ApprovedCouncil status: Decision Made

Continuation of development permitted by ESS/61/17/BAS without compliance with condition 2 and 3 (timescale's for cessation of use and completion of restoration) to allow retention of the transformer/substation room and no.4 storage tanks. ESS/61/17/BAS was a variation of ESS/21/11/BAS which was for “The retention of the substation/transformer room, centrifuge building, control room and laboratory and 4 storage tanks. The change of use of the centrifuge building to a storeroom, change of use of the control room to a mess room for the compost operators and the change of use of the laboratory as a support facility for the nearby leachate treatment plant."

Pitsea Landfill, Pitsea Hall Lane, Pitsea, Essex, SS16 4UH

Essex County CouncilReference ESS/123/22/BASRemoval/Variation of Condition ESS

Last published check: 28 Oct 2026, 10:36. Check the council record for more recent changes.

Status and dates

Last published check: 28 Oct 2026, 10:36 (UK)

  1. DoneReceived6 Dec 2022
  2. DoneValidated16 Jan 2023
  3. Not publishedConsultationNo date on council record
  4. Not publishedTarget decision dateNo date on council record
  5. DecidedGranted23 Jun 2023

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (6)
  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Consultation Start

    Published milestoneCouncil source
  4. Consultation Expiry

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Committee / Delegated Decision Date

    Published milestoneCouncil source
  6. Decision Date

    Published milestoneCouncil source
Application type
Removal/Variation of Condition ESS
Documents
15 published

Proposal

Continuation of development permitted by ESS/61/17/BAS without compliance with condition 2 and 3 (timescale's for cessation of use and completion of restoration) to allow retention of the transformer/substation room and no.4 storage tanks. ESS/61/17/BAS was a variation of ESS/21/11/BAS which was for “The retention of the substation/transformer room, centrifuge building, control room and laboratory and 4 storage tanks. The change of use of the centrifuge building to a storeroom, change of use of the control room to a mess room for the compost operators and the change of use of the laboratory as a support facility for the nearby leachate treatment plant."

Reference
ESS/123/22/BAS
Agent
Mr James Cook

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • Delegated ReportDelegated Report21 Jun 2023View
  • Decision NoticeDecision Notice23 Jun 2023View
  • Application Form - Without Personal DataApplication Form - Without Personal Data8 Dec 2022View
  • Planning statementPlanning statement8 Dec 2022View
  • Biodiversity survey and reportBiodiversity survey and report8 Dec 2022View
  • Decision Notice for ESS/61/17/BASDecision Notice for ESS/61/17/BAS11 Jan 2023View
  • The location planThe location plan8 Dec 2022View
  • Layout Plan - ExistingLayout Plan - Existing1 Mar 2023View

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Granted
Decision Notice Decision Notice for ESS/61/17/BAS
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.