Council planning record

Construction of an electrolytic low carbon hydrogen production facility, hydrogen export pipeline network, electricity and water connections, including water supply and effluent discharge, above ground installations, construction and laydown areas, and ancillary development

Land at the Foundry Site (Foundry Central), Teesworks, other land at Teesworks and land in the vicinity of and at Wilton International site and Lackenby

WithdrawnReference: R/2024/0271/ESMRedcar and Cleveland Borough Council

Last published check: 29 Oct 2026, 13:23. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Consultation Start

    Published milestoneCouncil source
  4. Consultation Expiry

    Past published deadline

    A published target or deadline. It does not confirm an outcome.

    Council source
  5. Decision Date

    Published milestoneCouncil source

Application summary

Status
Withdrawn
Application type
Env Statement Major
Received
22 Apr 2024
Validated
22 Apr 2024
Determination deadline
Not published
Local authority
Redcar and Cleveland Borough Council

Application overview

Construction of an electrolytic low carbon hydrogen production facility, hydrogen export pipeline network, electricity and water connections, including water supply and effluent discharge, above ground installations, construction and laydown areas, and ancillary development

Proposal details

Reference
R/2024/0271/ESM
Agent
DWD

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

Land at the Foundry Site (Foundry Central), Teesworks, other land at Teesworks and land in the vicinity of and at Wilton International site and Lackenby

This record has no verified map location.

Documents 323 of 323

DocumentPublishedAction
ApplicationFormRedacted.pdfApplication Form22 Apr 2024View
Covering Letter.pdfCovering Letter22 Apr 2024View
HyGreen CIL form.pdfApplication Form - CIL Form22 Apr 2024View
Redcar BC Electrolytic low carbon hydrogen facility Teeworks RC011.pdfConsultee response - Sabic Pipeline Operator (TPEP)25 Apr 2024View
1400020761(5).pdfConsultee response - Northern Gas Network Map 130 Apr 2024View
NGN Map 2.pdfConsultee response - Northern Gas Network Map 230 Apr 2024View
1400020761.pdfConsultee response - Northern Gas Network Map 330 Apr 2024View
1400020761(2).pdfConsultee response - Northern Gas Network Map 430 Apr 2024View
1400020761(3).pdfConsultee response - Northern Gas Network Map 530 Apr 2024View
1400020761(4).pdfConsultee response - Northern Gas Network Map 630 Apr 2024View
Planning Strategy.pdfConsultee response - Strategic Planning (Policy)8 May 2024View
MGE05267 Contaminated Land.pdfConsultee response - Environmental Protection (Contaminated Land)13 May 2024View
HSE LUP team response to RCBC - R-2024-0271-ERM - 15 May 2024.pdfConsultee response - Health & Safety Executive LUP team15 May 2024View
0271 Nusiance.pdfConsultee response - Environmental Protection (Nuisance)16 May 2024View
Police ALO Comments.pdfConsultee response - Cleveland Police17 May 2024View
Consultee Response North East Archaeological Research Limited.pdfConsultee Response - North East Archaeological Research Limited21 May 2024View
R20240271ESM - Planning Objection - Hygreen.pdfConsultee response - Wood Group CATS Pipeline22 May 2024View
NWL.pdfConsultee response - Northumbrian Water22 May 2024View
2024 05 22 HyGreenHydrogen NoObj.pdfConsultee response - National Highways24 May 2024View
474303_R_2024_0271_ESM_HyGreen_NEresponse_24.5.24.pdfConsultee response - Natural England28 May 2024View
EA_R.2024.0271.ESM_Official_31.05.2024.pdfConsultee response - Environment Agency31 May 2024View
Consultee Response - Network Rail.pdfConsultee Response - Network Rail14 Jun 2024View
LLFA response.pdfConsultee response - Engineers (Local Lead Flood Authority)17 Sept 2024View
490618_R_2024_0271_ESM_HyGreen_AdditonalInfo_NEresponse_15.11.24.pdfConsultee response - Natural England18 Nov 2024View
Highways.pdfConsultee response - Engineering Team (Highways)16 Dec 2024View
494675_R_2024_0271_ESM_HyGreen_AdditonalInfo_NEresponse_19.12.24.pdfConsultee response - Natural England19 Dec 2024View
504617_R_2024_0271_ESM_HyGreen_NE_response30.4.25.pdfConsultee response - Natural England1 May 2025View
Location Plan.pdfLocation Plan (Sheet 1 of 23)23 Apr 2024View
Page 4 location.pdfLocation Plan Page 4 of 2323 Apr 2024View
Page 5 location.pdfLocation Plan Page 5 of 2323 Apr 2024View
Page 6 location.pdfLocation Plan Page 6 of 2323 Apr 2024View
Page 7 location.pdfLocation Plan Page 7 of 2323 Apr 2024View
Page 8 location.pdfLocation Plan Page 8 of 2323 Apr 2024View
Page 9 location.pdfLocation Plan Page 9 of 2323 Apr 2024View
Page 10 location.pdfLocation Plan Page 10 of 2323 Apr 2024View
Page 11 location.pdfLocation Plan Page 11 of 2323 Apr 2024View
Page 12 location.pdfLocation Plan Page 12 of 2323 Apr 2024View
Page 13 location.pdfLocation Plan Page 13 of 2323 Apr 2024View
Page 14 location.pdfLocation Plan Page 14 of 2323 Apr 2024View
Page 15 location.pdfLocation Plan Page 15 of 2323 Apr 2024View
Page 16 location.pdfLocation Plan Page 16 of 2323 Apr 2024View
Page 17 location.pdfLocation Plan Page 17 of 2323 Apr 2024View
Page 18 location.pdfLocation Plan Page 18 of 2323 Apr 2024View
Page 19 location.pdfLocation Plan Page 19 of 2323 Apr 2024View
Page 20 location.pdfLocation Plan Page 20 of 2323 Apr 2024View
Page 21 location.pdfLocation Plan Page 21 of 2323 Apr 2024View
Page 22 location.pdfLocation Plan Page 22 of 2323 Apr 2024View
Page 23 location.pdfLocation Plan Page 23 of 2323 Apr 2024View
Page 2 location.pdfLocation Plan Page 2 of 2323 Apr 2024View
Page 3 location.pdfLocation Plan Page 3 of 2323 Apr 2024View
COMMENTS Ineos.pdfNeighbour Comments - INEOS UK SNS Limited24 Apr 2024View
50303-24 - AA Representation - App R_24_0271_ESM - RCBC - 080524(32130394.1).pdfNeighbour Comments - Lichfields on Behalf of Anglo American8 May 2024View
Neighbour Comments British Steel(1).pdfNeighbour Comments - British Steel9 May 2024View
Planning_Application_Objection_Letter_(ref__R_2024_2071_ESM).docx(1).pdfNeighbour Comments - Mishcon de Reya LLP on behalf of Redcar Bulk Terminal9 May 2024View
neighbour comments - Cartman B.pdfNeighbour Comments - Cartman B31 May 2024View
HyGreen ES APPENDIX 11-A baseline appendix_Ornithology REDACTED_Optimized.pdfEnvironmental Statement Appendix 11 A Baseline Appendix Ornithology Redacted Optimized22 Apr 2024View
HyGreen - 41500-00414-PT-DGA-00006 - Plan View and Isometric view .pdfPlan View And Isometric View22 Apr 2024View
HyGreen - 415000-00414 - PL - DLP - 00001_A - HYGREEN PIPELINES AND INFRASTRUCTURE DRAWING OVERALL LAYOUT.pdfPipelines And Infrastructure Drawing Overall Layout22 Apr 2024View
HyGreen - 415000-00414-00-EL-DGA-00001-001 Connection Cable Routing.pdfConnection Cable Routing22 Apr 2024View
HyGreen - 416041-50717-01-CI-DAL-00001 -OVERALL FOUNDATION LAYOUT FOR HYGREEN AT FOUNDRY.pdfOverall Foundation Layout22 Apr 2024View
HyGreen - 416041-50717-01-PI-DPP-00001-01_Rev-B (004)- Plot Plan for HyGreen at Foundry.pdfPlot Plan For Hygreen At Foundry22 Apr 2024View
HyGreen - 416041-50717-01-PI-DPP-00001-02_Rev-B-Plot Plan Layout for HyGreen at Foundry.pdfPlot Plan Layout For Hygreen At Foundry22 Apr 2024View
HyGreen - 415000-00414-PL-DGA-00001-001 and 002 AGI GENERAL ARRANGMENT.pdfAGI General Arrangment Plant End Of Line Sheet 122 Apr 2024View
HyGreen - Access Plan for HyGreen.pdfAccess Plan For Hygreen22 Apr 2024View
HyGreen - Access South.pdfAccess South22 Apr 2024View
HyGreen - Access North.pdfAccess North22 Apr 2024View
HyGreen - Figure 1 - Outline Landscape and Management Plan.pdfFigure 1 Outline Landscape And Management Plan22 Apr 2024View
HyGreen - 416041-50717-01-CI-DAL-11002 - DRAINAGE LAYOUT.pdfDrainage Layout22 Apr 2024View
HyGreen - 41500-00414-PT-DGA-00009 - Elevation and Section Views Sections A and B.pdfElevation And Section Views Sections A And B22 Apr 2024View
HyGreen - 41500-00414-PT-DGA-00008 - Elevation and Section Views Looking South and West .pdfElevation And Section Views Looking South And West22 Apr 2024View
HyGreen - 41500-00414-PT-DGA-00007 - Elevation and Section Views Looking North and East.pdfElevation And Section Views Looking North And East22 Apr 2024View
Construction Area Yard Layout 1 of 5.pdfConstruction Area Yard Layout 1 of 522 Apr 2024View
Construction Area Yard Layout 2 of 5.pdfConstruction Area Yard Layout 2 of 522 Apr 2024View
Construction Area Yard Layout 3 of 5.pdfConstruction Area Yard Layout 3 of 522 Apr 2024View
Construction Area Yard Layout 4 of 5.pdfConstruction Area Yard Layout 4 of 522 Apr 2024View
Construction Area Yard Layout 5 of 5.pdfConstruction Area Yard Layout 5 of 522 Apr 2024View
Typical Construction Right of Way Buried Open Cut Sheet 1 of 3.pdfTypical Construction Right of Way Buried Open Cut Sheet 1 of 322 Apr 2024View
Typical Construction Right of Way ABOVE GROUND PIPE CORRIDOR Sheet 2 of 3.pdfTypical Construction Right of Way above ground pipe corridor Sheet 2 of 322 Apr 2024View
Typical Construction Right of Way Pipe Racking and Pipe Bridges Sheet 3 of 3.pdfTypical Construction Right of Way Pipe Racking and Pipe Bridges Sheet 3 of 322 Apr 2024View
AGI General Arrangement Sheet NGN End of Line Sheet 2.pdfAGI General Arrangement NGN End of Line Sheet 222 Apr 2024View
Pipelines and Infrastructure Plant Approach 1 of 5.pdfPipelines and Infrastructure Plant Approach 1 of 522 Apr 2024View
Pipelines and Infrastructure Plant Approach 2 of 5.pdfPipelines and Infrastructure Plant Approach 2 of 522 Apr 2024View
Pipelines and Infrastructure Plant Approach 3 of 5.pdfPipelines and Infrastructure Plant Approach 3 of 522 Apr 2024View
Pipelines and Infrastructure Plant Approach 4 of 5.pdfPipelines and Infrastructure Plant Approach 4 of 522 Apr 2024View
Pipelines and Infrastructure Plant Approach 5 of 5.pdfPipelines and Infrastructure Plant Approach 5 of 522 Apr 2024View
Pipelines and Infrastructure Overall AGI Layout Sheet 1 of 4.pdfPipelines and Infrastructure Overall AGI Layout Sheet 1 of 422 Apr 2024View
Pipelines and Infrastructure Overall AGI Layout Sheet 2 of 4.pdfPipelines and Infrastructure Overall AGI Layout Sheet 2 of 422 Apr 2024View
Pipelines and Infrastructure Overall AGI Layout Sheet 3 of 4.pdfPipelines and Infrastructure Overall AGI Layout Sheet 3 of 422 Apr 2024View
Pipelines and Infrastructure Overall AGI Layout Sheet 4 of 4.pdfPipelines and Infrastructure Overall AGI Layout Sheet 4 of 422 Apr 2024View
Planning Application Site Boundary Sheet 3 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 3 of 822 Apr 2024View
Planning Application Site Boundary Sheet 2 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 2 of 822 Apr 2024View
Planning Application Site Boundary Sheet 1 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 1 of 822 Apr 2024View
Planning Application Site Boundary Sheet 8 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 8 of 822 Apr 2024View
Planning Application Site Boundary Sheet 7 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 7 of 822 Apr 2024View
Planning Application Site Boundary Sheet 6 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 6 of 822 Apr 2024View
Planning Application Site Boundary Sheet 5 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 5 of 822 Apr 2024View
Planning Application Site Boundary Sheet 4 of 8.pdfFigure 1 Planning Application Site Boundary Sheet 4 of 822 Apr 2024View
HyGreen ES Report Chapter 1 INTRODUCTION_FINAL.pdfEnvironmental Statement Report - Chapter 1 Introduction Final22 Apr 2024View
Hygreen ES Report Chapter 11 Ornithology REDACTED.pdfEnvironmental Statement Report - Chapter 11 Ornithology Redacted22 Apr 2024View
HyGreen ES Report Chapter 7 PLANNING POLICY CONTEXT_FINAL.pdfEnvironmental Statement Report - Chapter 7 Planning Policy Context Final22 Apr 2024View
HyGreen ES Report Chapter 8 WATER ENVIRONMENT FINAL.pdfEnvironmental Statement Report - Chapter 8 Water Environment Final22 Apr 2024View
HyGreen ES Report Chapter 9 GEOLOGY - FINAL.pdfEnvironmental Statement Report - Chapter 9 Geology Final22 Apr 2024View
HyGreen ES Report Chapter 10 ECOLOGY AND NATURE CONSERVATION_FINAL.pdfEnvironmental Statement Report - Chapter 10 Ecology And Nature Conservation Final22 Apr 2024View
HyGreen ES Report Chapter 2 ASSESSMENT METHODOLOGY_FINAL.pdfEnvironmental Statement Report - Chapter 2 Assessment Methodology Final22 Apr 2024View
HyGreen ES Report Chapter 3 DESCRIPTION OF THE EXISTING ENVIRONMENT_FINAL.pdfEnvironmental Statement Report - Chapter 3 Description Of The Existing Environment Final22 Apr 2024View
HyGreen ES Report Chapter 4 PROPOSED DEVELOPMENT_FINAL.pdfEnvironmental Statement Report - Chapter 4 Proposed Development Final22 Apr 2024View
HyGreen ES Report Chapter 5 CONSTRUCTION - FINAL.pdfEnvironmental Statement Report - Chapter 5 Construction Final22 Apr 2024View
HyGreen ES Report Chapter 6 ALTERNATIVES AND DESIGN EVOLUTION_FINAL.pdfEnvironmental Statement Report - Chapter 6 Alternatives And Design Evolution Final22 Apr 2024View
HyGreen ES Report Chapter 17 SOCIO-ECONOMICS AND LAND USE_FINAL.pdfEnvironmental Statement Report - Chapter 17 Socio Economics And Land Use Final22 Apr 2024View
HyGreen ES Report Chapter 18 MAJOR ACCIDENTS AND DISASTERS_FINAL.pdfEnvironmental Statement Report - Chapter 18 Major Accidents And Disasters Final22 Apr 2024View
HyGreen ES Report Chapter 19 MATERIALS AND WASTE_FINAL.pdfEnvironmental Statement Report - Chapter 19 Materials And Waste Final22 Apr 2024View
HyGreen ES Report Chapter 20 Human Health_FINAL.pdfEnvironmental Statement Report - Chapter 20 Human Health Final22 Apr 2024View
HyGreen ES Report Chapter 21 CLIMATE CHANGE_FINAL.pdfEnvironmental Statement Report - Chapter 21 Climate Change Final22 Apr 2024View
HyGreen ES Report Chapter 23 Summary of Significant Effects_FINAL.pdfEnvironmental Statement Report - Chapter 23 Summary Of Significant Effects Final22 Apr 2024View
HyGreen ES Report Chapter 12 LANDSCAPE AND VISUAL AMENITY_FINAL.pdfEnvironmental Statement Report - Chapter 12 Landscape And Visual Amenity Final22 Apr 2024View
HyGreen ES Report Chapter 13 Cultural Heritage_FINAL.pdfEnvironmental Statement Report - Chapter 13 Cultural Heritage Final22 Apr 2024View
HyGreen ES Report Chapter 14 TRAFFIC AND TRANSPORTATION_FINAL.pdfEnvironmental Statement Report - Chapter 14 Traffic And Transportation Final22 Apr 2024View
HyGreen ES Report Chapter 15 AIR QUALITY_FINAL.pdfEnvironmental Statement Report - Chapter 15 Air Quality Final22 Apr 2024View
HyGreen ES Report Chapter 16 NOISE AND VIBRATION_FINAL.pdfEnvironmental Statement Report - Chapter 16 Noise And Vibration Final22 Apr 2024View
Figure 1-1 - The Proposed Development Site.pdfEnvironmental Statement Figure 1 1 The Proposed Development Site22 Apr 2024View
Figure 3-1 - Areas of the Proposed Development Site.pdfEnvironmental Statement Figure 3 1 Areas Of The Proposed Development Site22 Apr 2024View
Figure 4-2 - Electricity Connection Corridor.pdfEnvironmental Statement Figure 4 2 Electricity Connection Corridor22 Apr 2024View
Figure 4-3 - Water Connection Corridor.pdfEnvironmental Statement Figure 4 3 Water Connection Corridor22 Apr 2024View
Figure 4-5 - Water Process Schematic.pdfEnvironmental Statement Figure 4 5 Water Process Schematic22 Apr 2024View
Figure 4-6 - Indicative Plot Layout (Main Site).pdfEnvironmental Statement Figure 4 6 Indicative Plot Layout (main Site)22 Apr 2024View
Figure 4-1 - Hydrogen Export Pipeline Corridor.pdfEnvironmental Statement Figure 4 1 Hydrogen Export Pipeline Corridor22 Apr 2024View
Figure 5-2 - Indicative Pipeline Routings and Construction Methodologies.pdfEnvironmental Statement Figure 5 2 Indicative Pipeline Routings And Construction Methodologies22 Apr 2024View
Figure 5-1 - Construction Compound and Laydown Areas.pdfEnvironmental Statement Figure 5 1 Construction Compound And Laydown Areas22 Apr 2024View
Figure 8-2 - Groundwater Features and their Attributes.pdfEnvironmental Statement Figure 8 2 Groundwater Features And Their Attributes22 Apr 2024View
Figure 8-3 - Fluvial Flood Risk.pdfEnvironmental Statement Figure 8 3 Fluvial Flood Risk22 Apr 2024View
Figure 8-4 - Surface Water Flood Risk.pdfEnvironmental Statement Figure 8 4 Surface Water Flood Risk22 Apr 2024View
Figure 8-1 - Surface Water Features and their Attributes.pdfEnvironmental Statement Figure 8 1 Surface Water Features And Their Attributes22 Apr 2024View
Figure 9-16 - Groundwater Abstraction.pdfEnvironmental Statement Figure 9 16 Groundwater Abstraction22 Apr 2024View
Figure 9-17- Surface Water Abstraction.pdfEnvironmental Statement Figure 9 17 Surface Water Abstraction22 Apr 2024View
Figure 9-18a - NGS Collapsible Deposits.pdfEnvironmental Statement Figure 9 18a Natural Ground Subsidence Collapsible Deposits22 Apr 2024View
Figure 9-18b - NGS Compressible Deposits.pdfEnvironmental Statement Figure 9 18b Natural Ground Subsidence Compressible Deposits22 Apr 2024View
Figure 9-18c - NGS Ground Dissolution of Soluble Rocks.pdfEnvironmental Statement Figure 9 18c Natural Ground Subsidence Ground Dissolution Of Soluble Rocks22 Apr 2024View
Figure 9-18d - NGS Landslides.pdfEnvironmental Statement Figure 9 18d Natural Ground Subsidence Landslides22 Apr 2024View
Figure 9-18e - NGS Running Sand.pdfEnvironmental Statement Figure 9 18e Natural Ground Subsidence Running Sand22 Apr 2024View
Figure 9-18f - NGS Shrink Swell Clays.pdfEnvironmental Statement Figure 9 18f Natural Ground Subsidence Shrink Swell Clays22 Apr 2024View
Figure 9-19a - Agricultural Land Classification - Main Site.pdfEnvironmental Statement Figure 9 19a Agricultural Land Classification Main Site22 Apr 2024View
Figure 9-19b - Agricultural Land Classification - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 19b Agricultural Land Classification Water And Wastewater Connection Works22 Apr 2024View
Figure 9-19c - Agricultural Land Classification - Electrical Connection Works.pdfEnvironmental Statement Figure 9 19c Agricultural Land Classification Electrical Connection Works22 Apr 2024View
Figure 9-19d - Agricultural Land Classification - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 19d Agricultural Land Classification Hydrogen Distribution Network22 Apr 2024View
Figure 9-20 - Brit Pits.pdfEnvironmental Statement Figure 9 20 Brit Pits22 Apr 2024View
Figure 9-21 - Non Coal Minings.pdfEnvironmental Statement Figure 9 21 Non Coal Minings22 Apr 2024View
Figure 9-22 - Surface Ground Workings.pdfEnvironmental Statement Figure 9 22 Surface Ground Workings22 Apr 2024View
Figure 9-23 - Underground Workings.pdfEnvironmental Statement Figure 9 23 Underground Workings22 Apr 2024View
Figure 9-11 - Discharge Consents.pdfEnvironmental Statement Figure 9 11 Discharge Consents22 Apr 2024View
Figure 9-12a - Superficial Aquifers - Main Site .pdfEnvironmental Statement Figure 9 12a Superficial Aquifers Main Site22 Apr 2024View
Figure 9-12b - Superficial Aquifers - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 12b Superficial Aquifers Water And Wastewater Connection Works22 Apr 2024View
Figure 9-12c - Superficial Aquifers - Electrical Connection Works.pdfEnvironmental Statement Figure 9 12c Superficial Aquifers Electrical Connection Works22 Apr 2024View
Figure 9-12d - Superficial Aquifers - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 12d Superficial Aquifers Hydrogen Distribution Network22 Apr 2024View
Figure 9-13a - Bedrock Aquifers - Main Site.pdfEnvironmental Statement Figure 9 13a Bedrock Aquifers Main Site22 Apr 2024View
Figure 9-13b - Bedrock Aquifers - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 13b Bedrock Aquifers Water And Wastewater Connection Works22 Apr 2024View
Figure 9-13c - Bedrock Aquifers - Electrical Connection Works.pdfEnvironmental Statement Figure 9 13c Bedrock Aquifers Electrical Connection Works22 Apr 2024View
Figure 9-13d - Bedrock Aquifers - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 13d Bedrock Aquifers Hydrogen Distribution Network22 Apr 2024View
Figure 9-14a - Groundwater Vulnerability - Main Site.pdfEnvironmental Statement Figure 9 14a Groundwater Vulnerability Main Site22 Apr 2024View
Figure 9-14b - Groundwater Vulnerability - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 14b Groundwater Vulnerability Water And Wastewater Connection Works22 Apr 2024View
Figure 9-14c - Groundwater Vulnerability - Electrical Connection Works.pdfEnvironmental Statement Figure 9 14c Groundwater Vulnerability Electrical Connection Works22 Apr 2024View
Figure 9-14d - Groundwater Vulnerability - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 14d Groundwater Vulnerability Hydrogen Distribution Network22 Apr 2024View
Figure 9-15 - Groundwater Source Protection Zones.pdfEnvironmental Statement Figure 9 15 Groundwater Source Protection Zones22 Apr 2024View
Figure 9-5 - Faults and Linear Features.pdfEnvironmental Statement Figure 9 5 Faults And Linear Features22 Apr 2024View
Figure 9-6 - Waste and Landfills.pdfEnvironmental StatementFigure 9 6 Waste And Landfills22 Apr 2024View
Figure 9-7 - Hazardous Sites.pdfEnvironmental Statement Figure 9 7 Hazardous Sites22 Apr 2024View
Figure 9-8a - Historical Industrial Landuses.pdfEnvironmental Statement Figure 9 8a Historical Industrial Landuses22 Apr 2024View
Figure 9-8b - Historical Industrial Landuses.pdfEnvironmental Statement Figure 9 8b Historical Industrial Landuses22 Apr 2024View
Figure 9-8c - Historical Industrial Landuses.pdfEnvironmental Statement Figure 9 8c Historical Industrial Landuses22 Apr 2024View
Figure 9-8d - Historical Industrial Landuses.pdfEnvironmental Statement Figure 9 8d Historical Industrial Landuses22 Apr 2024View
Figure 9-8e - Historical Industrial Landuses.pdfEnvironmental Statement Figure 9 8e Historical Industrial Landuses22 Apr 2024View
Figure 9-9 - Historical Tanks.pdfEnvironmental Statement Figure 9 9 Historical Tanks22 Apr 2024View
Figure 9-10a - Ecological Designations - Main Site.pdfEnvironmental Statement Figure 9 10a Ecological Designations Main Site22 Apr 2024View
Figure 9-10b - Ecological Designations - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 10b Ecological Designations Water And Wastewater Connection Works22 Apr 2024View
Figure 9-10c - Ecological Designations - Electrical Connection Works.pdfEnvironmental Statement Figure 9 10c Ecological Designations Electrical Connection Works22 Apr 2024View
Figure 9-10d - Ecological Designations - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 10d Ecological Designations Hydrogen Distribution Network22 Apr 2024View
Figure 9-2d - Superficial Geology - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 2d Superficial Geology Hydrogen Distribution Network22 Apr 2024View
Figure 9-3a - Bedrock Geology - Main Site.pdfEnvironmental Statement Figure 9 3a Bedrock Geology Main Site22 Apr 2024View
Figure 9-3b - Bedrock Geology - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 3b Bedrock Geology Water And Wastewater Connection Works22 Apr 2024View
Figure 9-3c - Bedrock Geology - Electrical Connection Works.pdfEnvironmental Statement Figure 9 3c Bedrock Geology Electrical Connection Works22 Apr 2024View
Figure 9-3d - Bedrock Geology - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 3d Bedrock Geology Hydrogen Distribution Network22 Apr 2024View
Figure 9-4 - BGS Boreholes.pdfEnvironmental Statement Figure 9 4 Bgs Boreholes22 Apr 2024View
Figure 9-1a - Artificial Geology - Main Site.pdfEnvironmental Statement Figure 9 1a Artificial Geology Main Site22 Apr 2024View
Figure 9-1b - Artificial Geology - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 1b Artificial Geology Water And Wastewater Connection Works22 Apr 2024View
Figure 9-1c - Artificial Geology - Electrical Connection Works.pdfEnvironmental Statement Figure 9 1c Artificial Geology Electrical Connection Works22 Apr 2024View
Figure 9-1d - Artificial Geology - Hydrogen Distribution Network.pdfEnvironmental Statement Figure 9 1d Artificial Geology Hydrogen Distribution Network22 Apr 2024View
Figure 9-2a - Superficial Geology - Main Site.pdfEnvironmental Statement Figure 9 2a Superficial Geology Main Site22 Apr 2024View
Figure 9-2b - Superficial Geology - Water and Wastewater Connection Works.pdfEnvironmental Statement Figure 9 2b Superficial Geology Water And Wastewater Connection Works22 Apr 2024View
Figure 9-2c - Superficial Geology - Electrical Connection Works.pdfEnvironmental Statement Figure 9 2c Superficial Geology Electrical Connection Works22 Apr 2024View
Figure 10-2 - Non-Statutory Designations Sites within 2 km.pdfEnvironmental Statement Figure 10 2 Non Statutory Designations Sites Within 2 Km22 Apr 2024View
Figure 10-3 - Habitats of Principal Importance.pdfEnvironmental Statement Figure 10 3 Habitats Of Principal Importance22 Apr 2024View
Figure 10-1 - Statutory Designations within 10 km.pdfEnvironmental Statement Figure 10 1 Statutory Designations Within 10 Km22 Apr 2024View
Figure 12-3 - Zone of Theoretical Visibility and potential Viewpoint Locations.pdfEnvironmental Statement Figure 12 3 Zone Of Theoretical Visibility And Potential Viewpoint Locations22 Apr 2024View
Figure 12-4 - Topography.pdfEnvironmental Statement Figure 12 4 Topography22 Apr 2024View
Figure 12-5 - Zone of Theoretical Visibility and Representative Viewpoint Locations.pdfEnvironmental Statement Figure 12 5 Zone Of Theoretical Visibility And Representative Viewpoint Locations22 Apr 2024View
Figure 12-7 Photomontages.pdfEnvironmental Statement Figure 12 7 Photomontages22 Apr 2024View
Figure 12-1 - Landscape Context.pdfEnvironmental Statement Figure 12 1 Landscape Context22 Apr 2024View
Figure 12-2 - Landscape Character.pdfEnvironmental Statement Figure 12 2 Landscape Character22 Apr 2024View
Figure 13-2 - Location of Non-Designated Heritage Assets.pdfEnvironmental Statement Figure 13 2 Location Of Non Designated Heritage Assets22 Apr 2024View
Figure 13-3 - Location of Cultural Heritage Events.pdfEnvironmental Statement Figure 13 3 Location Of Cultural Heritage Events22 Apr 2024View
Figure 13-4 - Historic Landscape Character.pdfEnvironmental Statement Figure 13 4 Historic Landscape Character22 Apr 2024View
Figure 13-1 - Location of Designated Heritage Assets.pdfEnvironmental Statement Figure 13 1 Location Of Designated Heritage Assets22 Apr 2024View
Figure 14-3 - Traffic Count Locations.pdfEnvironmental Statement Figure 14 3 Traffic Count Locations22 Apr 2024View
Figure 14-4 - Traffic Routes.pdfEnvironmental Statement Figure 14 4 Traffic Routes22 Apr 2024View
Figure 14-1 - Traffic Study Area.pdfEnvironmental Statement Figure 14 1 Traffic Study Area22 Apr 2024View
Figure 14-2 - HGV Routes to and from Site.pdfEnvironmental Statement Figure 14 2 Hgv Routes To And From Site22 Apr 2024View
Figure 15-1 - Air Quality Study Area.pdfEnvironmental Statement Figure 15 1 Air Quality Study Area22 Apr 2024View
Figure 16-1 - Noise Sensitive Receptor and Monitoring Locations.pdfEnvironmental Statement Figure 16 1 Noise Sensitive Receptor And Monitoring Locations22 Apr 2024View
Figure 16-2 - Construction Noise Model Sound Source Layout.pdfEnvironmental Statement Figure 16 2 Construction Noise Model Sound Source Layout22 Apr 2024View
Figure 16-3 - Operational Noise Model Sound Source Layout.pdfEnvironmental Statement Figure 16 3 Operational Noise Model Sound Source Layout22 Apr 2024View
Figure 18-1 - Major Accidents and Disasters Receptors within 5 km of the Proposed Development Site Boundary.pdfEnvironmental Statement Figure 18 1 Major Accidents And Disasters Receptors Within 5 Km Of The Proposed Development Site Boundary22 Apr 2024View
Figure 19-1 - Historic and Authorised Landfills and Waste and Mineral sites.pdfEnvironmental Statement Figure 19 1 Historic And Authorised Landfills And Waste And Mineral Sites22 Apr 2024View
Figure 22-1 - Zones of Influence for Cumulative Effects Assessment (Sheet 4 of 4).pdfEnvironmental Statement Figure 22 1 Zones Of Influence For Cumulative Effects Assessment (sheet 4 Of 4)22 Apr 2024View
Figure 22-2 - Long List of Other Developments (Sheet 1 of 2).pdfEnvironmental Statement Figure 22 2 Long List Of Other Developments (sheet 1 Of 2)22 Apr 2024View
Figure 22-2 - Long List of Other Developments (Sheet 2 of 2).pdfEnvironmental Statement Figure 22 2 Long List Of Other Developments (sheet 2 Of 2)22 Apr 2024View
Figure 22-3 - Short List of Other Developments (Sheet 1 of 2).pdfEnvironmental Statement Figure 22 3 Short List Of Other Developments (sheet 1 Of 2)22 Apr 2024View
Figure 22-3 - Short List of Other Developments (Sheet 2 of 2).pdfEnvironmental Statement Figure 22 3 Short List Of Other Developments (sheet 2 Of 2)22 Apr 2024View
Figure 22-1 - Zones of Influence for Cumulative Effects Assessment (Sheet 1 of 4).pdfEnvironmental Statement Figure 22 1 Zones Of Influence For Cumulative Effects Assessment (sheet 1 Of 4)22 Apr 2024View
Figure 22-1 - Zones of Influence for Cumulative Effects Assessment (Sheet 2 of 4).pdfEnvironmental Statement Figure 22 1 Zones Of Influence For Cumulative Effects Assessment (sheet 2 Of 4)22 Apr 2024View
Figure 22-1 - Zones of Influence for Cumulative Effects Assessment (Sheet 3 of 4).pdfEnvironmental Statement Figure 22 1 Zones Of Influence For Cumulative Effects Assessment (sheet 3 Of 4)22 Apr 2024View
HyGreen ES Volume II APPENDIX 5-A Framework CEMP FINAL (1).pdfEnvironmental Statement Volume Ii Appendix 5 A Framework CEMP Final (1)22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-D Reptiles - FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 D Reptiles Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-E Invertebrate Survey Report -FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 E Invertebrate Survey Report Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-G FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 G Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-C Bats - FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 C Bats Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 13-A DBA_FINAL.pdfEnvironmental Statement Volume Ii Appendix 13 A Dba Final22 Apr 2024View
HyGreen ES Report Chapter 22 CUMULATIVE AND COMBINED EFFECTS_FINAL.pdfEnvironmental Statement Report Chapter 22 Cumulative And Combined Effects Final22 Apr 2024View
Figure 10-4 - Phase 1 Habitats (reduced).pdfEnvironmental Statement Figure 10 4 Phase 1 Habitats (reduced)22 Apr 2024View
Figure 12-6a - Winter Photography_Part4.pdfEnvironmental Statement Figure 12 6a Winter Photography Part422 Apr 2024View
Figure 12-6a - Winter Photography_Part5.pdfEnvironmental Statement Figure 12 6a Winter Photography Part522 Apr 2024View
Figure 12-6a - Winter Photography_Part6.pdfEnvironmental Statement Figure 12 6a Winter Photography Part622 Apr 2024View
Figure 12-6a - Winter Photography_Part7.pdfEnvironmental Statement Figure 12 6a Winter Photography Part722 Apr 2024View
Figure 12-6a - Winter Photography_Part1.pdfEnvironmental Statement Figure 12 6a Winter Photography Part122 Apr 2024View
Figure 12-6a - Winter Photography_Part2.pdfEnvironmental Statement Figure 12 6a Winter Photography Part222 Apr 2024View
Figure 12-6a - Winter Photography_Part3.pdfEnvironmental Statement Figure 12 6a Winter Photography Part322 Apr 2024View
Figure 12-6b - Summer Photography_Part3.pdfEnvironmental Statement Figure 12 6b Summer Photography Part322 Apr 2024View
Figure 12-6b - Summer Photography_Part4.pdfEnvironmental Statement Figure 12 6b Summer Photography Part422 Apr 2024View
Figure 12-6b - Summer Photography_Part5.pdfEnvironmental Statement Figure 12 6b Summer Photography Part522 Apr 2024View
Figure 12-6b - Summer Photography_Part6.pdfEnvironmental Statement Figure 12 6b Summer Photography Part622 Apr 2024View
Figure 12-6b - Summer Photography_Part7.pdfEnvironmental Statement Figure 12 6b Summer Photography Part722 Apr 2024View
Figure 12-6b - Summer Photography_Part1.pdfEnvironmental Statement Figure 12 6b Summer Photography Part122 Apr 2024View
Figure 12-6b - Summer Photography_Part2.pdfEnvironmental Statement Figure 12 6b Summer Photography Part222 Apr 2024View
HyGreen_Outline Landscape and Biodiversity Management Plan (OLBMP) FINAL.pdfOutline Landscape And Biodiversity Management Plan (olbmp) Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-A Phase 1 Report - FINAL - Part 3.pdfEnvironmental Statement Volume Ii Appendix 10 A Phase 1 Report Final Part 322 Apr 2024View
HyGreen ES Volume II APPENDIX 10-A Phase 1 Report - FINAL - Part 4.pdfEnvironmental Statement Volume Ii Appendix 10 A Phase 1 Report Final Part 422 Apr 2024View
HyGreen ES Volume II APPENDIX 10-F Water-Vole and Otter - FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 F Water Vole And Otter Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-A Phase 1 Report - FINAL - Part 1.pdfEnvironmental Statement Volume Ii Appendix 10 A Phase 1 Report Final Part 122 Apr 2024View
HyGreen ES Volume II APPENDIX 10-A Phase 1 Report - FINAL - Part 2.pdfEnvironmental Statement Volume Ii Appendix 10 A Phase 1 Report Final Part 222 Apr 2024View
Hygreen ES Report Appendix 21-A Climate Change Risk Register_FINAL.pdfEnvironmental Statement Report Appendix 21 A Climate Change Risk Register Final22 Apr 2024View
Hygreen ES Report Appendix 21-B ICCI_FINAL.pdfEnvironmental Statement Report Appendix 21 B In-combination climate change impact assessment Icci Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 10-B GCN - FINAL.pdfEnvironmental Statement Volume Ii Appendix 10 B GCN Survey Report Final22 Apr 2024View
Hygreen ES Appendix 16-B Operational Noise Information -FINAL.pdfEnvironmental Statement Appendix 16 B Operational Noise Information Final22 Apr 2024View
Hygreen ES Appendix 16-C Baseline Sound Monitoring and Survey Information - FINAL.pdfEnvironmental Statement Appendix 16 C Baseline Sound Monitoring And Survey Information Final22 Apr 2024View
Hygreen ES Appendix 16-A Construction Noise Levels and Assumptions - FINAL.pdfEnvironmental Statement Appendix 16 A Construction Noise Levels And Assumptions Final22 Apr 2024View
HyGreen-Statutory Biodiversity Metric Calculation Tool - Option 1.xlsxStatutory Biodiversity Metric Calculation Tool Option 122 Apr 2024View
HyGreen-Statutory Biodiversity Metric Calculation Tool - Option 3.xlsxStatutory Biodiversity Metric Calculation Tool Option 322 Apr 2024View
HyGreen Hydrogen Project BNG Report_Part1.pdfHydrogen Project Biodiversity Net Gain Report Part 122 Apr 2024View
HyGreen Hydrogen Project BNG Report_Part2.pdfHydrogen Project Biodiversity Net Gain Report Part 222 Apr 2024View
HyGreen Hydrogen Project BNG Report_Part3.pdfHydrogen Project Biodiversity Net Gain Report Part 322 Apr 2024View
HyGreen Hydrogen Project BNG Report_Part4.pdfHydrogen Project Biodiversity Net Gain Report Part 422 Apr 2024View
HyGreen Energy Reduction Statement.pdfEnergy Reduction Statement22 Apr 2024View
HyGreen Arboricultural Impact Assessment_FINAL_Part 2.pdfArboricultural Impact Assessment Final Part 222 Apr 2024View
HyGreen Arboricultural Impact Assessment_FINAL_Part 3.pdfArboricultural Impact Assessment Final Part 322 Apr 2024View
HyGreen Arboricultural Impact Assessment_FINAL_Part 1.pdfArboricultural Impact Assessment Final Part 122 Apr 2024View
HyGreen ES NTS FINAL_Optimized.pdfEnvironmental Statement Non technical summary Final Optimized22 Apr 2024View
HyGreen ES Volume II APPENDIX 12-B Landscape Character FINAL.pdfEnvironmental Statement Volume Ii Appendix 12 B Landscape Character Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 12-C Potential Viewpoints FINAL.pdfEnvironmental Statement Volume Ii Appendix 12 C Potential Viewpoints Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 12-A Landscape and Visual Methodology FINAL.pdfEnvironmental Statement Volume Ii Appendix 12 A Landscape And Visual Methodology Final22 Apr 2024View
HyGreen ES Appendix 2-A Scoping Opinion Responses FINAL.pdfEnvironmental Statement Appendix 2 A Scoping Opinion Responses Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 15-A Air Quality FINAL.pdfEnvironmental Statement Volume Ii Appendix 15 A Air Quality Final22 Apr 2024View
HyGreen ES Volume II APPENDIX 9-A HYGREEN PHASE 1 GEOENVIRONMENTAL DESK STUDY_FINAL.pdfEnvironmental Statement Volume Ii Appendix 9 A Hygreen Phase 1 Geoenvironmental Desk Study Final22 Apr 2024View
Figure 4-4 - Hydrogen Production Process Schematic.pdfEnvironmental Statement Figure 4 4 Hydrogen Production Process Schematic22 Apr 2024View
HyGreen Statement of Community Involvement.pdfStatement Of Community Involvement22 Apr 2024View
Hygreen - Report to inform HRA FINAL_Optimized - 1 of 2.pdfReport To Inform Habitats Regulations Assessement Final Optimized 1 Of 222 Apr 2024View
Hygreen - Report to inform HRA FINAL_Optimized - 2 of 2.pdfReport To Inform Habitats Regulations Assessement Final Optimized 2 Of 222 Apr 2024View
HyGreen ES Volume II Appendices Cover Glossary and TOC.pdfEnvironmental Statement Report Volume Ii Appendices Cover Glossary And Toc22 Apr 2024View
HyGreen ES Volume III Figures Cover and TOC.pdfEnvironmental Statement Report Volume Iii Figures Cover And Toc22 Apr 2024View
HyGreen ES Volume I Cover Glossary and TOC.pdfEnvironmental Statement Report Volume I Cover Glossary And Toc22 Apr 2024View
HyGreen Design Access and Planning Statement.pdfDesign Access And Planning Statement22 Apr 2024View
HyGreen ES Volume II APPENDIX 1-A EIA Scoping Report PART 3.pdfEnvironmental Statement Volume Ii Appendix 1 A EIA Scoping Report Part 322 Apr 2024View
HyGreen ES Volume II APPENDIX 1-B RCBC EIA Scoping Opinion.pdfEnvironmental Statement Volume Ii Appendix 1 B RCBC EIA Scoping Opinion22 Apr 2024View
HyGreen ES Volume II APPENDIX 1-C Statement of Competence.pdfEnvironmental Statement Volume Ii Appendix 1 C Statement Of Competence22 Apr 2024View
HyGreen ES Volume II APPENDIX 1-A EIA Scoping Report PART 1.pdfEnvironmental Statement Volume Ii Appendix 1 A EIA Scoping Report Part 122 Apr 2024View
HyGreen ES Volume II APPENDIX 1-A EIA Scoping Report PART 2.pdfEnvironmental Statement Volume Ii Appendix 1 A EIA Scoping Report Part 222 Apr 2024View
HyGreen ES Appendix 2-A Scoping Opinion Responses.pdfEnvironmental Statement Appendix 2 A Scoping Opinion Responses22 Apr 2024View
HyGreen ES Volume II APPENDIX 8-B WFD Screening and Scoping Assessment.pdfEnvironmental Statement Volume Ii Appendix 8 B Water Framework Directive Assessment22 Apr 2024View
HyGreen ES Volume II APPENDIX 8-C Nutrient Neutrality Screening.pdfEnvironmental Statement Volume Ii Appendix 8 C Nutrient Neutrality Screening22 Apr 2024View
HyGreen ES Volume II APPENDIX 8-D Drainage Strategy Technical Note.pdfEnvironmental Statement Volume Ii Appendix 8 D Drainage Strategy Technical Note22 Apr 2024View
HyGreen ES Volume II APPENDIX 8-A Flood Risk Assessment.pdfEnvironmental Statement Volume Ii Appendix 8 A Flood Risk Assessment22 Apr 2024View
ANNEX B Envirocheck 285342089 Landmark 2021 - Part 3.pdfEnvironmental Statement Annex B Envirocheck 285342089 Landmark 2021 Part 322 Apr 2024View
ANNEX B GSIP-2022-13154-11993_smallScale Groundsure 2022c - Part 2.pdfEnvironmental Statement Annex B Gsip 2022 13154 11993 Smallscale Groundsure 2022c Part 222 Apr 2024View
ANNEX B GSIP-2022-13154-11993_smallScale Groundsure 2022c - Part 3.pdfEnvironmental Statement Annex B Gsip 2022 13154 11993 Smallscale Groundsure 2022c Part 322 Apr 2024View
ANNEX B GSIP-2022-13154-11993_smallScale Groundsure 2022c - Part 4.pdfEnvironmental Statement Annex B Gsip 2022 13154 11993 Smallscale Groundsure 2022c Part 422 Apr 2024View
ANNEX B GSIP-2023-13293-12624_E_1 Groundsure 2023.pdfEnvironmental Statement Annex B Gsip 2023 13293 12624 E 1 Groundsure 202322 Apr 2024View
ANNEX B 60559231_CTR05-002_EC_Index Landmark 2020.pdfEnvironmental Statement Annex B 60559231 Ctr05 002 Ec Index Landmark 202022 Apr 2024View
HyGreen ES Volume II APPENDIX 9-A HYGREEN PHASE 1 GEOENVIRONMENTAL DESK STUDY.pdfEnvironmental Statement Volume Ii Appendix 9 A Hygreen Phase 1 Geoenvironmental Desk Study22 Apr 2024View
ANNEX B GSIP-2022-13154-11993_smallScale Groundsure 2022c - Part 1.pdfEnvironmental Statement Annex B Gsip 2022 13154 11993 Smallscale Groundsure 2022c Part 122 Apr 2024View
ANNEX B GS-9167786_smallScale Groundsure 2022b and 2022d.pdfEnvironmental Statement Annex B Gs 9167786 Smallscale Groundsure 2022b And 2022d22 Apr 2024View
ANNEX B GS-9167761_smallScale Groundsure 2022a.pdfEnvironmental Statement Annex B Gs 9167761 Smallscale Groundsure 2022a22 Apr 2024View
ANNEX B Envirocheck 285342089 Landmark 2021 Part 1.pdfEnvironmental Statement Annex B Envirocheck 285342089 Landmark 2021 Part 122 Apr 2024View
ANNEX B Envirocheck 285342089 Landmark 2021 - Part 2.pdfEnvironmental Statement Annex B Envirocheck 285342089 Landmark 2021 Part 222 Apr 2024View
Figure 11-2_Wetland Bird Count Sectors.pdfEnvironmental Statement Figure 11 2 Wetland Bird Count Sectors22 Apr 2024View
Figure 11-3_Hygreen breeding bird survey areas.pdfEnvironmental Statement Figure 11 3 Hygreen Breeding Bird Survey Areas22 Apr 2024View
Figure 11-1_Study Areas.pdfEnvironmental Statement Figure 11 1 Study Areas22 Apr 2024View
Figure 11-4_NZT Breeding Bird Survey Areas.pdfEnvironmental Statement Figure 11 4 Net zero Teesside Breeding Bird Survey Areas22 Apr 2024View
Figure 11-5_Statutory Designated Sites.pdfEnvironmental Statement Figure 11 5 Statutory Designated Sites22 Apr 2024View
Figure 11-6_Non-statutory Designated Sites.pdfEnvironmental Statement Figure 11 6 Non Statutory Designated Sites22 Apr 2024View
Appendix 14-B CTMP.pdfEnvironmental Statement Appendix 14 B Construction Worker Travel Plan22 Apr 2024View
Appendix 14-C CWTP.pdfEnvironmental Statement Appendix 14 C Construction Worker Travel Plan22 Apr 2024View
Appendix 14-A Transport Assessment.pdfEnvironmental Statement Appendix 14 A Transport Assessment22 Apr 2024View
HyGreen ES Volume II APPENDIX 15-A Air Quality.pdfEnvironmental Statement Volume Ii Appendix 15 A Air Quality22 Apr 2024View
Hygreen ES Volume II Appendix 18-B Hazardous Substances Consent Flowchart.pdfEnvironmental Statement Volume Ii Appendix 18 B Hazardous Substances Consent Flowchart22 Apr 2024View
Hygreen ES Volume II Appendix 18-C COMAH Flowchart.pdfEnvironmental Statement Volume Ii Appendix 18 C Comah Flowchart22 Apr 2024View
HyGreen ES Volume II APPENDIX 18-A Major Accidents and Disasters.pdfEnvironmental Statement Volume Ii Appendix 18 A Major Accidents And Disasters22 Apr 2024View
HyGreen ES Volume II APPENDIX 22C_Shortlist.pdfEnvironmental Statement Volume Ii Appendix 22c Shortlist22 Apr 2024View
HyGreen ES Volume II APPENDIX 22-D_ASSESSMENT OF CUMULATIVE EFFECTS.pdfEnvironmental Statement Volume Ii Appendix 22 D Assessment Of Cumulative Effects22 Apr 2024View
HyGreen ES Volume II APPENDIX 22A_Long list.pdfEnvironmental Statement Volume Ii Appendix 22a Long List22 Apr 2024View
HyGreen ES Volume II APPENDIX 22B_ Cumulative Assessment Stages 1-3.pdfEnvironmental Statement Volume Ii Appendix 22b Cumulative Assessment Stages 1 322 Apr 2024View
HyGreen - 415000-00414 -PL-DAG-00004-001 Pipeline Network and Routing 20 sheets _Part1.pdfPipeline Network And Routing 20 Sheets Part122 Apr 2024View
HyGreen - 415000-00414 -PL-DAG-00004-001 Pipeline Network and Routing 20 sheets _Part2.pdfPipeline Network And Routing 20 Sheets Part222 Apr 2024View
HyGreen - 415000-00414 -PL-DAG-00004-001 Pipeline Network and Routing 20 sheets _Part3.pdfPipeline Network And Routing 20 Sheets Part322 Apr 2024View
HyGreen ES APPENDIX 11-A baseline appendix_Ornithology REDACTED_Optimized (2).pdfEnvironmental Statement Report - Appendix 11A Ornithology Redacted Amended 3.05.20243 May 2024View
HyGreen_Additional Ecology Information_Memo_Final for Issue.pdfAdditional Ecology Information Memo Final For Issue14 Oct 2024View
Supporting Information in response to Natural England consultation.pdfSupporting Information In Response To Natural England Consultation17 Feb 2025View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

WITHDRAWN
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.