Council planning record

Importation by rail of suitable restoration material over a period of 5yrs to partially infill an existing quarry void to provide for the restoration of the western and north-western areas of Barrington Quarry to a combination of agriculture and nature conservation after-uses and all associated works including railway refurbishment and the retention and continued use of existing weighbridge, office and workshop, Informative: Section 73 planning application to develop land without complying with condition 2 of planning permission S/0107/18/CW to allow restoration of land bordering North Pit to continue for a further 12 months until 31 December 2020

Barrington Cement Plant, Haslingfield Road, Barrington, Cambridge, Cambridgeshire, CB22 7RQ

ApproveReference: FMW/079/19Cambridgeshire County Council

Last published check: 21 Sept 2026, 06:56. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Valid Date

    Published milestoneCouncil source
  3. Consultation Start Date

    Published milestoneCouncil source
  4. Decision Date

    Published milestoneCouncil source
  5. Proposal

    Published milestoneCouncil source

Application summary

Status
Approve
Application type
Variation of condition
Received
18 Nov 2019
Validated
18 Nov 2019
Determination deadline
Not published
Local authority
Cambridgeshire County Council

Application overview

Importation by rail of suitable restoration material over a period of 5yrs to partially infill an existing quarry void to provide for the restoration of the western and north-western areas of Barrington Quarry to a combination of agriculture and nature conservation after-uses and all associated works including railway refurbishment and the retention and continued use of existing weighbridge, office and workshop, Informative: Section 73 planning application to develop land without complying with condition 2 of planning permission S/0107/18/CW to allow restoration of land bordering North Pit to continue for a further 12 months until 31 December 2020

Proposal details

Reference
FMW/079/19
Parish
Barrington
Agent
Mr Shaun Denny, CEMEX UK Operations Ltd.

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Barrington Cement Plant, Haslingfield Road, Barrington, Cambridge, Cambridgeshire, CB22 7RQ

This record has no verified map location.

Documents 17 of 17

DocumentPublishedAction
DECISION NOTICEDecision5 Mar 2020View
DELEGATED REPORTDecision20 Feb 2020View
LOCATION PLANApplication submission18 Nov 2019View
COVER LETTERApplication submission18 Nov 2019View
SECTIONS C-C & D-DApplication submission18 Nov 2019View
APPLICATION FORMApplication submission18 Nov 2019View
SECTIONS A-A & B-BApplication submission18 Nov 2019View
APPLICATION PLANApplication submission18 Nov 2019View
PROPOSED RESTORATION SCHEME-CROSS SECTIONSApplication submission18 Nov 2019View
PROPOSED RESTORATION SCHEMEApplication submission18 Nov 2019View
TO SCDC - SCREENING OPINIONEnvironmental Impact Assessment3 Jan 2020View
SCREENING OPINIONEnvironmental Impact Assessment2 Jan 2020View
FROM SOUTH CAMBS DISTRICT COUNCIL (NB: THEY HAVE USED THEIR REF. NO. NOT CCC'S)Consultee comment13 Feb 2020View
FROM FOXTON PARISH COUNCILConsultee comment20 Jan 2020View
FROM NATURAL ENGLAND (ATTACHMENT 14/12/2028)Consultee comment10 Jan 2020View
FROM NATURAL ENGLANDConsultee comment10 Jan 2020View
EA COMMENTSConsultee comment2 Jan 2020View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Approve
DECISION NOTICE
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.