Planning permission in principle for erection of a 400kv electricity substation, decommissioning of existing 275kv equipment and associated infrastructure including plant, machinery, accesses, drainage, underground cables and landscaping

Westfield Substation Fife

RegisteredReference: 25/03454/EIAFife

Application location

Westfield Substation Fife

This record has no verified map location.

View council map

Application summary

Status
Registered
Application type
Planning Permission (EIA Development)
Received
19 Dec 2025
Validated
25 Sept 2026
Determination deadline
Not published
Local authority
Fife

Application overview

Planning permission in principle for erection of a 400kv electricity substation, decommissioning of existing 275kv equipment and associated infrastructure including plant, machinery, accesses, drainage, underground cables and landscaping

Proposal details

Reference
25/03454/EIA
Alternative references
100733011-001
Ward
Lochgelly, Cardenden And Benarty
Agent
Scottish Power Energy Networks

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 62 of 62

DocumentPublishedAction
19 - PHASE 1 GROUND INVESTIGATION REPORT PART 1Report · PDF2 Sept 2026View
19 - PHASE 1 GROUND INVESTIGATION REPORT PART 2Report · PDF2 Sept 2026View
PSADApplication Form · PDF1 Sept 2026View
07 - AIR QUALITY ASSESSMENTReport · PDF1 Sept 2026View
05 - ARCHAEOLOGY AND HERITAGE ASSESSMENT PART 1Report · PDF1 Sept 2026View
06 - ARCHAEOLOGY AND HERITAGE ASSESSMENT PART 2Report · PDF1 Sept 2026View
12 - FLOOD RISK ASSESSMENTReport · PDF1 Sept 2026View
10 - TRANSPORT STATEMENT PART 1Report · PDF1 Sept 2026View
10 - TRANSPORT STATEMENT PART 2Report · PDF1 Sept 2026View
10 - TRANSPORT STATEMENT PART 3Report · PDF1 Sept 2026View
11 - ARBORICULTURE REPORTReport · PDF1 Sept 2026View
13 - EIA NON TECHNICAL SUMMARYReport · PDF1 Sept 2026View
14 - EIA VOL 01 MAIN REPORTReport · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 1.1 - PROJECT OVERVIEW PLANDrawing1 Sept 2026View
15 - EIA VOL 02 FIG. 1.2 - LOCATION PLANDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 1.3 - EXISTING SITE PLANDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.1 - INDICATIVE SITE PLANDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.2 - ILLUSTRATIVE LANDSCAPE STRATEGYDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.2 - ILLUSTRATIVE LANDSCAPE STRATEGYDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.3 - ILLUSTRATIVE CROSS SECTIONDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.4 - ILLUSTRATIVE DRAINAGE LAYOUTDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.5 - MAXIMUM HEIGHTSDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.6 - OHL RECONFIGURATIONDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 3.7 - TREE PROTECTION PLANDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.1 - SUBSTATION LOCATIONDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.2 - SITE CONTEXT AND LOCAL CHARACTERPhoto · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.3 - PLANNING DESIGNATIONS AND LOCAL CONTEXTDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.4 - LANDSCAPE CHARACTERDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.5 - TOPOGRAPHYDrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 6.6 - ZTV AND PHOTOVIEWPOINT LOCATIONSDrawing1 Sept 2026View
15 - EIA VOL 02 FIG. 6.7 - PHOTO VIEWPOINTSPhoto · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 9.1 - MONITORING LOCATIONSPhoto · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 9.2 - IAQM DUSTBAND CRITERIADrawing · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 10.1 - NSR LOCATIONSPhoto · PDF1 Sept 2026View
15 - EIA VOL 02 FIG. 12.1 - CUMULATIVE SITE LOCATIONSDrawing · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 1.1 - SCHED. 9 STATEMENT ON AMENITY PRESERVATIONReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 2.1 - EIA SCOPINGReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 2.2 - PRE-APP DECISION LETTERReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 3.1 - OUTLINE CEMPReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 6.1 - LANDSCAPE AND VISUAL IMPACT ASSESSMENTReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 7.1 - ECOLOGICAL APPRAISAL REPORT PART 1Report · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 7.1 - ECOLOGICAL APPRAISAL REPORT PART 2Report · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 7.1 - ECOLOGICAL APPRAISAL REPORT PART 3Report · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 7.2 - BIODIVERSITY STATEMENTReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 7.3 - HRA PROFORMAReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 8.1 - 2024 TRAFFIC COUNT SURVEY RESULTSReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 9.1 TO 9.3 - IAQM DUST GUIDANCE AND EPUK, IAQM, EPS AND RTPReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 10.1 - EHO CONSULTATIONReport · PDF1 Sept 2026View
16 - EIA VOL 03 APP. 10.2 - NOISE ASSESSMENTReport · PDF1 Sept 2026View
17 - PLANNING STATEMENTReport · PDF1 Sept 2026View
18 - ACCESS SWEPT PATH ANALYSISOther · PDF1 Sept 2026View
CARDENDEN CCConsultee · PDF20 Jan 2026View
Case Detail and NN ListCase Detail and NN List · PDF14 Jan 2026View
PAN CUSTOMER GUIDANCE NOTEOther · PDF22 Dec 2025View
PSADApplication Form · PDF22 Dec 2025View
08 - PAC REPORT AND APPENDICES A TO IReport · PDF22 Dec 2025View
PSADApplication Form · PDF22 Dec 2025View
01 - LOCATION PLANOS Extract · PDF19 Dec 2025View
09 - PAC REPORT APPENDICES J TO NReport · PDF19 Dec 2025View
Application FormApplication Form · PDF19 Dec 2025View
04 - PROPOSED SITE PLANOS Extract · PDF19 Dec 2025View
02 - SITE LOCATION PLANOS Extract · PDF19 Dec 2025View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Neighbour Consultation Expiry Date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Decision not yet published
16 - EIA VOL 03 APP. 2.2 - PRE-APP DECISION LETTER
Planning conditions

We haven’t collected any decision conditions for this application.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.