The development hereby permitted shall be implemented in accordance with the following plans numbered: Location and Block Plan - 10546-PL-01 Rev A Existing Floor Plan - 10546-PL-02 Rev B Existing Roof Plan - 10546-PL-03 Rev A Existing Elevations Plan (Front and Right Side) - 10546-PL-04 Rev B Existing Elevations Plan (Rear and Left Side) - 10546-PL-05-Rev A Proposed Floor Plan - 10546-PL-06 Proposed Roof Plan - 10546-PL-07 Rev A Proposed Front and Side Elevations - 10546-PL Rev B Proposed Rear and Side Elevations - 10546-PL-09 Rev A Reason: For the avoidance of doubt and in the interests of proper planning.
The development hereby permitted shall start no later than three years from the date of this decision. Reason: To comply with Section 91 of the Town and Country Planning Act 1990.
The materials to be used must match as closely as possible, in type, colour and texture those listed in the Materials Section of the application form. Reason: To ensure a satisfactory visual relationship of the new development to the existing.
Note to Applicant: The existing hedgerow must be protected during construction.
Note to Applicant: Any building materials must be stored covered on hard standing, no fires can be lit on site, chemicals must be stored safely, and any excavations or open pipes must be covered at night or fitted with a small animal escape ramp (slanted rough board) to avoid trapping any animals that have fallen in.
Note to Applicant: Work must only be done during daylight hours. Roof tiles must be removed carefully by hand, and if any bats or signs of bats are found the tiles should be replaced gently, all work must stop immediately and and Natural England must be called. Additional information is available on the Bat Conservation Trust website at https://www.bats.org.uk/advice/im-working-on-a-building-with-bats/ive-found-a-bat-during-works
Note to Applicant: New exterior lighting should be avoided, but if necessary for security purposes, then the latest updated lighting guidance note (GN08/23) should be followed. This is available at Guidance Note 8 Bats and Artificial Lighting | Institution of Lighting Professionals (theilp.org.uk).
Note to Applicant: Biodiversity enhancements have been recommended. A bat brick/box and a swift brick/nest box may be appropriate to build into the extensions. Built in boxes do not require maintenance and cannot fall off. The Bat Conservation Trust recommends installing a bat brick/box at least 4m above the ground, away from artificial light sources, sheltered from strong winds and exposed to the sun for part of the day, facing south, south-east or south-west. (https://www.bats.org.uk › our-work › putting-up-your-box) Swift nest boxes are best positioned under the eaves or on walls facing north, northeast or north-west out of direct sunlight, five metres above the ground, with clear adjacent airspace so swifts can access them in a high-speed direct flight. (https://www.swiftconservation.org/Nestboxes%26Attraction.htm ) Additional information is available at: https://sussexwildlifetrust.org.uk/discover/in-your-garden/article/31, planting for bats https://www.rhs.org.uk/science/conservation-biodiversity/wildlife/plants-for-pollinators https://www.bats.org.uk/our-work/buildings-planning-and-development/bat-boxes https://www.hampshireswifts.co.uk/nesting https://www.rspb.org.uk/birds-and-wildlife/advice/how-you-can-help-birds/nestboxes/nestboxes-for-small-birds/ https://www.swift-conservation.org/OurLeaflets.htm
Note to Applicant: In accordance with paragraph 38 of the National Planning Policy Framework (December 2023), Eastleigh Borough Council takes a positive approach to the handling of development proposals so as to achieve, whenever possible, a positive outcome and to ensure all proposals are dealt with in a timely manner.
Related records
No related records were published in this section.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.