Parish Council letterConsultee Comment23 Aug 2024View
national gridConsultee Comment14 Aug 2024View
preston councilConsultee Comment14 Aug 2024View
Environment Agency August 24Consultee Comment14 Aug 2024View
LCC Local Lead Flood AuthorityConsultee Comment13 Aug 2024View
Blackpool AirportConsultee Comment10 Aug 2024View
South Ribble Borough CouncilConsultee Comment8 Aug 2024View
Env ProtectionConsultee Comment8 Aug 2024View
BPA email attachment (1) Managing-developments-and-works-in-the-proximity-of-high-pressure-pipelinesBackground Documents6 Aug 2024View
BPA email attachment (2) Tree plantingBackground Documents6 Aug 2024View
BPA email attachment (3) Guide for Developers Working Around PipelinesBackground Documents6 Aug 2024View
BPA attachment (4) Cathodic Protection Guidance for Solar FarmsBackground Documents6 Aug 2024View
British Pipeline Agency (BPA)Consultee Comment6 Aug 2024View
Freckleton Parish CouncilConsultee Comment6 Aug 2024View
National Gas Email 1Consultee Comment6 Aug 2024View
HSE Land Use AssessmentConsultee Comment6 Aug 2024View
Health & Safety ExecutiveConsultee Comment1 Aug 2024View
national gas 1 of 2Consultee Comment29 Jul 2024View
national gas 2 of 2Consultee Comment29 Jul 2024View
electricity north westConsultee Comment26 Jul 2024View
Application Form RedactedApplication Form No Personal Data24 Jul 2024View
NATS SafeguardomgConsultee Comment24 Jul 2024View
ES Vol 2: Fig 6.3.1 Contaminated Land OverviewInitial Drawing22 Jul 2024View
ES Vol 2: Fig 6.6 Flow AccumulationSuperseded22 Jul 2024View
ES Vol 2: Fig 6.5 Topographic Wetness IndexSuperseded22 Jul 2024View
ES Vol 2: Fig 6.2 LiDar TerrainInitial Drawing22 Jul 2024View
ES Vol 2: Fig 6.3 Flood Zone OverviewSuperseded22 Jul 2024View
ES Vol 2: Fig 6.4 Fluvial Flood RiskSuperseded22 Jul 2024View
ES Vol 2: Fig 6.1 Hydrological OverviewInitial Drawing22 Jul 2024View
ES Vol 2: Fig 5.10 Post Construction Biodiversity PlanSuperseded22 Jul 2024View
ES Vol 2: Fig 5.7 Wetland & Wintering Bird Survey Results 2022-2023Initial Drawing22 Jul 2024View
ES Vol 2: Fig 5.9 Baseline Biodiversity AssessmentSuperseded22 Jul 2024View
ES Vol 2: Fig 5.8 Biodiversity Enhancement PlanSuperseded22 Jul 2024View
ES Vol 2: Fig 5.6 Breeding Bird Territories 2022Initial Drawing21 Jul 2024View
ES Vol 2: Fig 5.4 Great Crested Newt Risk Zone & PondsInitial Drawing21 Jul 2024View
ES Vol 2: Fig 5.5 Breeding Bird Survey Results 2022Initial Drawing21 Jul 2024View
ES Vol 2: Fig 5.3 Phase 1 Survey results 2022Initial Drawing21 Jul 2024View
ES Vol 2: Fig 5.1 Ecology Survey AreasInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.17 Viewpoint 10 minor road South of A584Initial Drawing21 Jul 2024View
ES Vol 2: Fig 5.2 Statutory & Non Statutory Designated SItesInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.16a Viewpoint 9 minor road South of A584Initial Drawing21 Jul 2024View
ES Vol 2: Fig 4.15 Viewpoint 8 A584 west of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.13 Viewpoint 6 Ribble Way & PROW to south of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.14 Viewpoint 7 Grange Lane, Hutton, south of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.10 Viewpoint 3 A583 east of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.11 Viewpoint 4 Thames St NewtonInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.12 Viewpoint 5 PROW to north of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.9 Viewpoint 2 A584 north of siteInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.8a Viewpoint 1 minor road South of A584Initial Drawing21 Jul 2024View
ES Vol 2: Fig 4.7 Outline Landscape PlanSuperseded21 Jul 2024View
ES Vol 2: Fig 4.6 Residental ReceptorsInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.5 Zone of Theoretical VisibilityInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.4 Landscape CharacterInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.3 TopographyInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.2 Environmental DesignationsInitial Drawing21 Jul 2024View
ES Vol 2: Fig 4.1 LVIA Study AreaInitial Drawing21 Jul 2024View
ES Vol 2: Fig 3.4 Indicative Transformer StationInitial Drawing21 Jul 2024View
ES Vol 2: Fig 3.5 Indicative Customer SubstationInitial Drawing21 Jul 2024View
ES Vol 2: Fig 3.2 Indicative Security Fencing & CCTVInitial Drawing21 Jul 2024View
ES Vol 2: Fig 3.3 Indicative SubstationSuperseded21 Jul 2024View
ES Vol 2: Fig 3.6 Indicative Storage ContainerSuperseded21 Jul 2024View
ES Vol 2: Fig 3.1 Indicative Panel & Access detailsSuperseded21 Jul 2024View
ES Vol 2: Fig 2.1 Site ConstraintsSuperseded21 Jul 2024View
ES Vol 2: Fig 1.2 Site LayoutSuperseded21 Jul 2024View
Planning And Renewable Energy StatementBackground Documents21 Jul 2024View
Design And Access StatementBackground Documents21 Jul 2024View
Environmental Statement Vol 4: Section Non Technical SummaryBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 1 Content and Approach to EIABackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 2 Site Selection and Design EvolutionBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 3 Project DescriptionBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 4 Landscape and Visual Impact AssessmentBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 5 Ecology and OrnithologyBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 6 Hydrology, Geology and Hydrogeology AssessmentBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 7 Traffic and Transport StatementBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 8 NoiseBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 9 Other MattersBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 10 Archaeology and Historic EnvironmentBackground Documents21 Jul 2024View
Environmental Statement Vol 1: Section 11 Schedule of MitigationBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 2.1 Previously Developed Land StatementBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 4 Landscape And Visual Impact AssessmentBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 5.1 Ecology & Ornithology Technical AppendixBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 5.2 Habitats Regulations AssessmentBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 5.3 Biodiversity Net Gain Assessment (metric)Background Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 5.4 Outline Habitat Management PlanBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 6.1 Agricultural Land ClassificationBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 6.2 Flood Risk Assessment & Drainage StrategyBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 6.3 Contaminated Land Desk StudyBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 7.1 Outline Construction Traffic Management PlanBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 8.1 Noise Survey ReportBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 9.1 Solar Photovoltaic Glint And Glare StudyBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 9.2 High Level Electromagnetic Field AssessmentBackground Documents21 Jul 2024View
Environmental Statement Vol 3: Appendix 10.1 Desk Based Assessment And Heritage StatementBackground Documents21 Jul 2024View
ES Vol 2: Fig 1.1 Location PlanLocation Plan11 Jul 2024View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Valid Date

    Published milestoneCouncil source
  3. Consultation Start Date

    Published milestoneCouncil source
  4. Site Notice Date

    Published milestoneCouncil source
  5. Consultation End

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Advert Expiry

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Committee Date (if applicable)

    Published milestoneCouncil source
  8. Decision Date

    Published milestoneCouncil source

Decision & conditions

Granted Subject to S106 & BNG
Decision Notice
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.