(1) The development hereby permitted shall start no later than three years from the date of this decision. Reason: To comply with Section 91 of the Town and Country Planning Act 1990.
(1) Start - 3 years
(2) The development hereby permitted shall be implemented in accordance with the following plans numbered: 1532/E/01, 1532/E/02, 1532/P/20 B. Reason: For the avoidance of doubt and in the interests of proper planning.
(2) Development in accordance with approved plans
(3) The materials to be used in the construction of the external surfaces of the development hereby permitted shall match in type, colour and texture those used on the existing building. Reason: To ensure a satisfactory visual relationship between the new development and the existing.
(3) Materials to match existing
(4) No development shall start until an Arboricultural Impact Assessment, Tree Survey (to BS5837:2012), and details of Root Protection Areas, Tree Protection Plan and Arboricultural Method Statement for works near trees, has been submitted to and approved in writing by the Local Planning Authority. Reason - To retain and protect the existing trees which form an important part of the amenity of the locality.
(4) Arboricultural Impact Assessment, Method Statement, Tree Survey and protective fencing plan - pr
(5) No additional window shall be constructed in the east elevation of the first floor of the development hereby approved. Reason: To protect the amenity and privacy of the adjoining residential properties.
(5) No addition/altered windows
(6) The development shall accord with the submitted flood risk assessment where the floor levels will be set 300mm above the existing floor levels. Reason: To ensure that the flood risk is minimised
(6) Flood risk assessment - pre start
(7) No construction, demolition or deliveries to the site shall take place during the construction period except between the hours of 0800 to 1800 Mondays to Fridays or 0900 to 1300 on Saturdays and not at all on Sundays or Bank Holidays. Reason: To protect the amenities of the occupiers of nearby dwellings.
(7) Construction hours
Note to Applicant: In accordance with paragraphs 186 and 187 of the National Planning Policy Framework, Eastleigh Borough Council takes a positive approach to the handling of development proposals so as to achieve, whenever possible, a positive outcome and to ensure all proposals are dealt with in a timely manner.
Related records
No related records were published in this section.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.