Council planning record
Lobb Farm, Access Road To Lobb Farm, Tetsworth North, OX9 7BE
Last published check: 22 Oct 2026, 13:51. Check the council record for more recent changes.
Council milestones and published deadlines. A deadline passing does not confirm a decision.
The proposed development is for a Gas Fired Electricity Generating Facility with the ability to generate up to 49.99 MW of electricity. A low carbon flexible generating facility using gas reciprocating engines. The facility will generate electricity principally for the regional distribution network in times of generation shortfall and/or high demand. (as clarified by additional information submitted 10 September 2019, 12 September 2019, 22 October 2019, 30 October 2019, 19 November 2019 and 21 November 2019). (As amended by Ownership Certificate B received 5 February 2020 and amplified by additional information received 5 February 2020).
Sign in to view all collected council fields and recorded changes.
Sign in to view collected detailsLobb Farm, Access Road To Lobb Farm, Tetsworth North, OX9 7BE
This record has no verified map location.
| Document | Published | Action |
|---|---|---|
| Corrected Certificate BApplication Form | Not published | View |
| Application Form - Certificate B SupersededApplication Form | Not published | View |
| Corrected Certificate BOther Plans/Information | Not published | View |
| 2019-09-10 Email from agentOther Plans/Information | Not published | View |
| Use of hydrogen in thermal generation (February 2020)Other Plans/Information | Not published | View |
| EnAppSys Energy InsightOther Plans/Information | Not published | View |
| 2019-09-12-Email from AgentOther Plans/Information | Not published | View |
| Planning Statement September 2019 RedactedOther Plans/Information | Not published | View |
| Planning Statement September 2019Other Plans/Information | Not published | View |
| 2019-11-19-Email from AgentOther Plans/Information | Not published | View |
| 2019-10-22 Access Technical NoteOther Plans/Information | Not published | View |
| 2019-10-22 Email from AgentOther Plans/Information | Not published | View |
| Construction Traffic Management Plan November 2019Other Plans/Information | Not published | View |
| 2019-11-21 Email from AgentOther Plans/Information | Not published | View |
| AEL-18080-TPP Rev B - Tree Protection Plan (North)Other Plans/Information | Not published | View |
| AEL-18080-TIP Rev B - Tree Impact PlanOther Plans/Information | Not published | View |
| AEL-18080-TCNLP Rev B - Tree Constraints New Layout PlanOther Plans/Information | Not published | View |
| Arboricultural Impact AssessmentOther Plans/Information | Not published | View |
| 2019-10-30 Email from AgentOther Plans/Information | Not published | View |
| Site Office Elevations drwgno 352 SO 01General Plan | Not published | View |
| Compound Perimeter Fence Detail drwgno GP WMF 02General Plan | Not published | View |
| Tree Protection Cable Run Plan drwgno AEL-18080-TPCRP-01-CGeneral Plan | Not published | View |
| Masterplan North drwgno SL194 L X MP 2General Plan | Not published | View |
| Masterplan drwgno SL194 L X MP 1General Plan | Not published | View |
| General arrangement 11KV Substation drwgno SL194 L X ELEV 3General Plan | Not published | View |
| Tree Protection Cable Run Plan drwgno AEL-18080-TPCRP-02-CGeneral Plan | Not published | View |
| Topographic Survey drwgno 18-112-01General Plan | Not published | View |
| Substation Plan and Elevations drwgno 352 SS 01General Plan | Not published | View |
| Site Access Plan drwgno 352 SA 01General Plan | Not published | View |
| Palisade Security Fence Detail drwgno GP PF 01General Plan | Not published | View |
| High Pressure Gas Main Connection drwgno GP GR 01 Rev AGeneral Plan | Not published | View |
| Heat Recovery Control Kiosk drwgno 352 HRK 01General Plan | Not published | View |
| Container for Welfare and Spare Parts Plan drwgno GP SPC 01General Plan | Not published | View |
| Ammonia-Urea Tank Elevations drwgno 352 AT 01General Plan | Not published | View |
| Location Plan drwgno 352 LP 01General Plan | Not published | View |
| High Pressure Gas Main Connection drwgno PREM364-GEN-0000-0001(Rev B)General Plan | Not published | View |
| Contractors Temporary Construction Compound drwgno GP CC 01 Rev AGeneral Plan | Not published | View |
| Water Tank Elevations drwgno 352 WT 01General Plan | Not published | View |
| Engine Oil Tanks Elevation drwgno SL194 L X ELEV 7General Plan | Not published | View |
| Engine House Elevations and Plan drwgno 352 EE 01General Plan | Not published | View |
| Cross Sections drwgno 352 CS 01General Plan | Not published | View |
| Planting Plan drwgno 352 PP 01General Plan | Not published | View |
| Compound Entrance Gate drwgno GP EG 03General Plan | Not published | View |
| Superseded Construction Traffic Management PlanSupporting documentation | Not published | View |
| Letter from National Grid re P18S2995FUL P18S2996FULSupporting documentation | Not published | View |
| Abnormal Load Routing Technical Note Part2Supporting documentation | Not published | View |
| Topographic Site Survey and AppendixSupporting documentation | Not published | View |
| Preliminary Ecological AssessmentSupporting documentation | Not published | View |
| Landscape and Visual Appraisal Part 1Supporting documentation | Not published | View |
| Air Quality AssessmentSupporting documentation | Not published | View |
| Letter from RenewableUKSupporting documentation | Not published | View |
| Letter from National GridSupporting documentation | Not published | View |
| Archaeological EvaluationSupporting documentation | Not published | View |
| Letter from Scottish&Southern Electricity NetworksSupporting documentation | Not published | View |
| Noise AssessmentSupporting documentation | Not published | View |
| Lighting Assessment PlanSupporting documentation | Not published | View |
| Flood Risk AssessmentSupporting documentation | Not published | View |
| Abnormal Load Routing Technical Note Part1Supporting documentation | Not published | View |
| Methodology StatementSupporting documentation | Not published | View |
| Landscape and Visual Appraisal Part 2Supporting documentation | Not published | View |
| Geophysical Survey ReportSupporting documentation | Not published | View |
| Arboricultural Impact AssessmentSupporting documentation | Not published | View |
| Planning Design and Access Statement 29.08.19Supporting documentation | Not published | View |
Documents open on the council website. Browse council documents if a link has changed.
Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.
Understanding planning · 13 min read
Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.
Understanding planning · 13 min read
Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.
Understanding planning · 13 min read
Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.