The development hereby permitted shall be implemented in accordance with the following plans numbered: 3285/04-01B Reason: For the avoidance of doubt and in the interests of proper planning.
The development hereby permitted shall start no later than three years from the date of this decision. Reason: To comply with Section 91 of the Town and Country Planning Act 1990.
The materials to be used in the construction of the external surfaces of the development hereby permitted shall match in type, colour and texture those used on the existing building. Reason: To ensure a satisfactory visual relationship between the new development and the existing.
Note to Applicant: In the unlikely event of any bats being found during demolition or construction, all work must stop immediately, and Natural England must be called. Additional information is available on the Bat Conservation Trust website at https://www.bats.org.uk/advice/im-working-on-a-building-with-bats/ive-found-a-bat-during-works.
Note to Applicant: New exterior lighting should be avoided, but if necessary for security purposes, then the latest updated lighting guidance note (GN08/23) should be followed. This is available at Guidance Note 8 Bats and Artificial Lighting | Institution of Lighting Professionals (theilp.org.uk).
Note to Applicant: Biodiversity enhancements are required in accordance with Local Plan policy DM 11 and NPPF paragraphs 187d and 192 b, and are recommended in the form of a bat box or a swift nest box. The Bat Conservation Trust recommends installing a bat brick/box at least 4 m above the ground, away from artificial light sources, sheltered from strong winds and exposed to the sun for part of the day, facing south, south-east or south-west. Swift nest boxes are best positioned under the eaves or on walls facing north, northeast or north-west out of direct sunlight, five metres above the ground, with clear adjacent airspace so swifts can access them in a high-speed direct flight.
Note to Applicant: You are reminded of your duties under the Party Wall Act 1996. This requires a building owner to notify and obtain formal agreement from adjoining occupier where the building owner intends to carry out work which involves: 1. Work involving an existing shared wall with another property; 2. Building on the boundary with a neighbouring property; 3. Excavating near a neighbouring building, and that work falls within the scope of the Act. Procedures under this Act are separate from the need for planning permission and building regulations approval. ‘The Party Wall etc. Act 1996: explanatory booklet’ is available at www.communities.gov.uk.
Note to Applicant: In accordance with paragraph 39 of the National Planning Policy Framework (December 2024), Eastleigh Borough Council takes a positive approach to the handling of development proposals so as to achieve, whenever possible, a positive outcome and to ensure all proposals are dealt with in a timely manner.
Related records
No related records were published in this section.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.