Council planning record

Variation of conditions 3 (surface water drainage) and 10 (list of approved drawings) relating to planning permission F/YR21/0887/F (Erect 1 x office/workshop, 1 x vehicle workshop and 1 x training centre, 2.4m high (approx) fence and formation of car park and associated infrastructure) to enable submission of a detailed surface water drainage strategy (including levels); revised layout and hardstanding to reflect this, revised training room design and inclusion of a substation

Land North West Of Middle Level Commissioners Whittlesey Road March Cambridgeshire

GrantedReference: F/YR25/0466/VOCFenland District Council

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Last Site Notice Posted Date

    Published milestoneCouncil source
  5. Last Advertised In Press Date

    Published milestoneCouncil source
  6. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  7. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  10. Standard Consultation Date

    Published milestoneCouncil source
  11. Standard Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  12. Agreed Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  13. Decision Issued Date

    Published milestoneCouncil source
  14. Decision Made Date

    Published milestoneCouncil source
  15. Permission Expiry Date

    Published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Application summary

Status
Granted
Application type
Variation or removal of condition
Received
12 Jun 2025
Validated
16 Jun 2025
Determination deadline
15 Sept 2025
Local authority
Fenland District Council

Application overview

Variation of conditions 3 (surface water drainage) and 10 (list of approved drawings) relating to planning permission F/YR21/0887/F (Erect 1 x office/workshop, 1 x vehicle workshop and 1 x training centre, 2.4m high (approx) fence and formation of car park and associated infrastructure) to enable submission of a detailed surface water drainage strategy (including levels); revised layout and hardstanding to reflect this, revised training room design and inclusion of a substation

Proposal details

Reference
F/YR25/0466/VOC
Alternative references
PP-14087625
Ward
March West And Benwick
Parish
March Town Council
Agent
Morton & Hall Consulting Ltd

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Land North West Of Middle Level Commissioners Whittlesey Road March Cambridgeshire

This record has no verified map location.

View council map

Documents 72 of 72

DocumentPublishedAction
Officer ReportOfficer Report · PDF4 Sept 2026View
Decision NoticeDecision Notice · PDF4 Sept 2026View
CCC LEAD LOCAL FLOOD AUTHORITYConsultee Comment · PDF19 Aug 2026View
TECH RESPONSE TO LLFAStatement · PDF11 Aug 2026View
TO AGENT WITH LLFA COMMENTCorrespondence · PDF23 Jul 2026View
EOT 04.09.2026Agreement to extension of time · PDF23 Jul 2026View
CCC FLOOD RISK TEAMConsultee Comment · PDF15 Jul 2026View
TECH RESPONSE TO LLFAStatement · PDF1 Jul 2026View
EOT 31.07.26Agreement to extension of time · PDF1 Jul 2026View
Reconsultation SheetReconsultation Sheet · PDF1 Jul 2026View
REQUEST FOR UPDATE AND FURTHER EOTCorrespondence · PDF24 Apr 2026View
AGREEMENT TO EOT - 29/5/26Agreement to extension of time · PDF24 Apr 2026View
FDC TREE CONSULTANTConsultee Comment · PDF29 Mar 2026View
CCC LEAD LOCAL FLOOR AUTHORITYConsultee Comment · PDF10 Mar 2026View
MARCH TOWN COUNCILConsultee Comment · PDF6 Mar 2026View
ANGLIAN WATERConsultee Comment · PDF6 Mar 2026View
DEFINITIVE MAP TEAMConsultee Comment · PDF26 Feb 2026View
MIDDLE LEVEL COMMISSIONERSConsultee Comment · PDF26 Feb 2026View
FDC ENVIRONMENT & HEALTHConsultee Comment · PDF25 Feb 2026View
Further Consultation SheetFurther Consultation Sheet · PDF23 Feb 2026View
Reconsultation SheetReconsultation Sheet · PDF23 Feb 2026View
AGREEMENT TO EOT - 17/4/26 AND REVISED DESCRIPTIONAgreement to extension of time · PDF20 Feb 2026View
Schedule of Change/sSchedule of Change/s · PDF11 Feb 2026View
AMENDMENT STATEMENTStatement · PDF11 Feb 2026View
PROPOSED SITE PLAN AND SUBSTATION DETAILSDrawing · PDF11 Feb 2026View
EMAIL FROM AGENT WITH REVISED DETAILSCorrespondence · PDF11 Feb 2026View
EMAIL TO AGENT WITH QUERIESCorrespondence · PDF4 Feb 2026View
AMENDMENT STATEMENTCANCELLED · PDF14 Jan 2026View
SCHEDULE OF CHANGE/SCANCELLED · PDF14 Jan 2026View
PROPOSED SITE PLANCANCELLED · PDF14 Jan 2026View
EXISTING AND PROPOSED SITE SECTIONSDrawing · PDF14 Jan 2026View
EMAIL FROM AGENT WITH REVISED DETAILSCorrespondence · PDF14 Jan 2026View
AGREEMENT TO EOT - 16/1/26Agreement to extension of time · PDF11 Nov 2025View
EMAIL FROM AGENT IN RESPONSE TO QUERIESCorrespondence · PDF4 Nov 2025View
EMAIL TO AGENT WITH QUERIESCorrespondence · PDF31 Oct 2025View
PROPOSED CONTOUR LAYOUTDrawing · PDF29 Sept 2025View
ENGINEERING LAYOUTDrawing · PDF29 Sept 2025View
POND 1 DETAILDrawing · PDF29 Sept 2025View
POND 2 DETAILDrawing · PDF29 Sept 2025View
POND 3 DETAILDrawing · PDF29 Sept 2025View
ACO V-SEPTOR SPECIFICATIONDrawing · PDF29 Sept 2025View
DRAINAGE SPECIFICATIONDrawing · PDF29 Sept 2025View
SURFACING AND KERBING PLANDrawing · PDF29 Sept 2025View
CONCRETE YARD 10 YEAR CALCSOther · PDF29 Sept 2025View
CONCRETE YARD 100 YEAR CALCSOther · PDF29 Sept 2025View
POND 1 10 YEAR CALCSOther · PDF29 Sept 2025View
POND 1 100 YEAR CALCSOther · PDF29 Sept 2025View
POND 2 10 YEAR CALCSOther · PDF29 Sept 2025View
POND 2 100 YEAR CALCSOther · PDF29 Sept 2025View
POND 3 10 YEAR CALCSOther · PDF29 Sept 2025View
POND 3 100 YEAR CALCSOther · PDF29 Sept 2025View
FDC TREE CONSULTANTConsultee Comment · PDF26 Jul 2025View
18 - 20 COMMERCIAL ROAD, MARCHNeighbour Response · PDF22 Jul 2025View
UNIT 3, 38 WHITTLESEY ROAD, MARCHReturned Post · PDF11 Jul 2025View
UNIT 2, 38 WHITTLESEY ROAD, MARCHReturned Post · PDF11 Jul 2025View
UNIT 1, 38 WHITTLESEY ROAD, MARCHReturned Post · PDF11 Jul 2025View
ENVIRONMENT AGENCYConsultee Comment · PDF9 Jul 2025View
MARCH TOWN COUNCILConsultee Comment · PDF8 Jul 2025View
Further Consultation SheetFurther Consultation Sheet · PDF7 Jul 2025View
49 WHITTLESEY ROAD MARCHReturned Post · PDF1 Jul 2025View
MIDDLE LEVEL COMMISSIONERSConsultee Comment · PDF27 Jun 2025View
AGREEMENT TO EOT 15/11/25Agreement to extension of time · PDF26 Jun 2025View
CANCELLEDCANCELLED · PDF23 Jun 2025View
Neighbour Consultee ListNeighbour Consultee List · PDF23 Jun 2025View
PROPOSED SITE PLANCANCELLED · PDF16 Jun 2025View
LOCATION PLANDrawing · PDF16 Jun 2025View
PROPOSED FLOOR PLAN, ELEVATIONS AND SECTIONDrawing · PDF16 Jun 2025View
TREE SURVEYCANCELLED · PDF16 Jun 2025View
DECISION NOTICE FOR F/YR21/0887/FOther · PDF16 Jun 2025View
WITHOUT PERSONAL DATAApplication Form · PDF16 Jun 2025View
SCHEDULE OF CHANGESCANCELLED · PDF16 Jun 2025View
AMENDMENT STATEMENTCANCELLED · PDF16 Jun 2025View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Grant

Appeal status: Unknown

Decision Notice DECISION NOTICE FOR F/YR21/0887/F
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.