Application under Section 42 of the Town and Country Planning (Scotland) Act 1997 (as amended) for the installation of a solar photovoltaic array (PV) with an export capacity of not more than 49.9MW and associated infrastructure subject to different conditions than those attached to planning permission appeal: PPA-120-2060. Specifically, the application seeks variation of condition 1 to extend the timescale for implementation of the planning permission until a date not later than 21 September 2027

Field 300M West Of Grange Of Berryhill Invergowrie

Approved Subject to ConditionsReference: 24/00048/FULMAngus

Last published check: 22 Sept 2026, 02:16. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Application Received Date

    Published milestoneCouncil source
  2. Application Validated Date

    Published milestoneCouncil source
  3. Latest Neighbour Consultation Date

    Published milestoneCouncil source
  4. Last Advertised In Press Date

    Published milestoneCouncil source
  5. Latest Advertisement Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  6. Neighbour Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  7. Standard Consultation Date

    Published milestoneCouncil source
  8. Latest Consultation Expiry Date

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  9. Actual Committee Date

    Published milestoneCouncil source
  10. Decision Made Date

    Published milestoneCouncil source
  11. Decision Issued Date

    Published milestoneCouncil source
  12. Determination Deadline

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  13. Proposal

    Scheduled

    Future date published by the council.

    Council source

Application summary

Status
Approved Subject to Conditions
Application type
Full Major Application
Received
5 Feb 2024
Validated
9 Feb 2024
Determination deadline
8 Jun 2024
Local authority
Angus

Application overview

Application under Section 42 of the Town and Country Planning (Scotland) Act 1997 (as amended) for the installation of a solar photovoltaic array (PV) with an export capacity of not more than 49.9MW and associated infrastructure subject to different conditions than those attached to planning permission appeal: PPA-120-2060. Specifically, the application seeks variation of condition 1 to extend the timescale for implementation of the planning permission until a date not later than 21 September 2027

Proposal details

Reference
24/00048/FULM
Alternative references
100657456-002
Ward
Monifieth & Sidlaw
Agent
Stephenson Halliday

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Field 300M West Of Grange Of Berryhill Invergowrie

This record has no verified map location.

View council map

Documents 51 of 51

DocumentPublishedAction
CONSTRUCTION TRAFFIC MANAMGEMENT PLANDischarge of Conditions · PDF6 Aug 2026View
PANEL STANDOFF DISTANCES TO LANDSCAPINGDischarge of Conditions · PDF8 Jul 2026View
SCHEME OF LANDSCAPINGDischarge of Conditions · PDF7 Jul 2026View
BIODIVERSITY MITIGATION AND ENHANCEMENT PLANDischarge of Conditions · PDF7 Jul 2026View
SHUNT REACTOR DETAILDischarge of Conditions · PDF6 Jul 2026View
TYPICAL TRACK CONSTRUCTION DETAILDischarge of Conditions · PDF6 Jul 2026View
SPECIES PROTECTION PLANDischarge of Conditions · PDF15 Jun 2026View
CCTV DETAILSDischarge of Conditions · PDF5 Jun 2026View
COVERING LETTER - FINAL SITE LAYOUT AND DESIGNDischarge of Conditions · PDF5 Jun 2026View
CUSTOMER SWITCHROOM FLOOR PLAN AND ELEVATIONSDischarge of Conditions · PDF5 Jun 2026View
DNO SUBSTATION FLOOR PLAN AND ELEVATIONSDischarge of Conditions · PDF5 Jun 2026View
NOISE IMPACT ASSESSMENT FOR FINAL SITE LAYOUT AND DESIGNDischarge of Conditions · PDF5 Jun 2026View
PERIMETER FENCING AND ENTRANCE GATE DETAILSDischarge of Conditions · PDF5 Jun 2026View
SITE LAYOUT PLANDischarge of Conditions · PDF5 Jun 2026View
SOLAR PV MODULE DETAILSDischarge of Conditions · PDF5 Jun 2026View
STRING INVERTER ELEVATIONSDischarge of Conditions · PDF5 Jun 2026View
SUBSTATION COMPOUND ELEVATIONSDischarge of Conditions · PDF5 Jun 2026View
SUBSTATION COMPOUND LAYOUTDischarge of Conditions · PDF5 Jun 2026View
SPARE PARTS CONTAINER FLOOR PLAN AND ELEVATIONSDischarge of Conditions · PDF5 Jun 2026View
SUBSTATION COMPOUND FENCING DETAILSDischarge of Conditions · PDF5 Jun 2026View
SUBSTATION COMPOUND GATE DETAILSDischarge of Conditions · PDF5 Jun 2026View
TRANSFORMER ELEVATIONS AND 3D VIEWDischarge of Conditions · PDF5 Jun 2026View
ECOW LETTER OF APPOINTMENTDischarge of Conditions · PDF20 May 2026View
ENVIRONMENTAL INCIDENT RESPONSE PLANDischarge of Conditions · PDF20 May 2026View
NOISE AND VIBRATION MANAGEMENT PLANDischarge of Conditions · PDF20 May 2026View
CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLANDischarge of Conditions · PDF20 May 2026View
CTMP COVERING LETTERDischarge of Conditions · PDF12 Dec 2025View
APPROVALDischarge of Conditions · PDF4 Dec 2024View
SCHEME OF DECOMMISSIONING AND RESTORATIONDischarge of Conditions · PDF3 Dec 2024View
ROAD ENHANCEMENT REVIEWDischarge of Conditions · PDF3 Dec 2024View
LANDSCAPE MANAGEMENT PLANDischarge of Conditions · PDF3 Dec 2024View
APPROVALDischarge of Conditions · PDF8 Nov 2024View
ACCESS MANAGEMENT PLANDischarge of Conditions · PDF7 Nov 2024View
PRIVATE WATER SUPPLY INFORMATIONDischarge of Conditions · PDF31 Jul 2024View
APPROVEDDecision Notice · PDF17 May 2024View
REPORT OF HANDLINGReport · PDF14 May 2024View
APPENDIX F3 - LANDSCAPE MITIGATION PLANSupporting Information · PDF1 May 2024View
PROPOSED SITE PLANDrawing · PDF30 Apr 2024View
ECOLOGY UPDATE SURVEYSupporting Information · PDF7 Feb 2024View
APPENDIX F - ECOLOGY ASSESSMENTSupporting Information · PDF7 Feb 2024View
APPENDIX F4 - BIODIVERSITY MANAGEMENT PLANSupporting Information · PDF7 Feb 2024View
CONDITION 6(C) - ACCESS MANAGEMENT PLANSupporting Information · PDF5 Feb 2024View
CONDITION 7 - BIODIVERSITY MITIGATION AND ENHANCEMENT PLANSupporting Information · PDF5 Feb 2024View
CONDITION 10 - LANDSCAPE MANAGEMENT AND MAINTENANCE PLANSupporting Information · PDF5 Feb 2024View
CONDITION 10 - PANEL STAND OFF DISTANCES TO LANDSCAPINGSupporting Information · PDF5 Feb 2024View
CONDITION 10 - SCHEME OF LANDSCAPINGSupporting Information · PDF5 Feb 2024View
LOCATION PLANDrawing · PDF5 Feb 2024View
SECTION 42 PLANNING STATEMENT FOR THE VARIATION OF CONDITION 1 FOR THE CONSENTEDSupporting Information · PDF5 Feb 2024View
APPLICATION PDFApplication Form · PDF5 Feb 2024View
CONDITION 8 - ROAD ENHANCEMENT REVIEWSupporting Information · PDF5 Feb 2024View
CONDITION 5 - SCHEME OF DECOMMISSIONING AND RESTORATIONSupporting Information · PDF5 Feb 2024View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

approved subject to conditions
APPROVED
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.