Council planning record

DISCHARGE OF CONDITION 10 (CEMP) FOR STAGE TCPA 6 OF PLANNING PERMISSION R/2020/0355/FFM FOR THE INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ...

LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CABLE CORRIDOR, FROM THE DOGGER BANK C ONSHORE CONVERTER STATION, SOUTH OF WILTON INTERNATIONAL, UP TO LACKENBY NATIONAL GRID SUBSTATION

ApprovedReference: R/2022/0847/CDRedcar and Cleveland Borough Council

Last published check: 23 Oct 2026, 09:53. Check the council record for more recent changes.

Application timeline

Council milestones and published deadlines. A deadline passing does not confirm a decision.

  1. Date Received

    Published milestoneCouncil source
  2. Date Valid

    Published milestoneCouncil source
  3. Decision Date

    Published milestoneCouncil source

Application summary

Status
Approved
Application type
Condition Discharge
Received
24 Oct 2022
Validated
24 Oct 2022
Determination deadline
Not published
Local authority
Redcar and Cleveland Borough Council

Application overview

DISCHARGE OF CONDITION 10 (CEMP) FOR STAGE TCPA 6 OF PLANNING PERMISSION R/2020/0355/FFM FOR THE INSTALLATION OF UNDERGROUND HIGH VOLTAGE ELECTRICAL CABLES AND ANCILLARY WORKS WITHIN FIVE AREAS TO CONNECT EXISTING APPROVED DOGGER BANK C AND SOFIA WIND OFFSHORE WIND FARMS AND LACKENBY SUBSTATION AND ...

Proposal details

Reference
R/2022/0847/CD
Agent
ROYAL HASKONING D H V

Sign in to view all collected council fields and recorded changes.

Sign in to view collected details

Application location

LAND ALONG THE DOGGER BANK C OFFSHORE WIND FARM CABLE CORRIDOR, FROM THE DOGGER BANK C ONSHORE CONVERTER STATION, SOUTH OF WILTON INTERNATIONAL, UP TO LACKENBY NATIONAL GRID SUBSTATION

This record has no verified map location.

Documents 12 of 12

DocumentPublishedAction
ApplicationFormRedacted.pdfApplication Form25 Oct 2022View
0847 PROW.pdfConsultee response - Public Rights of Way27 Oct 2022View
NWL 0847.pdfConsultee response - Northumbrian Water31 Oct 2022View
EP NU.pdfConsultee response - Environmental Protection (Nuisance)3 Nov 2022View
LLFA comments.pdfConsultee response - Engineers (Local Lead Flood Authority)8 Nov 2022View
NATURAL ENGLAND.pdfConsultee response - Natural England15 Nov 2022View
0847.pdfConsultee response - Engineering Team (Highways)29 Nov 2022View
Decision Notice(1).pdfDecision Notice1 Dec 2022View
0847(1).pdfOfficer Report1 Dec 2022View
Cover Letter.pdfCovering Letter CEMP Stage TCPA 625 Oct 2022View
DBC OWF LF700013-CST-DOG-REP-0086 Construction Environmental Management Plan DCO Stage 12.pdfCondition 10 - Construction Environmental Management Plan DCO Stage 1225 Oct 2022View
Decision Notice.pdfR 2020 0355 FFM Decision Notice25 Oct 2022View

Documents open on the council website. Browse council documents if a link has changed.

Decision & conditions

CONDITION DISCHARGE GRANTED
Decision Notice(1).pdf Decision Notice.pdf
Planning conditions

Conditions aren’t listed here. Read the council decision notice for the full decision and conditions.

Related records

Related records could not be loaded.

Understand this planning record

All planning guides
  • Understanding planning · 13 min read

    Planning application documents: what to read first

    Understand planning application documents, officer reports and decision notices. Use a reading checklist, document table and worked example to inspect a case.

  • Understanding planning · 13 min read

    Planning application statuses explained

    Understand pending consideration, approved, refused and withdrawn planning applications. Compare status labels and find the documents explaining each outcome.

  • Understanding planning · 13 min read

    Planning permission drawings: how to read plans

    Read planning drawings, floor plans, elevations and sections. Use labelled diagrams, a drawing comparison table and revision checks to understand a proposal.