(1) The development hereby permitted must be begun within a period of three years beginning with the date on which this permission is granted. Reason: To comply with Section 91 of the Town and Country Planning Act 1990.
(1) Commencement 3 years
(2) The development hereby permitted shall be carried out in accordance with the following approved plans: 5261-501-D1, 5261-502-D1, 5261-503-D1, 5261-504-D1, 5261-505-D6, 5261-506-D8, 5261-507-D4, 5261-508-D8. Reason: For the avoidance of doubt and in the interests of proper planning.
(3) The materials to be used must match as closely as possible, in type, colour, and texture, those on the existing buildings. Reason: To ensure a satisfactory visual relationship of the new development to the existing.
(3) Materials to match adjoining building
(4) No burning of materials obtained by site clearance or from any other source to take place on this site during the construction and fitting out process. Reason: In the interests of amenity.
(4) No burning from any source
Note to Applicant: It is considered that, subject to compliance with the conditions and any obligations attached to this permission, the proposed development is acceptable because it will not materially harm the character of the area, the amenity of neighbours or highway safety and it is in accordance with the policies and proposals of the development plan, as listed below, and after due regard to all other relevant material considerations the local planning authority is of the opinion that permission should be granted. The following development plan policies are relevant to this decision and the conditions attached to it: Eastleigh Borough Local Plan Review 2001-2011, Saved Policies - 59.BE 117.E. Pre submission Eastleigh Borough Local Plan 2011-2029, Policies - S1 S2 DM1 DM11 DM12 DM23 DM 24 In accordance with paragraphs 186 and 187 of the National Planning Policy Framework, Eastleigh Borough Council take a positive and proactive approach to the handling of development proposals so as to achieve, whenever possible, a positive outcome and to ensure all proposals are dealt with in a timely manner.
Note to applicant: development acceptable subject to conditions
Note to Applicant: Given the nature of the proposed development it is possible that a crane may be required during its construction. BAA would, therefore, draw the applicant’s attention to the requirement within the British Standard Code of Practice for the safe use of Cranes, for crane operators to consult the aerodrome before erecting a crane in close proximity to an aerodrome. This is explained further in Advice Note 4, ‘Cranes and Other Construction Issues’ [available at http://www.aoa.org.uk/policy-safeguarding.htm].
Related records
No related records were published in this section.
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.