Council planning record

A142 Ely Southern Bypass, linking Angel Drove with Stuntney Causeway: construction of 1.7km long single carriageway road between 2 new roundabouts, including crossings of the Cambridge to Ely railway line and River Gt Ouse. Associated works to include earthworks, planting, drainage, minor road structures, lighting, signage, pedestrian & cycle provision and temporary construction compounds and are inclusive of works to the bypassed A142.

Land To The South Of Ely Between Angel Drove & Stuntney Causeway

ApproveReference: E/03005/13/CCCambridgeshire County Council

Last published check: 22 Sept 2026, 09:14. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Valid Date

    Published milestoneCouncil source
  2. Decision Date

    Published milestoneCouncil source
  3. Application Received Date

    Published milestoneCouncil source

Application summary

Status
Approve
Application type
Full application
Received
24 Sept 2016
Validated
23 Sept 2013
Determination deadline
Not published
Local authority
Cambridgeshire County Council

Application overview

A142 Ely Southern Bypass, linking Angel Drove with Stuntney Causeway: construction of 1.7km long single carriageway road between 2 new roundabouts, including crossings of the Cambridge to Ely railway line and River Gt Ouse. Associated works to include earthworks, planting, drainage, minor road structures, lighting, signage, pedestrian & cycle provision and temporary construction compounds and are inclusive of works to the bypassed A142.

Proposal details

Reference
E/03005/13/CC
Parish
Ely
Agent
Mr Frost CC1211

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Land To The South Of Ely Between Angel Drove & Stuntney Causeway

This record has no verified map location.

Documents 235 of 235

DocumentPublishedAction
Decision noticeDecision13 Oct 2014View
Environmental MasterplanApplication submission29 Aug 2014View
Cross Sections - Scheme Landscape Proposals - Sheet 2 of 2Application submission29 Aug 2014View
Cross Sections - Scheme Landscape Proposals Sheet 1 of 2Application submission29 Aug 2014View
Sustainability Appraisal - FINALApplication submission19 Aug 2014View
Statement of Community & Stakeholder InvolvementApplication submission19 Aug 2014View
Application FormApplication submission19 Aug 2014View
Transport Assessment - FINALApplication submission19 Aug 2014View
Preliminary Underpass Traffic CalmingApplication submission19 Aug 2014View
Design & Access Statement (Final)Application submission19 Aug 2014View
LA dev letterApplication submission19 Aug 2014View
Flood Risk Assessment FINALApplication submission19 Aug 2014View
Planning Statement - FINALApplication submission19 Aug 2014View
ES Vol 2 - FinalApplication submission19 Aug 2014View
ES Vol 1 NTS - FinalApplication submission19 Aug 2014View
Applicant covering letterApplication submission19 Aug 2014View
from Ely Crossing ActionApplication submission5 Aug 2014View
Planning Statement Addendum July 2014Application submission7 Jul 2014View
Applicant letter 4 July 2014Application submission7 Jul 2014View
Environmental Statement Addendum July 2014Application submission7 Jul 2014View
Visual impact assessmentApplication submission8 May 2014View
Planning StatementApplication submission28 Feb 2014View
ECDC Planning Committee ReportApplication submission27 Feb 2014View
from English Heritage - Review of Addendum 2Application submission27 Feb 2014View
Addendum 1 Landscaping summaryApplication submission23 Jan 2014View
Addendum 3 Winter bird survey planApplication submission23 Jan 2014View
Addendum 2 Transport assessment and Highway designApplication submission23 Jan 2014View
Addendum 4 Preliminary sources study reportApplication submission23 Jan 2014View
Addendum 4 Enviro check reportApplication submission23 Jan 2014View
Addendum 4 Groundwater protection summaryApplication submission23 Jan 2014View
Addendum 4 Ground investigation reportApplication submission23 Jan 2014View
Addendum 1 Zone of visual influence fig 10 - 9 revBApplication submission23 Jan 2014View
Addendum 1 Tree protectionApplication submission23 Jan 2014View
Addendum 3 Ecology summaryApplication submission23 Jan 2014View
Addendum 3 Great crested newts surveyApplication submission23 Jan 2014View
Addendum 3 Breeding bird survey planApplication submission23 Jan 2014View
Addendum 3 Bat surveyApplication submission23 Jan 2014View
Protected species resultsApplication submission21 Nov 2013View
Photomontage viewpoint 4 existing view and summer view 2030 sheet 8Application submission21 Nov 2013View
Photomontage viewpoint 1 existing view and summer view 2030 sheet 2Application submission21 Nov 2013View
Photomontage methodologyApplication submission21 Nov 2013View
Option assessment reportApplication submission21 Nov 2013View
NVC frequency tablesApplication submission21 Nov 2013View
Land contamination Construction and operation impact assessment tablesApplication submission21 Nov 2013View
Land contamination construction and operation CSM tablesApplication submission21 Nov 2013View
Front sheet option assessment report addendum 3.2Application submission21 Nov 2013View
Fig 4.1 Lighting Contours- Angel Drove RAApplication submission21 Nov 2013View
Fig 11.4 Bat Activity SurveysApplication submission21 Nov 2013View
Fig 10.21 Photographs 1-4Application submission21 Nov 2013View
Fig 10.15 Panoramic Viewpoints P1-2Application submission21 Nov 2013View
Fig 10.13 Year 2030 Summer Visual Impact ResidentialApplication submission21 Nov 2013View
Environmental masterplanApplication submission21 Nov 2013View
Elements of the setting of Ely and CathedralApplication submission21 Nov 2013View
Tree protection plan sheet 1Application submission21 Nov 2013View
Photomontage viewpoint 5 existing view and winter view 2015 sheet 9Application submission21 Nov 2013View
Photomontage viewpoint 4 existing view and winter view 2015 aheet 7Application submission21 Nov 2013View
Noise difference do minimum opening year vs with scheme design yearApplication submission21 Nov 2013View
Landscape, townscape and visual assessment schedulesApplication submission21 Nov 2013View
Fig 13.1 Exploratory Hole Location PlanApplication submission21 Nov 2013View
Fig 10.19 Panoramic Viewpoints P9Application submission21 Nov 2013View
Fig 10.17 Panoramic Viewpoints P5-6Application submission21 Nov 2013View
Designated assets showing the location of the schemeApplication submission21 Nov 2013View
Cross sections - scheme landscape proposals sheet 1Application submission21 Nov 2013View
Archaeological desk-based assessment App 9.2Application submission21 Nov 2013View
Fig 7.3 2011 Background No2 Concentrations at modlled gridApplication submission21 Nov 2013View
Fig 7.2 Location of Discrete Receptors Included In ModelApplication submission21 Nov 2013View
Fig 11.2 Phase 1 Habitat MapApplication submission21 Nov 2013View
Fig 11.1 Protected Species & Designated SitesApplication submission21 Nov 2013View
Fig 10.5 Landscape ConstraintsApplication submission21 Nov 2013View
Fig 10.4 Townscape CharacterApplication submission21 Nov 2013View
Fig 10.16 Panoramic Viewpoints P3-4Application submission21 Nov 2013View
Existing ground contoursApplication submission21 Nov 2013View
Drawing showing representative receptor locationsApplication submission21 Nov 2013View
Architectural bridge drawingsApplication submission21 Nov 2013View
Air QualityApplication submission21 Nov 2013View
Tree protection plan sheet 7Application submission21 Nov 2013View
Tree protection plan sheet 6Application submission21 Nov 2013View
Photomontage viewpoint 3 existing view and summer view 2015 sheet 5Application submission21 Nov 2013View
Land contamination problems and consequencesApplication submission21 Nov 2013View
Heritage viewsApplication submission21 Nov 2013View
Fig 8.11 Noise difference do minimum 2015 vs do something 2015Application submission21 Nov 2013View
Fig 7.1 Air Quality Constraints MapApplication submission21 Nov 2013View
Fig 10.6 Environmental MasterplanApplication submission21 Nov 2013View
Fig 10.3 Local Landscape CharacterApplication submission21 Nov 2013View
Fig 10.23 Photographs 9-13Application submission21 Nov 2013View
Fig 10.20 Night time Panoramic Viewpoint P10Application submission21 Nov 2013View
Ely Setting studyApplication submission21 Nov 2013View
Drainage and fencingApplication submission21 Nov 2013View
Ely setting study front sheet app 9.1Application submission21 Nov 2013View
Ely capacity study quintessential & long distance viewApplication submission21 Nov 2013View
Biodiversity and landscaping management planApplication submission21 Nov 2013View
Assessment methods and significance criteriaApplication submission21 Nov 2013View
Arboricultural development reportApplication submission21 Nov 2013View
Volume 3A cover page and contents A3 landscapeApplication submission21 Nov 2013View
Tree protection plan sheet 4Application submission21 Nov 2013View
Photomontage viewpoint 1 existing view and summer view 2030 sheet 2Application submission21 Nov 2013View
Photomontage viewpoint 2 existing view and summer view 2015 sheet 3Application submission21 Nov 2013View
Photo Montage- View point 1 Existing View and Summer View 2015 sheet 1 of 12Application submission21 Nov 2013View
Habitat survey resultsApplication submission21 Nov 2013View
Fig 8.1 Noise contour map do minimum opening yearApplication submission21 Nov 2013View
Fig 7.9 Indicative dist&sensitive receptors for const.site boundaryApplication submission21 Nov 2013View
Fig 11.5 Barn owl SurveysApplication submission21 Nov 2013View
Environmental masterplan - Environmental statement chapter 10Application submission21 Nov 2013View
Environmental driversApplication submission21 Nov 2013View
Bypass long and cross sectionApplication submission21 Nov 2013View
Tree survey front sheetApplication submission21 Nov 2013View
Tree protection plan sheet 5Application submission21 Nov 2013View
Tree protection plan sheet 2Application submission21 Nov 2013View
Site access and compoundsApplication submission21 Nov 2013View
Photomontage viewpoint location planApplication submission21 Nov 2013View
Photomontage viewpoint 6 existing view and summer viw 2030 sheet 12Application submission21 Nov 2013View
Noise contour maps do something 2031Application submission21 Nov 2013View
Noise contour maps do something 2015Application submission21 Nov 2013View
Noise contour map with scheme design yearApplication submission21 Nov 2013View
Noise contour map do minimum 2015Application submission21 Nov 2013View
Methodology to acquire digital imagesApplication submission21 Nov 2013View
Local landscaping characterApplication submission21 Nov 2013View
Invertebrate reportApplication submission21 Nov 2013View
General arrangementApplication submission21 Nov 2013View
Front sheet Environmental Impact assessment scoping opinion 5.1Application submission21 Nov 2013View
Fig 4.2 Lighting Contours Stutney Causeway RAApplication submission21 Nov 2013View
Fig 14.1 Agricultural LandholdingsApplication submission21 Nov 2013View
Fig 10.8 Cross Sections Environmental Masterplan Sheet 2Application submission21 Nov 2013View
Fig 10.14 Viewpoint Location PlanApplication submission21 Nov 2013View
Desk based archaeological assessmentApplication submission21 Nov 2013View
Water framework directiveApplication submission21 Nov 2013View
MethodologyApplication submission21 Nov 2013View
Location planApplication submission21 Nov 2013View
Fig 15.1 Water Attributes & FeaturesApplication submission21 Nov 2013View
Fig 10.9 Zone of Visual Influence Winter 2015Application submission21 Nov 2013View
Fig 10.22 Photographs 5-8Application submission21 Nov 2013View
Fig 10.12 Key Visual Effects Year 15 of Opening Summer 2030Application submission21 Nov 2013View
Fig 10.11 Year 2015 Winter Visual Impact ResidentialApplication submission21 Nov 2013View
Fig 10.10 Key Visual Effects Completion- WinterApplication submission21 Nov 2013View
Environmental masterplan A1Application submission21 Nov 2013View
Ely railway crossing option assessment addendumApplication submission21 Nov 2013View
EIA scoping opinionApplication submission21 Nov 2013View
Cross sections - scheme landscape proposals sheet 2Application submission21 Nov 2013View
Tree protection plan sheet 3Application submission21 Nov 2013View
Photomontage viewpoint 5 existing view and summer view 2030 sheet 10Application submission21 Nov 2013View
Photomontage viewpoint 3 existing view and summer view 2030 sheet 6Application submission21 Nov 2013View
Photmontage viewpoint 2 existing view and summer view 2030 sheet 4Application submission21 Nov 2013View
Noise difference do minimum opening year vs with scheme opening yearApplication submission21 Nov 2013View
Noise contour map with scheme opening yearApplication submission21 Nov 2013View
MethodologiesApplication submission21 Nov 2013View
Legislation and policyApplication submission21 Nov 2013View
Fig 7.6 Air Quality Monitoring Site LocationsApplication submission21 Nov 2013View
Underpass traffic calmingApplication submission21 Nov 2013View
Tree protection plan sheet 8Application submission21 Nov 2013View
Tree protection planApplication submission21 Nov 2013View
Photomontage viewpoint 6 existing view and winter view 2015 sheet 11Application submission21 Nov 2013View
Photomontage methodologyApplication submission21 Nov 2013View
Front sheet Option assessment report App 3.1Application submission21 Nov 2013View
Fig 8.10 Noise difference do minimum vs do nothing 2015Application submission21 Nov 2013View
Fig 11.3 Waterbody Survey MapApplication submission21 Nov 2013View
Fig 10.7 Cross Sections Environmental Masterplan Sheet 1Application submission21 Nov 2013View
Fig 10.2 Regional Landscape CharacterApplication submission21 Nov 2013View
Fig 10.18 Panoramic Viewpoints P7-8Application submission21 Nov 2013View
Fig 10.1 TopographyApplication submission21 Nov 2013View
from Cambs Chambers of CommerceConsultee comment1 Dec 2014View
from City of Ely CouncilConsultee comment1 Dec 2014View
from Littleport PCConsultee comment29 Aug 2014View
from English HeritageConsultee comment29 Aug 2014View
from Greater Cambridge & Greater Pbro Local Enterprise PartnershipConsultee comment20 Aug 2014View
from Mepal PCConsultee comment15 Aug 2014View
from Soham Town CouncilConsultee comment29 Jul 2014View
from CCC Rights of WayConsultee comment23 Jul 2014View
from Network RailConsultee comment23 Jul 2014View
from ECDC PlanningConsultee comment23 Jul 2014View
from Highways AuthorityConsultee comment22 Jul 2014View
from Natural EnglandConsultee comment18 Jul 2014View
Response from Littleport Parish CouncilConsultee comment16 Jul 2014View
response from Environment AgencyConsultee comment20 Jun 2014View
Response from ECDC Tree Officer Oct 13Consultee comment8 May 2014View
Response from ECDC EHO Nov 13Consultee comment8 May 2014View
Response from City of Ely Feb 14Consultee comment8 May 2014View
Response from Rights of Way Oct 13Consultee comment8 May 2014View
Response from Natural England Oct 13Consultee comment8 May 2014View
Response from ECDC Nov 13Consultee comment8 May 2014View
Response from East Cambs Commercial Vehicles Nov 13Consultee comment8 May 2014View
Response from Cathedral fabric commission Oct 13Consultee comment8 May 2014View
Response from Baldwin to applicantConsultee comment8 May 2014View
Response from Landscape Partnership Feb 14Consultee comment8 May 2014View
Response from ECDC Feb 14Consultee comment8 May 2014View
Response from ECDC EHO Nov 13Consultee comment8 May 2014View
From East Cambs HCV CommitteeConsultee comment8 May 2014View
From East Cambs HCV CommitteeConsultee comment8 May 2014View
Response from Highways Feb 14Consultee comment8 May 2014View
Response from English Heritage report Nov 13Consultee comment8 May 2014View
Response from English Heritage Nov 13Consultee comment8 May 2014View
Response from Ecology Nov 13Consultee comment8 May 2014View
Response from ECDC Jan 13Consultee comment8 May 2014View
Response from ECDC Comments Oct 13Consultee comment8 May 2014View
Response from CPRE Oct 13Consultee comment8 May 2014View
Response from Transport officer Nov 13Consultee comment8 May 2014View
Response from Soham town council Oct 13Consultee comment8 May 2014View
Response from Mgr Enterprise Mar 14Consultee comment8 May 2014View
Response from ECDC EHO Nov 13Consultee comment8 May 2014View
Response from CPRE Mar 14Consultee comment8 May 2014View
Response from Local enterprise Mar 14Consultee comment8 May 2014View
Response from English Heritage Nov 13Consultee comment8 May 2014View
response from English HeritageConsultee comment8 May 2014View
Response from Ecology Mar 14Consultee comment8 May 2014View
Response from ECDC Wendy HagueConsultee comment8 May 2014View
Response from ECDC Nov 13Consultee comment8 May 2014View
Response from ECDC conservation Oct 13Consultee comment8 May 2014View
Response from City of Ely Council Oct 13Consultee comment8 May 2014View
Response from Cawdle Fen IDB Oct 13Consultee comment8 May 2014View
report from English HeritageConsultee comment8 May 2014View
Response from Stuntney village Nov 13Consultee comment8 May 2014View
Response from Landscape partnership Nov 13Consultee comment8 May 2014View
Response from Highways Mar 14Consultee comment8 May 2014View
Response from ECDC planning decision Feb 14Consultee comment8 May 2014View
Response from ECDC comments Oct 13Consultee comment8 May 2014View
Response from EA Oct 13Consultee comment8 May 2014View
Response from Archaeology Nov 13Consultee comment8 May 2014View
Response from Sutton Parish Council Nov 13Consultee comment8 May 2014View
Response from Middle Fen & Mere Oct 13Consultee comment8 May 2014View
Response from Landscape partnership Nov 13Consultee comment8 May 2014View
Response from Highways Mar 14Consultee comment8 May 2014View
from Rights of Way & Access TeamApplicant/Agent correspondence3 Apr 2014View
from Cathedrals Fabric Commission for EnglandApplicant/Agent correspondence3 Apr 2014View
from ECDC Conservation OfficerApplicant/Agent correspondence2 Apr 2014View
from CPREApplicant/Agent correspondence2 Apr 2014View
from CPREApplicant/Agent correspondence2 Apr 2014View
from Environment AgencyApplicant/Agent correspondence21 Mar 2014View
ECDC Planning Committee reportApplicant/Agent correspondence5 Mar 2014View
Response from Environment AgencyApplicant/Agent correspondence27 Feb 2014View
from English HeritageApplicant/Agent correspondence27 Feb 2014View
Response Ely Allotment associationApplicant/Agent correspondence19 Feb 2014View
Natural EnglandApplicant/Agent correspondence19 Feb 2014View
Response Network railApplicant/Agent correspondence19 Feb 2014View
Response Ely CouncilApplicant/Agent correspondence19 Feb 2014View
Response ECDCApplicant/Agent correspondence19 Feb 2014View
Response Cllr HuntApplicant/Agent correspondence19 Feb 2014View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

Approve
Decision notice Response from ECDC planning decision Feb 14
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

No related records were published in this section.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.