Up to 19 no. wind turbines with a generating capacity in excess of 50MW, maximum overall ground to blade tip heights of up to 156.5 metres; 1 no. permanent Meteorological Mast up to a maximum height of 110 metres; 1 no. 110kV electrical substation with 2 no. control buildings with welfare facilities, associated electrical plant and equipment, security fencing and waste water holding tank; internal wind farm underground cabling; 110kV underground grid connection cabling; upgrade of access junctions; upgrade of existing tracks, roads and provision of new site access roads and hardstand areas; 3 no. borrow pits; 2 no. temporary construction compounds; recreation and amenity works, including marked trails, picnic amenity and play areas, car parking and vehicular access; site drainage; forestry felling; permanent signage; all associated site development and ancillary works

Townlands of Meenbog (ED Goland) Croaghhonagh and Cashelnavean Co Donegal.

Consultation OpenReference: LA11/2017/1134/TBADepartment for Infrastructure

Last published check: 9 Oct 2026, 00:22. Check the council record for more recent changes.

Application location

Townlands of Meenbog (ED Goland) Croaghhonagh and Cashelnavean Co Donegal.

This record has no verified map location.

Application summary

Status
Consultation Open
Application type
Transboundary Application
Received
18 Dec 2017
Validated
18 Dec 2017
Determination deadline
Not published
Local authority
Department for Infrastructure

Application overview

Up to 19 no. wind turbines with a generating capacity in excess of 50MW, maximum overall ground to blade tip heights of up to 156.5 metres; 1 no. permanent Meteorological Mast up to a maximum height of 110 metres; 1 no. 110kV electrical substation with 2 no. control buildings with welfare facilities, associated electrical plant and equipment, security fencing and waste water holding tank; internal wind farm underground cabling; 110kV underground grid connection cabling; upgrade of access junctions; upgrade of existing tracks, roads and provision of new site access roads and hardstand areas; 3 no. borrow pits; 2 no. temporary construction compounds; recreation and amenity works, including marked trails, picnic amenity and play areas, car parking and vehicular access; site drainage; forestry felling; permanent signage; all associated site development and ancillary works

Proposal details

Reference
LA11/2017/1134/TBA
Alternative references
PAO721471
Ward
Glenderg

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 162 of 162

DocumentPublishedAction
PAO721471_Original Application Form_001Application Form26 Nov 2022View
PAO721471_NI Water - Strategic Applications_Consultation Response_211201820274.pdfConsultation Responses26 Nov 2022View
PAO721471_IN-Roads Service Londonderry_Consultation Response_2812018203245.DOCXConsultation Responses26 Nov 2022View
PAO721471_Foyle Carlingford Irish Lights Commiss_Consultation Response_122201894112.docxConsultation Responses26 Nov 2022View
PAO721471_Environmental Health Derry City and Stra_Consultation Response_1712018161213.docxConsultation Responses26 Nov 2022View
PAO721471_Chief Exec Derry City and Strabane_Consultation Response_52201815199.pdfConsultation Responses26 Nov 2022View
PAO721471_Chief Exec Derry City and Strabane_Consultation Response_192201816711.docConsultation Responses26 Nov 2022View
PAO721471_AB-DARDNI (Dundonald House)_Consultation Response_1322018155613.DOCConsultation Responses26 Nov 2022View
PAO721471_NIEA_Consultation Response_522018154258.pdfConsultation Responses26 Nov 2022View
PAO721471_Historic Environment Division (HED)_Consultation Response_231201811510.PDFConsultation Responses26 Nov 2022View
PAO721471_RA-Rivers Agency Headquarters_Consultation Response_221201810938.pdfConsultation Responses26 Nov 2022View
PAO721471_BW-Royal Society for the Protection of B_Consultation Response_522018143137.pdfConsultation Responses26 Nov 2022View
An Bord Pleanála Decision Letter - 29.6.2018Planning decisions and reports26 Nov 2022View
Appendix 7.3 - Summary Results TablesImpact Assessments and Statements26 Nov 2022View
Appendix 11.1 - Glossary of Acoustic TermsImpact Assessments and Statements26 Nov 2022View
Appendix 6.3 - Fisheries AssessmentImpact Assessments and Statements26 Nov 2022View
Appendix 8.2 - Gouge Core LogsImpact Assessments and Statements26 Nov 2022View
Appendix 8.1 - Peat Stability Assessment ReportImpact Assessments and Statements26 Nov 2022View
Appendix 14.1 - Traffic and Transport FiguresImpact Assessments and Statements26 Nov 2022View
Appendix 4.3 - Forestry Replanting Assessment B_Part1Impact Assessments and Statements26 Nov 2022View
Appendix 5.3 - House Prices Study - CXC Scotland 2016Impact Assessments and Statements26 Nov 2022View
Appendix 7.8 - Post-Construction Monitoring ProgrammeImpact Assessments and Statements26 Nov 2022View
Appendix 4.3 - Forestry Replanting Assessment B_Part2Impact Assessments and Statements26 Nov 2022View
Appendix 13.1 - Site Description and Photographic RecordImpact Assessments and Statements26 Nov 2022View
Appendix 3.1 - Letter from Ionic ConsultingImpact Assessments and Statements26 Nov 2022View
Appendix 12.1 - Figures 12.1 to 12.23_Part1Impact Assessments and Statements26 Nov 2022View
Appendix 4.1 - Site Layout Drawings_Part3Impact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part4Impact Assessments and Statements26 Nov 2022View
Appendix 11.3 - Calcualtion Parameters an SettingsImpact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part1Impact Assessments and Statements26 Nov 2022View
Appendix 7.6 - Collision RiskImpact Assessments and Statements26 Nov 2022View
Appendix 6.2 - Aquatic Macroinvertebrate SamplingImpact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part7Impact Assessments and Statements26 Nov 2022View
Appendix 2.2 - NI Scoping ResponsesImpact Assessments and Statements26 Nov 2022View
Appendix 12.3 - Landscape Character SensitivityImpact Assessments and Statements26 Nov 2022View
160502 - Volume 2 - Photomontage Layouts_Part3Impact Assessments and Statements26 Nov 2022View
Appendix 9.2 - Culvert AssessmentImpact Assessments and Statements26 Nov 2022View
Appendix 4.3 - Forestry Replanting Assessment B_Part3Impact Assessments and Statements26 Nov 2022View
Appendix 12.2 - LVIA MethodologyImpact Assessments and Statements26 Nov 2022View
160502 - Natura Impact Assessment - 2017.12.11_Part2Impact Assessments and Statements26 Nov 2022View
Appendix 4.2 - Peat and Spoil Management PlanImpact Assessments and Statements26 Nov 2022View
Appendix 6.4 - Turbine Base Botanical SurveyImpact Assessments and Statements26 Nov 2022View
Appendix 7.5 - Staff CVsImpact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part6Impact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part5Impact Assessments and Statements26 Nov 2022View
Appendix 9.1 - Lab CertificateImpact Assessments and Statements26 Nov 2022View
160502 - Volume 2 - Photomontage Layouts_Part1Impact Assessments and Statements26 Nov 2022View
Appendix 6.5 - FWPM SurveyImpact Assessments and Statements26 Nov 2022View
Appendix 10.1 - Carbon Loss CalculationImpact Assessments and Statements26 Nov 2022View
Appendix 14.2 - Traffic and Transport - Grid Connection AssessmentImpact Assessments and Statements26 Nov 2022View
Appendix 4.1a - Grid Connection Layout DrawingsImpact Assessments and Statements26 Nov 2022View
Appendix 12.4 - Viewpoint AssessmentImpact Assessments and Statements26 Nov 2022View
Appendix 4.1 - Site Layout Drawings_Part2Impact Assessments and Statements26 Nov 2022View
Appendix 7.1 - Species ListsImpact Assessments and Statements26 Nov 2022View
Appendix 7.7 - Hen Harrier Habitat Enhancement PlanImpact Assessments and Statements26 Nov 2022View
160502 - Volume 2 - Photomontage Layouts_Part2Impact Assessments and Statements26 Nov 2022View
Appendix 11.2 - Calibration CertificateImpact Assessments and Statements26 Nov 2022View
Appendix 5.1 - Wind Farms and Health Literature Review - Chapman 2015Impact Assessments and Statements26 Nov 2022View
Appendix 2.1 - ROI Scoping ResponsesImpact Assessments and Statements26 Nov 2022View
Appendix 4.4 - Construction and Environmental Management PlanImpact Assessments and Statements26 Nov 2022View
Appendix 4.1 - Site Layout Drawings_Part1Impact Assessments and Statements26 Nov 2022View
Appendix 7.4 - Bird Survey DataImpact Assessments and Statements26 Nov 2022View
Appendix 7.2 - Bird Survey EffortImpact Assessments and Statements26 Nov 2022View
Appendix 5.2 - Eirgrid EMF and YouImpact Assessments and Statements26 Nov 2022View
Appendix 11.4 - Noise Contour at Rated Power WindspeedImpact Assessments and Statements26 Nov 2022View
Appendix 12.1 - Figures 12.1 to 12.23_Part2Impact Assessments and Statements26 Nov 2022View
160502 - Natura Impact Assessment - 2017.12.11_Part1Impact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part2Impact Assessments and Statements26 Nov 2022View
160502 - Volume 2 - Photomontage Layouts_Part5Impact Assessments and Statements26 Nov 2022View
Appendix 6.1 - Bat ReportImpact Assessments and Statements26 Nov 2022View
160502 - EIAR Volume 1 - NTS and EIAR_Part3Impact Assessments and Statements26 Nov 2022View
Appendix 13.2 - Description of Recorded Monuments and NIAH StructuresImpact Assessments and Statements26 Nov 2022View
160502 - Volume 2 - Photomontage Layouts_Part4Impact Assessments and Statements26 Nov 2022View
PAO721471_Site Layout or Block Plan_032Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_008Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_010Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_004Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_006Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_030Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_003Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_004Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Location Plan_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_015Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_024Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_007Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_009Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Sign Elevations_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_007Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_020Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_012Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_026Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_014Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_021Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_013Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_010Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Location Plan_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_014Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_017Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Sign Elevations_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_005Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_006Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_011Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_017Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_005Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_022Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_003Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_023Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_018Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_005Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_008Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_004Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_009Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_008Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_012Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_007Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_025Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_002Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_028Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_019Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_008Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_019Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_006Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_001Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_016Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_027Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_015Plans, Maps and Drawings26 Nov 2022View
PAO721471_Proposed Elevations_006Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_013Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_003Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_016Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_029Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_007Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_018Plans, Maps and Drawings26 Nov 2022View
PAO721471_Levels and Cross Sections_010Plans, Maps and Drawings26 Nov 2022View
PAO721471_Road Access Plan_004Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_031Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_011Plans, Maps and Drawings26 Nov 2022View
PAO721471_Site Layout or Block Plan_009Plans, Maps and Drawings26 Nov 2022View
PAO721471_Technical Specification_003Other Supporting Information26 Nov 2022View
PAO721471_Technical Specification_005Other Supporting Information26 Nov 2022View
PAO721471_Technical Specification_004Other Supporting Information26 Nov 2022View
PAO721471_Technical Specification_006Other Supporting Information26 Nov 2022View
Response from SPD to An Bord Pleanala - Dated 14-02-18Other Supporting Information26 Nov 2022View
PAO721471_Technical Specification_001Other Supporting Information26 Nov 2022View
PAO721471_Technical Specification_002Other Supporting Information26 Nov 2022View
Letter from An Bord Pleanála re determination of application via written procedure - 16.4.2018Miscellaneous26 Nov 2022View
EIA Consultation Letter - P28MSUSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSTSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSSSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSRSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSPSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSOSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSNSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSMSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSLSV2R000Consultation Requests26 Nov 2022View
EIA Consultation Letter - P28MSJSV2R000Consultation Requests26 Nov 2022View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Received date

    Published milestoneCouncil source
  2. Validated date

    Published milestoneCouncil source

Decision & conditions

Not Available
An Bord Pleanála Decision Letter - 29.6.2018
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.