Council planning record

Certificate of Lawfulness for the confirmation of commencement of works including the creation of the access point, construction of gravel access tracks, site compound and building foundation for one of the electrical buildings and erection of security fencing prior to 6 January 2025 of planning permission 23/00846/STVAR (Variation of Condition 3 (approved plans) of planning permission 21/02335/STPLF - Construction of a 49.9MW Solar Farm, underground cabling, 18 inverter substations, installation of perimeter fencing (up to 2.5m high) with access gates and 176 CCTV cameras/infra-red lighting on steel poles (up to 3.5m high steel poles) and 2 temporary construction compounds; construction of a grid compound consisting of substations, control rooms, transformers, cabling and fencing; construction of a storage compound consisting of 24 battery storage containers, 24 PCS units and 2.5m high perimeter fencing and associated grid infrastructure and associated works to allow for minor design changes to battery layout to reflect a more efficient and optimised design for construction)

Land South Of Creyke Beck Substation 4875 Park Lane Cottingham East Riding Of Yorkshire HU16 5SB

Application ApprovedReference: 25/00111/CLEEast Riding of Yorkshire Council

Last published check: 30 Sept 2026, 08:15. Check the council record for more recent changes.

Application location

Land South Of Creyke Beck Substation 4875 Park Lane Cottingham East Riding Of Yorkshire HU16 5SB

This record has no verified map location.

View council map

Application summary

Status
Application Approved
Application type
Cert of Lawful Development - Existing
Received
16 Jan 2025
Validated
16 Jan 2025
Determination deadline
Not published
Local authority
East Riding of Yorkshire Council

Application overview

Certificate of Lawfulness for the confirmation of commencement of works including the creation of the access point, construction of gravel access tracks, site compound and building foundation for one of the electrical buildings and erection of security fencing prior to 6 January 2025 of planning permission 23/00846/STVAR (Variation of Condition 3 (approved plans) of planning permission 21/02335/STPLF - Construction of a 49.9MW Solar Farm, underground cabling, 18 inverter substations, installation of perimeter fencing (up to 2.5m high) with access gates and 176 CCTV cameras/infra-red lighting on steel poles (up to 3.5m high steel poles) and 2 temporary construction compounds; construction of a grid compound consisting of substations, control rooms, transformers, cabling and fencing; construction of a storage compound consisting of 24 battery storage containers, 24 PCS units and 2.5m high perimeter fencing and associated grid infrastructure and associated works to allow for minor design changes to battery layout to reflect a more efficient and optimised design for construction)

Proposal details

Reference
25/00111/CLE
Alternative references
PP-13687200
Ward
Dale
Parish
Skidby Parish Council

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 12 of 12

DocumentPublishedAction
OFFICERS REPORTOfficer Report13 Mar 2025View
DECISIONeDecision · PDF13 Mar 2025View
MR ANDREW CRABBEConsultee Comment · PDF24 Feb 2025View
. COTTINGHAM PARISH COUNCILConsultee Comment · PDF18 Feb 2025View
. ROWLEY PARISH COUNCILConsultee Comment · PDF15 Feb 2025View
. WALKINGTON PARISH COUNCILConsultee Comment · PDF12 Feb 2025View
. SKIDBY PARISH COUNCILConsultee Comment · PDF4 Feb 2025View
APPLICATION FORMApplication Form · PDF16 Jan 2025View
LOCATION PLANPlans · PDF16 Jan 2025View
SUPPORTING STATEMENT - PART 2Supporting Documents · PDF16 Jan 2025View
SUPPORTING STATEMENT - PART 3Supporting Documents · PDF16 Jan 2025View
SUPPORTING STATEMENT - PART 1Supporting Documents · PDF16 Jan 2025View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Latest Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  4. Latest Site Notice Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Decision Issued Date

    Published milestoneCouncil source

Decision & conditions

Approve

Appeal status: No information · No information

DECISION
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.