Council planning record

Erection of a 2-bed bungalow

82, Hednesford Road, Heath Hayes, Staffordshire, Cannock, WS12 3EA

Decision made 07 May 2026 Full - Approval with Conditions. Delegated.Reference: CH/25/0342Cannock Chase District Council

Last published check: 2 Oct 2026, 02:57. Check the council record for more recent changes.

Application location

82, Hednesford Road, Heath Hayes, Staffordshire, Cannock, WS12 3EA

This record has no verified map location.

Application summary

Status
Decision made 07 May 2026 Full - Approval with Conditions. Delegated.
Application type
Full Planning Application
Received
26 Nov 2025
Validated
23 Dec 2025
Determination deadline
12 Feb 2026
Local authority
Cannock Chase District Council

Application overview

Erection of a 2-bed bungalow

Proposal details

Reference
CH/25/0342
Alternative references
PP-14195683
Ward
Heath Hayes & Wimblebury
Parish
Heath Hayes and Wimblebury CP
Agent
Paul Simkin
UPRN
MAN000000000123470

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents 19 of 19

DocumentPublishedAction
Approved 7.5.26 - Proposed Plans and ElevationsPAPPDWG28 Nov 2025View
BNG MetricPSUPPSTA2 Dec 2025View
BNG Assessment RedactedPSUPPSTA2 Dec 2025View
Design and Access StatementPDNAS23 Dec 2025View
Policy commentsPCONSULT29 Dec 2025View
Environmental Health commentsPCONSULT5 Jan 2026View
Landscape CommentsPCONSULT12 Jan 2026View
Heath Hayes & Wimblebury PC commentsPCONSULT14 Jan 2026View
Ecology Officer commentsPCONSULT15 Jan 2026View
SCC Highways commentsPCONSULT16 Jan 2026View
Coal Mining Risk AssessmentPADDINFO26 Mar 2026View
Approved 7.5.26 - Amended - Site Location and Block PlanPAPPDWG31 Mar 2026View
Proposed Site PlanPPLAN31 Mar 2026View
The Coal Authority commentsPCONSULT2 Apr 2026View
Landscape further commentsPCONSULT29 Apr 2026View
Highways further commentsPCONSULT1 May 2026View
Amended Application formPAPPFRM7 May 2026View
Officer ReportPOFFREP7 May 2026View
Decision NoticePDECNOT7 May 2026View

Documents open on the council website. Browse council documents if a link has changed.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application date

    Published milestoneCouncil source
  2. Received date

    Published milestoneCouncil source
  3. Registration date

    Published milestoneCouncil source
  4. Press notice start date

    Published milestoneCouncil source
  5. Valid date

    Published milestoneCouncil source
  6. Decision due date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Publicity end date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  8. Dispatch date

    Published milestoneCouncil source
  9. Decision date

    Published milestoneCouncil source
  10. Extension date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source

Decision & conditions

Full - Approval with Conditions
Decision Notice
Planning conditions
  1. In accordance with Paragraph 38 of the National Planning Policy Framework the Local Planning Authority has worked with the applicant in a positive and proactive manner to approve the proposed development, which accords with the Local Plan and the National Planning Policy Framework.
  2. No development shall commence until; a) a scheme of intrusive investigations has been carried out on site to establish the risks posed to the development by past coal mining activity, and; b) any remediation works and/or mitigation measures to address land instability arising from coal mining legacy, as may be necessary, have been implemented on site in full in order to ensure that the site is safe and stable for the development proposed. The intrusive site investigations and remedial works shall be carried out in accordance with authoritative UK guidance. Reason In the interests of public safety and in accordance with the NPPF.
  3. Prior to the occupation of the development, or it being taken into beneficial use, a signed statement or declaration prepared by a suitably competent person confirming that the site is, or has been made, safe and stable for the approved development shall be submitted to the Local Planning Authority for approval in writing. This document shall confirm the methods and findings of the intrusive site investigations and the completion of any remedial works and/or mitigation necessary to address the risks posed by past coal mining activity. Reason In the interests of public safety and in accordance with the NPPF.
  4. The development hereby permitted shall be carried out in accordance with the following approved plans: Location & Block Plans 000 Rev B Proposed Plans and Elevations 001 Reason For the avoidance of doubt and in the interests of proper planning.
  5. The development to which this permission relates must be begun not later than the expiration of three years beginning with the date on which this permission is granted. Reason To comply with the requirements of Section 91 of the Town & Country Planning Act 1990.
  6. The approved landscape works shown on the submitted Block Plan shall be carried out in the first planting and seeding season following the occupation of any buildings or the completion of the development whichever is the sooner. Reason In the interest of visual amenity of the area. In accordance with Local Plan Policies SO1.2, SO7.1, SO7.4, SO8.3 and the NPPF.
  7. No materials shall be used for the external surfaces of the development other than those specified on the application. Reason In the interests of visual amenity and to ensure compliance with Local Plan Policies SO1.1, SO1.2, SO2.2 & SO8.3 (where applicable) and the NPPF.
  8. Any trees or plants which within a period of five years from the date of planting die, are removed or become seriously damaged or diseased, shall be replaced in the following planting season with others of similar size and species unless the Local Planning Authority gives written consent to any variation. Reason In the interests of visual amenity of the area. In accordance with Local Plan Policies SO1.2, SO2.2, SO7.4 & SO7.5 (where applicable) and the NPPF.
  9. No plant or machinery shall be operated, no loading or unloading of vehicles and no movement of commercial vehicles to or from the site shall take place outside the hours of 08:00 to 18:00 Monday to Friday and 08:00 to 13:00 Saturday. None of the above operations shall be carried out at any time on Sundays or Bank and Public Holidays. Reason To ensure that the proposed development does not prejudice the enjoyment by neighbouring occupiers of their properties and to ensure compliance with the Local Plan Policy SO2.2, and the NPPF.
  10. Coal Authority (i) The proposed development lies within an area that has been defined by the Mining Remediation Authority as containing coal mining features at surface or shallow depth. These features may include: mine entries (shafts and adits); shallow coal workings; geological features (fissures and break lines); mine gas and former surface mining sites. Although such features are seldom readily visible, they can often be present and problems can occur, particularly as a result of new development taking place. Any intrusive activities which disturb or enter any coal seams, coal mine workings or coal mine entries (shafts and adits) requires a Mining Remediation Authority Permit. Such activities could include site investigation boreholes, excavations for foundations, piling activities, other ground works and any subsequent treatment of coal mine workings and coal mine entries for ground stability purposes. Application forms for Mining Remediation Authority permission and further guidance can be obtained from The Mining Remediation Authority’s website at: www.gov.uk/get-apermit-to-deal-with-a-coal-mine-on-your-property What is a permit and how to get one? – https://www.gov.uk/government/publications/permit-process/permit-process If any coal mining features are unexpectedly encountered during development, this should be reported immediately to the Mining Remediation Authority on 0800 288 4242. Further information is available on the Mining Remediation Authority website at: https://www.gov.uk/government/organisations/mining-remediation-authority In areas where shallow coal seams are present caution should be taken when carrying out any on site burning or heat focused activities. To check your site for coal mining features on or near to the surface the Coal Authority interactive map viewer allows you to view selected coal mining information in your browser graphically. To check a particular location either enter a post code or use your mouse to zoom in to view the surrounding area.
  11. The effect of Paragraph 13 of Schedule 7A to the Town and Country Planning Act 1990 is that, subject to some exemptions, every grant of planning permission in England is deemed to have been granted subject to the biodiversity gain condition that development may not begin unless: (a) a Biodiversity Gain Plan has been submitted to the planning authority, and (b) the planning authority has approved the plan. Based on the information available this permission is considered to be one which WILL require the approval of a Biodiversity Gain Plan before development is begun because none of the statutory exemptions or transitional arrangements are considered to apply. This objective is for development to deliver at least a 10% increase in biodiversity value relative to the pre-development biodiversity value of the onsite habitat. This increase can be achieved through onsite biodiversity gains, registered offsite biodiversity gains or statutory biodiversity credits. The Planning Authority, for the purposes of determining whether to approve a Biodiversity Gain Plan in respect of this permission is Cannock Chase District Council. The Biodiversity Gain Plan should be submitted as an ‘application for approval of details reserved by condition following grant of planning permission’ via the Planning Portal. When submitting an application to discharge the biodiversity gain condition the LPA requests that the applicant uses the standard national templates for a Biodiversity Gain Plan and a Habitat Management and Monitoring Plan. Submit a biodiversity gain plan - GOV.UK (www.gov.uk) The biodiversity gain condition cannot be removed or varied.
Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.