RefusedCouncil status: Decision made 28 May 2026 Full- Refusal. Delegated.

Development of a battery energy storage system with associated infrastructure, access, drainage and landscaping.

Land to the rear of the Bungalow, Lime Lane, Pelsall, Walsall, WS3 5AL

Cannock Chase District CouncilReference CH/25/0225Full Planning Application

Last published check: 3 Oct 2026, 07:07. Check the council record for more recent changes.

Status and dates

Last published check: 3 Oct 2026, 07:07 (UK)

  1. DoneReceived17 Jul 2025
  2. DoneValidated24 Jul 2025
  3. ClosedConsultationEnded 2 Sept 2025
  4. Date set by councilAgreed decision date29 May 2026
  5. DecidedFull- Refusal28 May 2026

Dates come from the council record. A target date passing does not confirm a decision.

All published dates (13)
  1. Committee date

    Published milestoneCouncil source
  2. Application date

    Published milestoneCouncil source
  3. Received date

    Published milestoneCouncil source
  4. Registration date

    Published milestoneCouncil source
  5. Valid date

    Published milestoneCouncil source
  6. Press notice start date

    Published milestoneCouncil source
  7. Site notice date

    Published milestoneCouncil source
  8. Site notice end date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Publicity end date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  10. Decision due date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  11. Dispatch date

    Published milestoneCouncil source
  12. Decision date

    Published milestoneCouncil source
  13. Extension date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
Application type
Full Planning Application
Ward
Norton Canes
Parish
Norton Canes CP
Documents
51 published

Proposal

Development of a battery energy storage system with associated infrastructure, access, drainage and landscaping.

Reference
CH/25/0225
Alternative references
PP-14030379
Ward
Norton Canes
Parish
Norton Canes CP
Agent
Matthew Taylor
UPRN
MAN000000000122715

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Documents

  • Refused 29.5.26 - Environmental Statement - ArboriculturePREFDWGNot publishedView
  • Refused 29.5.26 - Environmental Statement - TransportPREFDWGNot publishedView
  • Refused 29.5.26 - BNG ReportPREFDWGNot publishedView
  • Refused 29.5.26 - Technical Chapter 9 - Appendicies Part 3PREFDWGNot publishedView
  • Refused 29.5.26 - Technical Chapter 9 - Appendicies Part 2PREFDWGNot publishedView
  • Refused 29.5.26 - Appendix 9.1 - Phase 1 Geo-Environmental Desk StudyPREFDWGNot publishedView
  • Refused 29.5.26 - Environmental Statement - Ground ConditionsPREFDWGNot publishedView
  • Refused 29.5.26 - Appendix 10.1 P2 - Flood Risk AssessmentPREFDWGNot publishedView

Documents open on the council website. Browse council documents if a link has changed.

Decision and conditions

Full- Refusal
Decision Notice
Planning conditions
  1. The application has failed to provide sufficient information to enable full assessment of flood risk and drainage impacts arising from the proposal. The absence of an adequate Flood Risk Assessment and supporting drainage details means the Local Planning Authority cannot be satisfied that the development would not increase flood risk across the site and within the wider area. Accordingly, the proposal is in conflict with Policy SO2.2 of the Cannock Chase District Local Plan (2018-2040) and paragraph 181 of the National Planning Policy Framework (2024).
  2. The application fails to provide sufficient information to adequately assess the ecological impact of the proposal upon the biodiversity of the site. The applicant has failed to provide details relating to potential alternative sites, the potential presence of protected species on site, Biodiversity baseline conditions and the delivery of biodiversity Net Gain. The submitted Environmental Impact Assessment does not adequately assess potential impacts or demonstrate that harm can be avoided or mitigated. As such, it has not been demonstrated that the scheme accords with policy SO7.1 of the Cannock Chase District Local Plan (2018-2040) and paragraph 187 of the National Planning Policy Framework (2024).
  3. The application has failed to provide an adequate assessment of noise arising from the proposed development. The nature and scale of the proposal, which has the potential to generate noise through ongoing operational noise may create a potential adverse impact on the amenity of nearby residents. As such, it has not been demonstrated that the scheme would safeguard residential amenity and conflicts with Policy SO2.2 of the Cannock Chase District Local Plan (2018-2040) and the National Planning Policy Framework (2024).
  4. The application fails to provide sufficient information to adequately assess the full impact of the proposal on the highway. In particular, it has not been demonstrated that the junction of School Lane with the A5 Trunk Road, which does not meet current standards, would be suitable and would not have an adverse impact upon highway safety, thereby potentially increasing the risk of traffic collisions in this location. Therefore, the proposal is contrary to paragraph 116 of the National Planning Policy Framework (2024).
  5. Reason for Refusal of Planning Permission In accordance with paragraph (38) of the National Planning Policy Framework the Local Planning Authority has worked with the applicant in a positive and proactive manner to approve the proposed development. However, in this instance the proposal fails to accord with the Local Plan and the National Planning Policy Framework.
Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.