The development hereby permitted shall be commenced before the expiration of FIVE years from the date of this decision.
Rhaid dechrau'r datblygiad a ganiateir yma cyn pen PUM mlynedd o ddyddiad y penderfyniad hwn.
The development hereby permitted shall be carried out in accordance with the following approved plans and details contained within the application form, and in any other documents accompanying the application, unless condition(s) to amend them is/are included on this planning decision notice: 002 Site Location Plan (received 09.07.26) 100 Existing Site Plan (received 09.07.26) 150 Proposed Site Plan (received 09.07.26) 200 Existing Site Elevation (received 09.07.26) 201 Existing Site Elevation (received 09.07.26) 202 Existing Site Elevation (received 09.07.26) 203 Existing Site Elevation (received 09.07.26) 204 Existing Site Elevation (received 09.07.26) 250 Proposed Site Elevation (received 09.07.26) 251 Proposed Site Elevation (received 09.07.26) 252 Proposed Site Elevation (received 09.07.26) 253 Proposed Site Elevation (received 09.07.26) 254 Proposed Site Elevation (received 09.07.26) Diesel Generator Specification 28/09/21 Baker Hughes Green Infrastructure Statement & Biodiversity Enhancement Scheme 19.08.26 (received email 26.08.26 15:46)
Mae'n rhaid cyflawni'r datblygiad a ganiateir yma yn unol â'r cynlluniau a gymeradwywyd isod a’r manylion a gynhwysir yn y ffurflen gais, ac mewn unrhyw ddogfennau eraill sy'n cyd-fynd â'r cais, oni bai bod amod(au) i'w diwygio wedi'u cynnwys ar yr hysbysiad penderfyniad cynllunio hwn: 002 Site Location Plan (received 09.07.26) 100 Existing Site Plan (received 09.07.26) 150 Proposed Site Plan (received 09.07.26) 200 Existing Site Elevation (received 09.07.26) 201 Existing Site Elevation (received 09.07.26) 202 Existing Site Elevation (received 09.07.26) 203 Existing Site Elevation (received 09.07.26) 204 Existing Site Elevation (received 09.07.26) 250 Proposed Site Elevation (received 09.07.26) 251 Proposed Site Elevation (received 09.07.26) 252 Proposed Site Elevation (received 09.07.26) 253 Proposed Site Elevation (received 09.07.26) 254 Proposed Site Elevation (received 09.07.26) Diesel Generator Specification 28/09/21 Baker Hughes Green Infrastructure Statement & Biodiversity Enhancement Scheme 19.08.26 (received email 26.08.26 15:46)
3) Within 3 months of the substantial completion of the development hereby approved, the following biodiversity enhancement shall be installed in accordance with the approved Green Infrastructure Statement & Biodiversity Enhancement Scheme 19.08.26 (received email 26.08.26 15:46): 1 RSPB Classic Nest Box The biodiversity enhancement shall thereafter be maintained in accordance with the manufacturer’s instructions and shall be retained for the lifetime of the development; any replacements shall be of an equivalent specification.
O fewn 3 mis i gwblhau'n sylweddol y datblygiad a gymeradwyir drwy hyn, rhaid gosod y mesur gwella bioamrywiaeth canlynol yn unol â'r Datganiad Seilwaith Gwyrdd a'r Cynllun Gwella Bioamrywiaeth cymeradwy dyddiedig 19.08.26 (a dderbyniwyd drwy e-bost ar 26.08.26 am 15:46): 1 Blwch Nythu Classic RSPB Rhaid cynnal y mesur gwella bioamrywiaeth wedi hynny yn unol â chyfarwyddiadau'r gwneuthurwr a rhaid ei gadw ar gyfer oes y datblygiad; rhaid i unrhyw eitemau newydd yn ei le fod o fanyleb gyfatebol.
To Comply with Section 91 (as amended) of the Town and Country Planning Act 1990.
I gydymffurfio a Rhan 91 (fel y diwygiwyd) o'r Ddeddf Gynllunio Gwlad a Thref 1990.
To define the permission and for the avoidance of doubt.
Er mwyn diffinio’r caniatâd ac i osgoi amheuaeth.
To provide biodiversity enhancements in accordance with Strategic Policy D of the adopted Eryri Local Development Plan and Planning Policy Wales.
I ddarparu gwelliannau i fioamrywiaeth yn unol â Pholisi Strategol D Cynllun Datblygu Lleol Eryri a fabwysiadwyd a Pholisi Cynllunio Cymru.
Informative The application proposes non-vulnerable development in Flood Zone 3 (rivers). The applicant/developer should be aware of the potential flood risks and consequences. It is recommended that flood-resilient measures be incorporated in the design.
Nodyn gwybodaeth Mae'r cais yn cynnig datblygiad nad yw'n agored i niwed mewn Parth Llifogydd 3 (afonydd). Dylai'r ymgeisydd/datblygwr fod yn ymwybodol o'r risgiau llifogydd posibl a'r canlyniadau. Argymhellir ymgorffori mesurau sy'n gwneud yr adeiladwaith yn wydn yn wyneb llifogydd yn y dyluniad.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.